Excise Duties in subcontracting challan
Dear Friends
I am creating subcontracting challan57f4 in ref to material transfer document.MY query is, should duties also appear while creating subcontracting challan i my case this is not happening.
Can anybody help me on this issue
Regards
VIvek
Hi,
The excise duties should not appear in the Sub-Contracting challan. Because, you are creating the excise challan for sending the excisable material outside to your sub-contractor for processing without payment of duties. Hence it is the right thing that excise duties are not appearing in your challan.
Regards,
Prashant Kolhatkar
Similar Messages
-
Excise Group in subcontracting challan
hi experts
while creating subcontracting challan nothing displayed in Excise Group
can u anybody explain how make excise group for singapore
thanks
ganeshHi,
First ensure following;
Configuration: -
- Go to SPRO > Logistics - General > Tax on Goods Movements > India > Account Determination > Specify Excise Accounts per Excise Transaction > Here maintain as following;
ETT Subtrn Typ DC ind Acct name
57FC CR PLABED
57FC CR RG23BED
57FC CR RG23ECS
57FC DR CLEAR
57FC 01 CR PLABED
57FC 01 CR RG23AT1
57FC 01 CR RG23BED
57FC 01 CR RG23ECS
57FC 01 DR CLEAR
57NR CR CLEAR
57NR CR PLABED
57NR CR RG23BED
57NR CR RG23ECS
57NR DR REVERS
57NR 01 CR CLEAR
57NR 01 CR PLABED
57NR 01 CR RG23BED
57NR 01 CR RG23ECS
57NR 01 DR REVERS
- And then go to SPRO > Logistics - General > Tax on Goods Movements > India > Account Determination > Specify G/L Accounts per Excise Transaction > Here do Account Determination for the above combination and Excise Group
Apart from above also do following configuration for Subcontracting;
- SPRO > Logistics - General > Tax on Goods Movements > India > Business Transactions > Subcontracting > Subcontracting Attributes
Here maintain following;
Excise Group XX
Excise TT 57FC
Subtransaction Type 01
Subtran Type Text 57FC CHALLAN
Subc. Period 180
Rate-subcontracting
Mvt Grp Issues 0001
Mvt Grp Receipt 0002
Filter Non exise
EI Items 10
No. range no. 01
***. Val. /Exc Inv
Subcon Output Type J1IF
- SPRO > Logistics - General > Tax on Goods Movements > India > Business Transactions > Subcontracting > Maintain Movement Type Groups
Here maintain following
MVT. Grp. MvT S
0001 101 O
0001 541 O
0002 542
0002 542 O
0002 543 O
- J1I9 - maintain No range for object "J_1I57FC" for series group
Then follow the below process;
Subcontracting without Payment of Duty
- Creation of Subcontracting PO (ME21N)
- Transfer Posting of Components to Subcontractor (Mvmt Type - 541) (MB1B/ME2O/MIGO)
- Creation of Subcontracting Challan w.r.t. Transfer Posting Doc (J1IF01)
- Goods Receipt w.r.t. Subcontracting PO and Refer Subcontracting Challan at the time of GR (MIGO) {GR with 101 and autoconsumption of components with 543 movement}
- Reconciliation of Subcontracting Challan (J1IFQ)
- Completion of Subcontracting Challan (J1IF13)
- Generation of Annexure IV (J1IFR)
Master Data
- MM01- Material Masters for Components and FG
- XK01 - Vendor Master (Subcontractor)
- CS01 - BOM for FG
- ME11 - Purchase Inforecord for Subcontracting -
Subcontracting challan reverse since 180 days passed
HI
Error is Cannot reconcile crossed return date,please reverse
Scenario is such
Material is received MIGO is done after process now they want to create J1IFQ here the problem exists ,
kindly help how to sort out the problem.Reverse the excise duties in J1IF13.
Then do the reconciliation in J1IFQ
After that recredit the excise duties & complete the challan in J1IF1
3
Maintain the accounts for Excise TT-57N
Regards,
SATPAL -
Excise Invoice Selection Vs assessable value in Subcontracting Challan
Hi,
I have maintained the Assessable Value for my subcontracting components and also there is Excise Invoice exists for this components. While creating Subcontracting challan, system is displaying information message that Material XXXXXX has an assessable value, but I would like to refer the Excise Invoice.
Hence, when I click the Excise Invoice selection, there is no effect. As per SAP message "The message is for information purpose only. Go ahead with the option selected" system should ignore this message and allow me to select Excise Invoices but it is not happening.
Is this bug or any other config setting to be done to overcome this issue?.
Your replies to resolve this issue is highly appreciated.
Thanks,
Babu.Hi,
For every excisable material (whether you procure, manufacture or sale) has to be declared as excisable material in table J1ID with appropriate chapter ID, assessable value & CENVAT declaration.
When you send the excisable material to the sub-contractor the material needs to be returned back to your plant within 180 days. If this is not done, then you will have to pay back the excise duty on the material with base value as assessable value. Hence it is required to maintain the assessable value.
Hope this clears your query.
Regards,
Prashant -
EXCISE SUBCONTRACTING CHALLAN REVERSAL
Hi!
we are using TAXINN in ECC5.0. we are creating subcontracting challan after maintianing assessable value and excise rates 16% BED, 2% ECS and 1% SEC ECS for the chapter id. When we are trying to reverse the subcontracting challan, the duty values are not calculated in the challan. we have also maintained excise indicator for the vendor and also excise details.
Can anybody help us out?
Thanking you in advance
GaneshHi,
against which document you are reversing it 541 0r 542 material document check following link
[Subcontract Challan;
[http://help.sap.com/saphelp_470/helpdata/ru/1c/d6a1d82b5611d4ae1700105a16d13d/content.htm]
Regards
kailas Ugale -
Excise treatment during subcontracting process with excise duty
Dear all,
Iam aware of the subcontracting process STEPS, but my query is while dealing with Excise in Subcontracting process, will the Excise duties captured in J1IS(create outgoing excise invoice) be RECONCILED with excise duties captured in J1IEX(subcontractor's excise invoice). As per my scenario both the duties are different unlike reconciliation process in the process without excise duty. My questions are
1.Do both excise duties during j1is and j1iex should be same or can it be different (since in j1is we capture Duties on raw material's assesable value where as in j1iex we capture duties semi finished goods given by sub contractor.)
2.Kindly eloborate treatment of excise duties captured in these steps.
Revert if you didnt understand this scenarion.
Regards,
Sravanthi.YHi,
57fc challan will be issued when we send raw materials to subcontractors WITHOUT EXISE DUTY.Hence not relevant in my case. But my case is WITH excise duty.we send subcontractor the excise invoice by using j1is. later he will process these raw materials and will give back the semi finished goods along with excise invoice(which we will capture n post using j1iex). so my question will excise duties differ in j1is(excise invoice TO subcontractor) and in j1iex(excise duty FROM subcontractor)? -
Reversal of the subcontracting Challan
I have the following doubts:
1) Does the system automatically debits the modvat accounts in case the material is not sent by the subcontractor within 180 days. Do I need to enter the amounts in "Utilization Tab"? In the subcontracting challan the duties are shown as calculated on the posting data tab. In the utilization tab the entry for
RG23A BED
RG23A SED
RG23A AED
RG23A NCD
is editable.
The header is like this
Balance for utilization Modvat Debit
RG23A BED 0.00
RG23A SED 0.00
RG23A AED 0.00 Total
PLA BED 0.00 0.00 BED 0.00
PLA SED 0.00 0.00 AED 0.00
PLA AED 0.00 0.00 SED 0.00
RG23A NCD 0.00 NCCD 0.00
Do I need to enter the values in the utilization tab to debit the modvat accounts or it will be debited as per the entries in "Posting Tab"
2) When does the report J1IFR shows the challan under "Recredit Due" ?
Please help for these 2 questions I have gone through the other posts related to this topic but unable to understand the transactions for reversal/ recreditHi,
1) Does the system automatically debits the modvat accounts in case the material is not sent by the subcontractor within 180 days. Do I need to enter the amounts in "Utilization Tab"? In the subcontracting challan the duties are shown as calculated on the posting data tab. In the utilization tab the entry for
If you send exciable material to subcontractor vendor and you not get your material in 180 days then what happen check following
1) why 180 days first because as per Indian law your excise invoice valid for 180 days to take credit after that you can not take credit
2) when 180 days complete ,then it consider as you sale your material to vendor and you have to create sale invoice along with excise invoice and send to vendor ,system will not do automatically.
3) while doing utilization you can not edit sales value or MM value also ,once outgoing excise invoice d yo subcontractor it will come automatically in utilization.
Regards
Kailas Ugale -
Subcontracting challan reconcilation & re credit
Hi,
Please suggest me about Subcontracting challan reconcilation & re credit in case material is recieved after 180 days. how challan is handled & regarding credit what needs to be done.
We can reverse challan & reconcile using j1ifq but what steps to be followed in case of paying excise amount.Hi,
follow following steps-
1.TCode-j1if13.-Complete/Reversal/Recredit- Reverse challan.
All duties will get reversed.
2.TCode-j1if13.-Complete/Reversal/Recredit- Recredit challan.
All duties will get recredited.
3.Create GR for the purchase order and provide the reference of Challan created.
4.Reconcile and Complete the Challan
5.Check RG23A part 2 entries for transaction type 57NR and 57RC in table J_1IPart2
6.Extract RG23A Part 2 register and download the entries in excel through J2I6
regards -
Error While creating Subcontracting challan in J1IF01
Hi,
While creating Subcontracting challan in J1IF01Im getting error " Deficit of 3.2000000000000002E+00 in RG23ABED".
Any suggestion in this regard is very helpful.
durga
[email protected]Hi,
You are referring the material challan, which is not posted for Sub-Contracting PO. Pl. check your Material document number. Also pl. check that plant is same in material document & s/c Challan.
Excise values are not appearing in the S/C Excise Challan, because you are sending the excisable material to your sub-contractor without paying any excise duty. When you reverse & recredit the S/C Challan, it will show the Excise Amounts.
Regards,
Prashant Kolhatkar -
MIGO Error -while refering the subcontracting challan
Hi all
1.)We purchsed material from vendor A & send these material to vendor B directly for Job work ( for this we have seperate PO with subcontractor)
2.) In Material PO we tick SC vendor & give vendor B.
3.) Then made GR(with only part 1)
4.) MMBE report shows stock provide to vendor B.
5.) After that we made subcontracting challan for vendor B with reference to GR number.
6.)Then capture and post the Excise invoice no
7.) Now when I am trying to the GRN of subcontracting PO and refering the subcontracting challan , system is throwing an error " Challan material is different from material document "
Usualy in the normal scenario, while doing the 541 movement type , we use to refer the subcon PO(by making the PO no field mandatory/optional against the movement type 541 in customization ) , as during MIGO, system checks the PO no against the material issued and PO against the GRN is being done, if it does't matches, then the above error comes.
But in the above scenario, there is no way to give the reference of giving the subcon PO during 101 "o" . that is why , this error is coming.
Please suggest the way out , how to deal this scenario.
Thanks & Regards
Nitin Chhabrahi nitin
pls refer following link
Re: SUBCONTRACT J1IFQ ERROR
Vipin -
MIGO with reference to Subcontracting challan
Dear Friends,
I have a couple of questions which u may be able to solve:-
1. In a MIGO for a subcontracting PO, i can select the option Refer subcontracting challan in the excise invoice tab. I wanted to know the purpose of this functionality. If i refer the subcontracting challan in the MIGO does it mean I dont have to reconcile the challan after MIGO.
2. When I refer the subcontracting challan in the GR and enter the challan no and year the system throws an error which says - Challan material is different from material document. i have checked the material document for the transfer posting made. But the material is the same in all the cases and flows from the PO itself. please help me out with this error.
Regards
Gurvinderfor point 2 do this
In spro --> taxon goods movemnt > indiac> business transaction --> subcontrcating --> maintain movement type grp
here miantain
0001 101 O
0001 122
0001 541
0001 544 O
0002 542
0002 543 O
Edited by: Kedar Kulkarni on Jan 27, 2010 7:53 PM
Edited by: Kedar Kulkarni on Jan 27, 2010 8:21 PM
Edited by: Kedar Kulkarni on Jan 27, 2010 8:26 PM -
Issue in Subcontract Challan Creation
Dear All,
We just started subcontractor challan process in sap for tracking the material supplied to vendor and finding the stock which will be laying at more than 180 days at vendor end.
The issue we found is while creating subcontract challan excise group and other details not stored, since we are doing testing and it would be resolve before implementing.
Regards,
MaliniHi,
Please do the necessary settings if customization is missing then you need to do it. If your asking how to making the settings please sit with FICO consultant and Client Discuss it and come with your questions
Hope it is clear
Shiva
http://scn.sap.com/thread/1950603 -
Creation of subcontracting challan
Hi all,
I have done all the required customization settings,,,
procedure i followed is:
1. created two raw materials with material type ROH, - materials R1, R2
cretated a semifinished material with material type HALB- material S1
2.created a BOM for semifinished material S1 and assigned materials R1, R2 as components.
3. Created a PO with item category 'L', material S1, quantity 1, exploded BOM for assigning rawmaterials R1, R2.
4. Accessed t_code MB1B- movement type 541, with reference to purchase order for providing material to vendor.
5. Now I run t_code J1IF01 for creating subcontracting challan,,, there i had given material document, year, excise group, service group and executed the t_code,
and all the required fields in the transaction were filled and saved.
so finally system giving me this message:
Document 2007 10 created
problem is ,,, its not creating a number for subcontracting challan,,,
i had filled up all the excise data for the material,,,
someone can me help me out in this issue,urgent.
regards,
urendraHi Prasanna,
I had checked these number ranges viz. J_1IINTNUM, J_1IRG23A1,J_1IRG23A2, J_1I57FC all were maintained correctly,
System creating the subcontracting challan,, but it is not picking up the number range, I have selected the print immediately option and got the print with no subcontracting challan number...
as soon as I saved the Subcontracting challan, system gives this message
Document 2007, 50 created,,, here 2007 is the fiscal year, and 50 is the series group.
checked all the excise registers, excise group, material chapter id combination,,, everythings is ok,, kindly help me out in this issue.
regards,
urendra
[email protected] -
Referance of subcontracting challan at time of GR
Hi Experts ,
i m not getting excise tab for refering subcontracting challan
Receiving material is semifinish material - all details r maintained in j1id
child material is raw material -all details maintained in jild
j1id details r -
plant -chap combination , cenvat determination , accessible value for both material
in cenvat dete input raw and output semifinish maintained
All Cin -subcontracting config is also done - subcontracting attributes in bussiness transactions and movement type groups r maintained
Now problem is that if i maintain Receiving material ( which is semifinish ) as RAw material in J1id(chapid-material combination ) then only i m getting excise tab in which there is refering subcontracting challan option available ..................but if i maintain Semifinish material as a RG1 in J1id then i dont get excise tab ............it is wrong ............how i can maintain semifinish material as a raw in J1id .it will create problem
so my requirement is although if i m maintaining semifinish material as a RG1 in J1id Which is i m going to receive from subcontractor , subcontracting tab should appear while making GR . Then only i will be able to reconsile the challan after making GR .
Please help me
Regards
ChandanPlease use the exit to define the way you want the system to consider Scrap in the subcontracting process.
1084323 USER-EXIT to update challan status if scrap is calculated
1103537 Correction to note 1084323 for ECC 600 Release
Please note the user exit will be accessed only if you were to write a code for it and you assigned/made 545 O as relevant to subcontracting
subcontracting scrap will work if the scrap percentage is defined for the component which is sent to the job worker. If you have a completely new material for scrap then this is not going to work as the system will never be able to assign the qty (mismatch of material code between the scrap material & the challan material). -
Standard O/P Type for Subcontract Challan PO
Hi,
For Subcontract Challan print out we have a made a seperate transaction code , but i want to know which is the std. o/p type for Taking the print out of Subcontract challan, like for po NEU is there , so which is the o/p type is for taing the subcontarct challan print out can u give the program name and form which is use for it.
regards,
zafarHi,
Standard Output type for SUBCONTRACT CHALLAN is J1IF
You can give the Print for the subcontract challen in J1IF01 transaction, enter the Excise group and series group
In the next screen you can find print parameters
regards,
santosh
Maybe you are looking for
-
Locations of server host name in different SAP system files
Hello, We are implementing SAP ECC 6.0, with i5/OS V5R4 on IBM System i. Could someone please guide me on the locations where the server host name exists in the different SAP system files. We need to change this server host name, and the reason is th
-
Can't edit button text - 6.0.2
iDVD 6.0.2 I'm unable to edit chapter button text - I can't select individual buttons, therefore can't highlight the text to change it. Clicking on a button selects the main title for that screen, not the button. "Select All Buttons" will allow me to
-
Why doesn't a search show the number of instances found?
I'm shocked that Internet Explorer does this but Firefox doesn't -- when I do a search on a page (ctrl-F), why doesn't it show the number of instances found on that page? See IE8 for an example. This should be built-in and not require an add-on, but
-
Hi, In my itunes library i have all my videos twice... One formated for iphone which are about 200 - 500mb and a set for apple TV which are the best quality possible, is there anyway i can sync just the videos that are for the iphone to the iphone??
-
Hi, I need to create a tabular report with breaks on certain columns. The only option I have for the "Break Style" is "Left Break". I need to be able to create a break on one of the columns to give me a look like a master-detail report (like in Oracl