Equipment cost in PM module

Dear all,
Is it possible to maintain the cost of equipment, if yes the in which t code i can see it.(i don't want from the FI or CO module) i want to see it in PM module. Is it possible?

Hi,
You can maintain the cost of equipment value in Field  "AcquistnValue"  In General Tab Using TC IE01 while creation of equipment or IE02 while changing of equipment.
Then you can execute the report according Cost of equipment="AcquistnValue"  using TC IH08
Regards,
Rakesh
Edited by: RAKESH ASHOK MANE on May 13, 2009 7:11 AM

Similar Messages

  • Cost elements for labour cost and equipment cost

    how to know  the cost elements maintained for labour csot and Equipment cost in our project ??is there any table or details please letme know
    thanks inadvance
    gopal

    Gopal,
    Use the following T code:
    KA03 and specify the GL Account, If cost element already  created it will display.
    Regards,
    Pavan Kumar

  • Roll up sub equipment cost to Superior Equipment

    Hello,
    Is there a way to see sub equipment cost to the superior equipment.
    We have a pump (superior) then under that we have motor (sub) and elec (sub). Is there a way to see the total cost of the two subs in the superior.
    Thanks.

    Another work-around is to get your list of equipment, say from IE05.
    Then paste the equipment into IW39 to get your costs
    PeteA

  • Capture equipment cost in project

    Dear All,
    need to capture the cost of equipment which uses for project,but problem is that they take equipment from stock & uses for project work & keep it back in stock after use,
    How we can capture this cost in project?
    please help me out.
    Regards
    Gajjen

    Hi,
    If you are only using some tools for which requires simple functionalities, they can be defined as PRT's. In case they need to be treated as Assets with depreciation functionality, maintenance functionality as equipments ans so on, then treating them as equipments would me more appropriate. There is one more module in SAP called ETM which has enhanced functionality over PM in handling of equipments.
    Usage depends on your requirement. Consult other modules too before deciding.
    Regards,
    Arul.

  • PM - Report - Equipment - Cost Details

    Hi,
    As per my the requirements i need to create a report for reporting on Equipment ID and the various key figures like Total Costs, Number of orders created till date, MTTR/MTBR etc in PM in one single repoort.
    I am able to get the Cost based on Orders but not based on Equipments. Please help on getting the cost based on Equipment ID.
    Thanks and regards,
    Ankur

    Hi,
    You can maintain the cost of equipment value in Field  "AcquistnValue"  In General Tab Using TC IE01 while creation of equipment or IE02 while changing of equipment.
    Then you can execute the report according Cost of equipment="AcquistnValue"  using TC IH08
    Regards,
    Rakesh
    Edited by: RAKESH ASHOK MANE on May 13, 2009 7:11 AM

  • Creating new equipment category in PM Module

    hi guru's
    can i create new equipment category in  plant maintenance module
    plz specify the tcode.
    its very urgent
    if helpful, person will be rewarded

    Hi Gurbir,
    The T.Code is 'SPRO'
    path in customization is,
    IMG --> Plant Maintenance and Customer Serivce --> Master Data in Plant Maintenance and Customer Service --> Technical Objects --> Equipment --> Equipment Categories --> Maintain Equiment Category
    Regards,
    Prabhakar

  • Profit Center to be picked from Equipment Cost center in Maintenance Order

    Hi All
    We are not maintianing any costcenter in work center and only maintaning the cost center in equipment master.
    So when i create the maintenance order, profit center is not picked up in Additional Data Tab from Cost center maintained in equipment master.
    Please  provide your valuable sugesstions.
    Regards
    Praveen

    Hi,
    The profit center is derived from the cost center of the responsible work center when the order is first created. If a cost center is not available then I expect the profit center cannot be automatically filled on the order. The user can manually enter a value.
    The exit IWO10005 is frequently used to determine the profit center. You may want to look at implementing some custom logic there.
    -Paul

  • Update Equipment BOM using Function module (very urgent)

    Hi All,
    I am an ABAPER and trying to update equipemnt BOM.
    I want to update equipment BOM using a function module. I am currently using 'CSAI_BOM_MAINTAIN' function module. But i am not able to update the Equipment BOM. After function call the sy-subrc value is 0, even though the BOM is not updated.
    Please help its very urgent.
    Kind Regards,
    Sharat.

    Hi Sharat,
    I am facing the same problem. Could you please let me know what might be the reason.
    Plz mail me at [email protected]
    Plz update this section once u have mailed the answer.
    Thanks a lot in advance.
    Regards,
    Himanshu

  • Adjusting Dealer cost in sales module

    Hi
    During every sales order my client pays some commision to dealer.So he wants to keep track in sales order to sales invoice.In this track he enters the commision of the dealer saperatly order wise.
    On saving the invoice amount should be paid to dealer as this amount does not belong to client it should go in account of dealer.
    So suggest me how can i do this in system for proper results?
    Thanks
    Edited by: Pari Minhas on Apr 9, 2009 10:06 AM

    Nagababu,
    I think you would need to create a Query based Report and then create a Query PLD.
    Let me know if you need directions.
    Suda

  • Equipment is common for both the plants.How to differentiate the cost seperatly

    Hi Guys,
    Maintenance plants are Ex:2076 and 2023 and planning is done by 2076 for both the plants.Equipments is unique for both the plants.
    Suppose for example i have a equipment installed in 2023 and i will have the cost center of 2023 plant.When i create the order How can i differentiate the cost for both the plants.Manually i have to change the cost center in settlement rule.
    Regards
    Kumar

    Hi Maheswaran,
    I have maintain the values in Z- table like Equipment,Cost Center and  percentage.
    and also for reporting purpose in equipment location field :COMM is created.
    When the development is done iam getting the below mesage when i try to REL the order.
    "Enter a valid value for the settlement type".
    I need to maintain any other values.
    Regards
    Kumar

  • Best Practices to implement PM module in BI 7

    Hello Guys, how are you.
    I need your help to find the documentation of the Building Blocks to configure PM modelue in BI 7.
    I acces the following pages, but i cannot find where the building blocks for this module are.
    http://help.sap.com/saphelp_nw2004s/helpdata/en/f6/7a0c3c40787431e10000000a114084/frameset.htm
    http://help.sap.com/bp_biv370/html/Bw.htm
    The last link contains the documentation to implement somo modules like SD, MM, PP, FI, and you can access the configuration guide of this modules, but i need to find out the documents for PM (Plant Maintenance) module in order to know the correct steps to initialice the tables in R/3, the extractors to use and the cubes.
    Thanks for your help guys.

    Hi,
    You have a good start.  What you need to do is 1.) Find out what the requirements are -- what does your user want.... if this is a fact finding mission (e.g., they want to see what's in the system) then your requirement becomes load the data in R/3, so figure out what they configured in PM and use those definitions as your requirements.   2.) Use those requirements to find data in the fields listed in the MultiProvider, InfoCubes, or DataStore Objects sections in your first link ... in other words, now that you know what data to look for, look for it in the Data Targets (MP's, Cubes and DSO's).  If you find some of the data you want, then trace back the infosources and determine what datasources in R/3 load the data you are looking for.  After all that, check those datasources for any additional fields you may need and add them in.
    So, if your company doesn't maintain equipment costs or maintenance costs for equipment, then you don't have to worry about 0PM_MP04.  Use this type of logic to whittle down to what your really need and want, then activate those object only.
    Good Luck,
    Brian

  • Posting settled internal order costs to PM Order

    Hi,
    Our client doesn't have PM module upto now. So they posted all the maintenance costs to internal orders. All the internal orders are settled properly. Now they want to implement PM module. They want the costs previously posted in internal order should be reflected in PM orders.
    How it will possible?  Any inputs please.. is the historical PM order helps???
    Regards
    Radha

    Radha,
    Technically speaking, yes its possible.
    But do you know which costs were booked against each equipment?
    Even if you do, then you will need to write an ABAP program to create PM orders and then move the costs from the settlement orders to the PM orders in the period thatg they were accrued. This is a big job.
    If you only need a record of the equipment costs (ie not move the actual costs) then the simpler approach would be to use Historical Orders.
    PeteA

  • Repair of equipment

    We have the following scenario.
    Some equipment or component of equipment, which are defined as equipment master in PM module are to be sent out for repair.
    What should be the procedure adopted?
    What we are planning is to create a material master for this item to be sent out and upload the stock with 561 movement.
    Is it the correct way of doing or can we get stock from PM module directly.
    We need to have a print of material document for sending the material outfrom the company
    However there is no excise involved in our company
    CAn anybody explain the correct procedure to be followed?

    Follow below procedure;
    1. MM01 - Create Equipment as a Material for e.g. "M1"(Valuated OR Non-valuated, depends on requirement)
    2. MIGO - Goods Receipt > Others (Using Movement Type "202" i.e. Receipt from Material "M1" against Cost Center, do not use 561)
    3. ME21N - Create Subcontracting PO for Material "M1", use Item categroy "L" in PO, use component as "M1" only
    4. MIGO/MB1B - Transfer Posting of Material "M1" to Vendor using Movement Type "541" (Activate Print settings for this Material Doc and take print from MB90)
    5. MB90 - Print Transfer Posting Material Doc
    6. MIGO - Goods Receipt against Subcontracting PO through Movement Type "101' (Here Stock of M1 will get consumed through "543" from vendor stock and get received through "101" in unrestricted stock)
    7. MIRO - Invoice Verification for Servcie charges

  • Overall equipment efficency ..functional and technical

    Hi
    friends
    doing a module pool for overall equipment effiency
    as iam new in p.m module i need some functional help.
    but have to create a z tables for it .
    my criteria is
    <b>header --</b>equipment
    cost center
    plant
    functional location
    <b>detail table</b>.
    equipment
    from date
    from time
    to dta
    to time
    operations--production,
                maintaince
                ideal
    batch
    material
    reasons
    Planned production quantity
    equipment
    month/hours
    god hrs
    planned production hrs
    reason no
    reason code
    std hrs/min.
    have to create table but iam stuck in normaliazation what should be
    keys on and indexes on as there is no functional guy avalab1e here
    i have to do it and this module pool should allow to modify delete
    and change that can be done but ..on one screen this 2 table control
    i have to display .
    so pls give the suggestion for  functional and technical
    regards
    answers will be awarded points

    Hi,
    See the Views  VIAUFKS and VIAUF_AFVC ,
    you will get all the fields related to PM module
    See the fields and the data elemetns and create the tables and use them in the Table controls and design your screens and the code.
    see the info on Table controls:
    syntax:
    CONTROLS .
    if you only want to determine the row of the table control. SY´-SUBRC allows you to check if the cursor is placed in a row of a table control.
    u need to comment the performs of table control fields and write ur own perform statements. And u have to declare the table control fields as separate internal tables.
    Go through this urls.
    www.****************
    www.sap-img.com
    Check the below links.
    http://www.planetsap.com/howdo_a.htm
    http://help.sap.com/saphelp_nw2004s/helpdata/en/9f/dbac5135c111d1829f0000e829fbfe/content.htm
    http://sap.niraj.tripod.com/id25.html
    reward if useful
    regards,
    ANJI

  • Issued quantity to Equipment wise in one screen

    Hi,
    Can anyone solve the following issue....
    We have topped up diesel for 15-20 different Heavy earthmoving machineries  work at mines site,   In order to close monitor we have to enter the topped up quantity in each machines individually.
    Now we are issuing the diesel to cost centre as a issued quanty from store, not inidivual equipment.
    In PM module/store, if any screen available as enter the issued quantity to equipment wise in one screen  is convinenet .Kindly request to give any T code to enter on equpment wise for the diesel topped up individually.
    Regards,
    Aritra

    Hi Mukherjee,
    Point1: If you are issuing the material to Cost center from store ther is not linkage with the equipment master. Try to issue to Maintenance order.
    You will get the reservation and withdrawn qty from T code IW13.
    Point 2: For capturing the diesel amoount topped up for the equipment.
    Create Measuring point with respect to the equipment using T Code - IK01
    Enter the Topped up amount in with ref to measuring point at T code IK11
    You can see the report with respect to equipment from T code IK17
    Regards
    DPS

Maybe you are looking for