Field setting when collective conversion from planned order to PR

Dear expert:
Is there any way(except ABAP enhancement) to add the field "tracking number" in MD15 when I conduct collective conversion from planned order to PR. Seems in standard config this field in not included in this screen. I have set this field as a mandatory field, but even though when I conduct the conversion, this field still can not be displayed in the MD15 conversion screen.

Hi,
There are following T. Codes to convert Planned Order to PR;
MD14 - Individual Conversion
MD15 - Collective Conversion
MDUM - In Background
Also MD04
User Exit is LMDZU001 - User exits in additional planning

Similar Messages

  • Creation of production order from manual or conversion from Planned Order

    Hello Guru,
    i would like to know why does the production finish date differ when we do manual and conversion of planned order into a production order?
    Thanks

    Ryan,
    When a planned order is created it just uses the Inhouse production time defined to derive the dates, whereas incase of production orders, it would try to schedule the operation and based on that the scheduled dates are derived. The other possibility is the different scheduling types are used for Planned order and Production order. Check transaction OPU5 and OPU3
    Regards,
    Prasobh

  • Collective conversion of planned order

    hello experts,
                       i have some planned orders, while doing the collective converison in production order by CO41 i m unable to do so, the system is giving the error message "PLZ MAINTAIN SETTLEMENT RULE" and message number is "ZSD01000", but i can convert these planned orders individually in MDO4, there's no problem in individual conversion in MD04.
    Regards,
    Sarfaraz.

    Dear
    Check ur configuratin settings
    1. U must have maintained Plant Parameters for the Planned Order - Conversion
    In that the profile u have selected, maintain that in the Settlement Profile Customization.
    Use T code - OPPQ for Plant Parameters Settings
    Use T Code - OPKT (Define Settlement)
    Regards
    Samunder Singh

  • Collective conversion of planned order to one production order

    Dear all,
    1. I have N number of pld ord for same material so i need to convert as production order with cumulative quantity.
    Because to reduce  Issing and confirming and receiving of number of production orders.
    2. I need to create Number of production order with diffferent material numbers  in one screen with different production order number.
    Because per day i need to create more number of production order with different material number. If i create one by one it will consume more time as well as its not practical possible for our business scenario.
    Pls let me know any standards are available in SAP.
    Regards,
    S.Suresh.

    Dear Suresh,
    You can convert Planned Orders into Production order collectively as a mass maintanance in CO41 Tcode.
    Revert if any doubt in case using above tcode.
    Further if you wish to have one production order against multiple planned orders it is not possible as per Standard SAP.
    You can convert to each planned order into individual production order not to single production order.
    If you wish clubbed production order then better you use Individual / Collective Indicator  as
    2     Collective requirements only
    Then you will get cumulative planned orders only against each material and you can convert all of them cumulatively to production orders in CO41 as a mass maintanance.
    Hope your problem resolves.
    Regards,
    Tejas
    Regards,
    Tejas

  • Order type for conversion of planned order

    Hi gurus,
    I have configured 6 different order types for PPPI and not maintained any default order type for conversion of planned order into process order. But when I am trying to convert planned order into process order by branching out from MD04 to COR7 via the popup window, default order type PI01 gets selected which  cannot be changed. However, if I am converting the planned order into process order directly through COR7, then choice of order type is available.
    Could you please tell me how to ensure choice of order type while branching from MD04 to COR7?
    Regards,
    Abhik

    Hi Datta
    The order type is selected as below
    First it will look for any scheduling profile is maintained. If so it will select default from the profile.
    Next if the profile is not there it will look for any scheduler is assigned in material master. Through the scheduler it will select the profile and default order order type.
    Next it will look in plant parameter. With conversion from plan order to prod order  order type
    Next it will look in MRP group conversion order type,  if you have mainted it in Material master.
    This is the sequence. Please check have to maintained any of these.
    Hope this is clear
    Regards
    J . Saravan

  • Set new Required Field for MD14 and MD15 for conver from Planned order to P

    Dear all,
    I would like to set new required field (Purchasing Organization)  in T-CODE MD14 and MD15 for convert from Planned Order to PR. What's should I do?
    Please help, I 'm new for MRP.
    Best Regards,
    Kate

    Hi Kate,
    You are not on the right track; MD14 and 15 will choose the PLANNED ORDER population for the conversion. In planned orders there's NO PURCHASING ORGANIZATION DATA (normally)!
    So even if you managed to put the field on the screen, it will not do anything that makes sense.

  • Order type selection when converting from planned order to prod order

    Hello friends,
    I have one doubt.That when i am converting the planned order to the production order than from which default settings it takes the order type.
    As we can maintain the default order type in OPPQ , under conversion and in production scheduling profile also we maintain order type for make to stock, make to order, etc.
    So my question is to which setting the system gives the priority.
    Or they both are for different purpose.
    Thanking you guys in advance.

    Hi ,
       You can maintain the order type for conversion of planned order to production order in the T Code OPPE.
    Hope it will be clear.
    Regards,

  • Default PR Type when convert from Planned Order

    Hi all,
    How can I default my PR Type when convert from Planned Order after MRP run. This can done via MRP Group control but how to go about controlling via Planned Order profile?
    Which planned object type and planned order profile to be used? assuming that i need my planned to be output at LA type and convert to NB1 PR type instead of the default NB PR type?
    Thanks.
    Regards,
    Andrew

    Hi,
    The system determines the document type from the stettings u are making in "planned order Profile" in Customising for MRP. There u define the order type, the procurement key and the special procurement key and also the account assignment category. So based on the procurement key and the special procurement key maintained in the Marterial master, the document type is selected.
    Production > Materials Requirement Planning > Procurement Proposals > Planned Order > Define order profile
    Choose the planned order type - NB1 Within this you specify the P req doc type to be used.
    Through MRP group and the different PR document type for MRP generated PR is possible only if you assign the document type to MRP group in the MRP configuration.
    Please try and come back.
    Regards,
    R.Brahmankar
    Edited by: R Brahmankar on Aug 28, 2008 10:54 AM

  • Re-exploding BOM at conversion of planned order to production order

    Hi, all.
    I'd like to be able to specify that the planned orders I'm converting to production order re-explode the BOM on the scheduled date rather than the basic date of the production order.
    I want to be able to do this in customizing rather than specifying a BOM Explosion Date (fixed key date) in the planned order or independent requirements.  Is there anything in customizing that could do this?
    Thanks!
    Sarah

    Hi Sarah,
    I think you have checked the note:
    391846 Modif: Reading master data when converting planned order
    Because only with the modification of this note, you will be able to re-explode the BOM when converting the planned order to production order,  however, there is no way to set the BOM explosion date to the scheduled date during the conversion, there is no such customizing as the note only add three action for this function:
         ' '  Do not read
         '1'  Read with explosion date from planned order
         '2'  Read with newly determined explosion date
    So if you need such function, you may try to develop the modification by yourself.
    Regards,
    Rachel

  • Conversion of planned orders to production orders

    Hi,
    we are doing mass conversion of planned orders to production orders and performing capacity availability check, how system will give log information based on these two things,
    when i perform availability check at time of order creation and will not allow to create if anything is missing (i selected user decides option in configuration), does it show any error log report and where can i see.
    When i perform availability check at time of release, if anything missing it will not allow to release and give a choice for a user to release in normal production order creation process, how it will work in mass conversion. is there any standard report to look at missing planned orders so that users will come to know and then decides whether to convert to production order or not.
    thanks in advance.

    Dear ,
    In SM38-Enter PPBICO40 -Execute -Here you need to Mark the Output log option with Erros only or Error Folder for each MRP controller  .Frist you do it in test mode and then remove test mode , mark the Output log option as per requured field and check the result .
    refer this useful thread : Program PPBICO40 for conversion of planned orders to production order
    Regards
    JH

  • Conversion of planned orders to prod orders in background

    hi All
    Is there any program for mass conversion of planned orders in production orders which we can schedule in background.
    Amit

    Hi Amit,
    Try below method
    TCode: COHV (tab selection --- plant and etc...,, tab mass processing --- function - conveted planned order, order type - PP01, collective orders - do not collective orders)
    after Menu -- Program --- Excute in background -- set properties -- to set send SAP spooler --- click button immediate then check box periodic job and periodic values after save
    to monitor and get spool request bcackground this job
    TCode SM37
    or
    you can create background job using TCode SM36
    pls create varient for COHV
    PRG: PPIO_ENTRY with Varient
    Regards,
    Sankaran

  • Collective scheduling for planned order

    Dear Gurus,
    i create the planned order using the bapi standard whit the production version , but when create the new planned order the version don't is read in the order, ( BOM + ROUTING ) OF THE version.
    For read the production version you must reschedulling the planned order.
    Are there the methods for read the production version at the creation of the panned order ,
    or the strument for rescheduling collctive?
    Thanks a lot
    Daniele Pistilli
    PP TEAM

    Dear Gurus,
    thanks for indication of the material master, but we don't  always manage the versions of productions.
    For the production order there are the routing without the production versions, but when i create whit the bapi or whit the transaction MD11 the new planned order manually i need setting the production version , but when i setting the version for the find the version ( bom+routing) i must re-scheduling the planned order.
    Are there the BAPI or alternative soluction for re-scheduling the planned order collective, or for read directly the version present in the BAPI ?
    Thanks a lot
    Daniele Pistilli
    PP TEAM

  • Partial conversion of planned order into production order of AFS material

    Dear Experts,
    I am working with SAP 6.0 EHP4 with AFS add-on. My material is AFS specific material. I am not able to convert planned order into production order partially from MD04 screen as all the fields in the CO48 screen is grayed out. 
    Please help...
    Regards,
    Alok Tiwari

    Hi,
    I am not able to get what is passing the start date.
    Second thing is how you are generating the serial number - manually or automatic?
    If you are generating serial number automatic, then it is not possible to generate it considering the basic start date.
    But if you are entering the serial number manually, then there should not be any problem as system will accept that serial number which you enter at the time of conversion of planned order to production order.
    Regards
    Amit parkhi

  • Conversion of planned order into subcontracting order

    Hello Gurus,
    my problem concerns a subcontracted material.
    This material may be produced internally (managed with production order) OR produced externally (managed with subcontracting order) depending on the available capacity of the production line.
    For this material MRP must generate planned orders, so the planner can choose either to produce either to subcontract.
    The planned order is then converted manually into production order or into purchase request.
    With procurement type = X, it is possible to do so. However when I convert my planned order into purchase request, my item category is NOT automatically set up to L.
    So I have to enter the item category manually even if I have only one purchasing info record (with record category = 3).
    Do you think it is possible to create automatically a "subcontracting request" from the planned order ?
    Many thanks for your help
    regards
    Amaury

    Hello,
    I am afraid that when I enter procurement type=X & special procurement=30 in material master data, planned orders created by MRP have then a order type = NB (standard purchase order) and special produrement type = 3 (subcontracting).
    So this kind of planned orders can only be converted into purchase request and NOT into production order.
    It looks like it is not standard to do so in SAP and that I will have to manage subcontracting in prodution order; 1 routing for internal operation and 1 routing for subcontracting.
    Thanks
    Amaury

  • Conversion of Planned order into a Production Order.

    Hi All,
             I have one ticket in which I have to change the format of generating serial no.s.This format has to consider
    Basic Start Date while generating it.In our project Serial No is getting generated at the time of Production Order.
    So I have to pass this start date before Prod Order is getting created from a Planned Order.What i want to know is it possible to pass a start date when a Planned Order is getting converted into Prod Order as i think it will be a standard SAP program which will convert a Planned Order into Prod Order.Any suggestions on how to achieve this is most welcome.
    Thanks in Advance,
    Saket

    Hi,
    I am not able to get what is passing the start date.
    Second thing is how you are generating the serial number - manually or automatic?
    If you are generating serial number automatic, then it is not possible to generate it considering the basic start date.
    But if you are entering the serial number manually, then there should not be any problem as system will accept that serial number which you enter at the time of conversion of planned order to production order.
    Regards
    Amit parkhi