Function of lot size PB,FS.

Hello SAP Gurus,
   Can you help in understanding the function of lot size PB(period lot size=posting period) and FS (Fixing and Splitting).
     I mean i what to know how these lot sizes works.With this also share that where can i get study material on it.
                        Thanking You.

Hi,
Lot Size FS :-
When entering the lot size "FS" and in field the qty as fixed the system is splitting up the planned order qty.
For ex qty is 100  the fixed lot size is 25 the sys creates 5 planned orders of 25 each. The total qty now comes to 25
Lot Size PB :-
In period lot-sizing procedures, the system groups several requirements within a time interval together to form a lot
In PB periods of flexible length equal to posting periods.
Determines how the lot size is calculated for a certain lot-sizing procedure during material requirements planning.
Please go SAP help for details and system configuration in OMI4.
http://help.sap.com/saphelp_46c/helpdata/en/f4/7d281244af11d182b40000e829fbfe/frameset.htm
Hope it will help you.
Regards,
R.Brahmankar

Similar Messages

  • Min max lot size time based for use with SNP and PPDS

    Hi all, Is there anyway to set up time based min and max lot sizes? ie we want to have a Max lot size which is small for use with the first 3 months of our plan which starts life in SNP and then converts to PPDS and into blocks for block planning, but months 4 to 36 we want to leave as large max lot sizes as there is no need to have the small max lot sizes for the different horizon.
    As far as I can see there is only a material/plant lot size  and Max lot size and no way to have a different setting in a different time period.
    Thanks
    j

    Hi John,
    As you know, in the product master, the lot size maintenance is time-independent, so that obviously can not be used for your scenario. As per my understanding, to meet this using standard functionality, you can maintain multiple product specific t-lanes (for STRs) and PDSs (planned orders) with required lot size ranges and validity dates (for short or long term horizon). But, again since the validity of t-lanes and PDSs will not be automatically rolling forward so the updating the validities will be a challenge.
    The other option could be to enhance the heuristic functionality at lot size selection step while creating order.
    Regards,
    Umesh

  • Pass on lot size" function not supported in costing runs

    hi when i am doing cost estimate through ck40n i am getting following error.
    Pass on lot size" function not supported in costing runs
    Message no. CK463
    Diagnosis
    You have selected costing variant PPC1 for the costing run. The Pass on lot size indicator is set in this costing variant. Costing variants in which this indicator is set cannot be used by the costing run.
    System Response
    The costing run is not created.
    Procedure
    You have the following options:
    Reset the Pass on lot size indicator in costing variant PPC1 so that the lot size is not passed on.
    Use a different costing variant in which the Pass on lot size indicator is not set.
    if any one had found any same king of error please help me in fix it.
    thanks
    kareem

    Probably this might be the cause
    Sales order by Costing
    Check out the below
    Pass On Lot Size
    Definition
    If this indicator is selected, the system determines the costing lot size using the lot size of the highest material in the BOM and the input quantities of the components.
    Use
    1) Do not pass on lot size
    If this indicator is not selected, the materials further down in the structure are costed in accordance with the lot size in the costing view of the material master record. When the materials in the next-highest costing level are costed, the costing results of the semifinished materials are converted to the lot size of the finished material to calculate the material costs for the finished product.
    2) Pass on lot size only with individual requirement
    In the MRP view of the material master record, you can specify that a material is planned as an individual requirement. If such a material is added to another material, costing uses the lot size of the highest material.
    3) Always pass on lot size
    Here, the costs for all the materials in a multi-level BOM are calculated using the costing lot size of the highest material. This function is used principally in sales order costing.
    If you are costing sales orders using product costing for a material with a multilevel BOM that is produced in-house, choose 2) or 3) . For those individual requirements materials, from a business management point of view it is recommended that the order lot size be used when costing the material components going into the finished product. On the other hand, materials subject to collective requirements are generally costed using the costing lot size in the material master record.
    Thanks

  • Report for Reorder point, safety stock, current stock and fixed lot size

    Hi,
    Purchasing Dept. is looking for a report which can give list of materials falling below the reorder point, so that they can go ahead and create procurement proposals for those materials.
    They also want to see the Reorder Point, Safety Stock, current stock and fixed lot size in the same report.
    Let me know if there ia any standard report availbale which displays the same or any approach to get the same.
    Thanks in Advance.
    Regards,
    Shankar Goud.

    Hi,
    There is no standard report because this is meant to be managed by the MRP run.
    The MRP lists show all materials that have a problem (such as stock below reorderpoint) but MRP generates requirements for these anyway and so all you need to do is to look for the MRP generated requirements (requisitions?) and you have your list?
    Are you using MRP?
    If so then please use the standard functions in MRP to get this.
    If not, then WHY NOT?
    Steve B

  • PLANNING CALENDER IN LOT SIZE

    Hi
    What is the function of Planning Calender in Lot Sizing procedure in SNP.

    Hi
    You can define the planning calendar to define the periodicity of lot size.
    For example in our case we want to SNP to create requirement only in alternate month based on lot size.
    So we create planning calendar which consist only alternate month and attach to lot size.
    Now when we execute the SNP planning, it will create supply element only in alternate month.
    I hope this will give insight of it. Please let us know , if it helps you.
    Thanks
    Amol

  • Parameters controlling: Lot Size

    Dear,
    I'm a jobstudent at NV Niko and I have to do some research to introduce new features about SAP.
    It is about inventory controlling : parameters controlling.
    For certain articles, I can access the parameter controlling and for exemple get the bar chart of the Lot size.
    The bar takes place at a certain range of coverage at the average receipt and value of the average receipt. Now I have a few questions about this topic:
    Are these 2 variables determined by SAP or is it possible to change them and try to optimize?
    In the chart, the bar has a specific place, is their a possibility to see what the perfect place would be? By perfect place I mean in which segment should the lot size be in the optimum for a specific article. Maybe their is a function to see this.
    How can we do follow-up-analyze-actions? For exemple, when we select more than 1 article, is their a possibility to take out the bad ones (these that are not in their optimum) and that way spot and improve them?
    For the safety stock, I have the same problems, so I hope you can help me with these too.
    Thank you
    Best regards,

    Dear,
    I'm a jobstudent at NV Niko and I have to do some research to introduce new features about SAP.
    It is about inventory controlling : parameters controlling.
    For certain articles, I can access the parameter controlling and for exemple get the bar chart of the Lot size.
    The bar takes place at a certain range of coverage at the average receipt and value of the average receipt. Now I have a few questions about this topic:
    Are these 2 variables determined by SAP or is it possible to change them and try to optimize?
    In the chart, the bar has a specific place, is their a possibility to see what the perfect place would be? By perfect place I mean in which segment should the lot size be in the optimum for a specific article. Maybe their is a function to see this.
    How can we do follow-up-analyze-actions? For exemple, when we select more than 1 article, is their a possibility to take out the bad ones (these that are not in their optimum) and that way spot and improve them?
    For the safety stock, I have the same problems, so I hope you can help me with these too.
    Thank you
    Best regards,

  • Use of max stock level w/o lot size HB

    hello champs..
    need  a help on below functionality
    Can I have the functionlity of max stock level without using "lot size - HB" in material master.
    my requirement..tht system should not create any procurement proposal if stock reachs at max level..
    but with this i am using min lot size also..and this functionality got vanish if I use "lot size=HB" ..system dont see min or max lot size..it just create the proc proposal for the qty upto max stock level..
    my requirement
    for a material max stock level -100
    min lot size - 50  , max lot size 80
    and if my stock is 30 ,and my reuirement is for 80..system should not cross the max stock level and should create the prc proposal for 70 only..
    pl share your thoughts on this..I'll appriciate wih necessary reward points..
    Br
    Sumit

    Hi
    thanks for reply..but i am not sure whther w/o using HB max stock level will be considered or not..
    i yet have to test the same but as per SAP , if you want t maintain themax stock level in the plant , lot size should be EX
    is this undertsnding is okie..
    thx in advance
    BR
    Sumit

  • Fixed Lot Size

    Dear Gurus,
    I am simulating the functionality of Fixed Lot Size so I enter Lot Size = FX and indicated Fixed order Quantity = 40,000 in Material Master. We are using Ind./Coll = 1 and I want to generate fixed quantity of planned order equal to 40,000. But when I run MD42, the system still generated planned order equal to the shortage/required quantity. Our requirement is to generate fixed quantity of 40,000 per planned order regardless of demand requirement.  
    Please help. Thanks in advance.
    Regards,
    SD

    Hi,
    Please find my reply below,
    Use MRP Type VB:Manual reorder point planning:Here you need to define reorder point in material master in MRP view.When the stock level reaches the re order point then system will create a procurement proposals.
    Regards,
    Kumar.S

  • Default costing lot size and price unit as 100 in material master

    Hello,
    The costing lot size and price unit is "1" by default in material master. Due to this in CK11N the costing lot size is coming as 1.
    Then we go to MM02 and change the master by making costing lot size as 100 and price unit as 100.
    Please advise how can we make this default as 100 instead of 1 in material master. So that everytime we don't need to change.
    Is it coming from BOM?
    Please suggest.
    Regards,
    Tapan

    Hi Tapan
    No doubts, it is ABAP's responsibility to develop it.. It requires ABAP code to be written
    The functional specifications need to be given by you.. This BADI is called during Mat Master Creation/Change.. Your Func Specs should cover
    1. Which Mat types it should be used for
    2. The costing lot size and price unit to be defaulted...
    I used it to check Plant = Profit Center and it worked... For whatever checks and validations required during Mat Master creation, this badi needs to be used
    Regards
    Ajay M

  • CK727 -Lot size cannot be passed on in combination with mixed costing

    I get below error.
    We have KMAT materials and scenario  is Non Valuated Sales Order Stock.
    in our PPC4 - we have below settings. (Both are SAP recommended)
    Qty Structure tab we have Pass on Lot size "1" with individual requirements (must of Non Valuated Sales) and
    Transfer Control "PC03" has "Current Std Cost" with "Transfer only with Collective requirements"
    I just created a mixed cost qty structure. In it I even added Costing type "01". Sales order costing type is "18".
    Mixed costing works as expected. However we are unable to create any Sales Orders.
    Lot size cannot be passed on in combination with mixed costing
    Message no. CK727
    Diagnosis
    For costing variant PPC4 and costing version 01, it was defined in Customizing that a mixed cost estimate should be created for quantity structure category M0001. At the same time, it was defined in the costing variant that the Pass_on_lot_size function should be active.
    System Response
    Mixed costing cannot be carried out simultaneously with Pass on lot size . Costing cannot be proceeded with.
    Any help is appreciated.

    Hi Kala,
    system's response is correct
    In the standard program the combination of mixed costing and
    simultaneously pass on lot size is not possible.
    Please review SAP Notes 402440, 584420 and 749128 .
    In particular the SAP Note 402440 describes the determination of the
    costing lot size at a mixed costing in detail.
    br, Guido

  • MPS Lot size rounding

    Hi,
    We have following scenario:
    1) FG X with planning strategy 11, MRP Type: M0, Fix Lot Size: 100 Box
    2) PIR entered for FG X for 100 box.
    3) MPS Run
    4) Plan Order of 100 box created
    5) Convert to Production Order and final confirmation of op 10 for 90 box.
    6) Production Order appeared as receipt element as 90 box.
    6) In next MPS Run, Plan Order of 100 box being triggered for the FG X again to cater for the outstanding requirement of 10 box.
    The client do not want the Plan Order of 100 boxed to be generated again. the stock initial GR of 90 box is deem to be able to cater for the market. In generak if the requirement is less then the batch size (fix lot size), no plan order should be created.
    Appreciate if you have any idea/solution that can overcome the above requirement, kindly share with us..
    Thanks.
    WH. ONG.

    Hi Wan Haur Ong,
    Well i gone through with your thread and i am having an idea for your requirement.
    As you said that you want only for particularly the the remaining quantity like 10 boxes should have a production., It means only for 10 boxes:
    I would like to suggest you there is a funcationality called rework process for that you have to use funcationality called Trigger point for that particular operation:
    Please maintain these steps for that operation OK:
    First check in Tcode OPJF for the selection id a Priority is defined for the Task list type S with usage 1 and status 4 and then Proceed as follows:
    1. Create a Reference op set in tcode Ca11.
    Enter the plant,Description , usage and status for the ref op set Enter lotsize and unit of measure.
    Enter the op as 0010 / workcenter/op control key/Description for the op Enter the standard values and save.
    2. Create a Standard trigger point in CO31.(Ex Production)
    Enter the Trigger Point usage /Group as FERT.
    3. Tick the Trigger Point Functions.
    4. Enable the indicator create order with Reference.
    5. Enter the system status as PCNF.
    6. Enter change as +.
    7. Enable the indicator once.
    8 . Now place the cursor on the create order with reference.
    9. Goto Parameters.
    10. In the Parameter enter in the group the created Reference op set group no.
    11. Order type as PP01 and group counter as 1 and save the Trigger Point.
    12. Now goto the Routing for your Material.
    13. Choose the last op to assign the Trigger point.
    14. Select the OP -
    > Goto ---> Trigger Point overview.
    15. Enter the Trigger Point usage as FERT.
    16. Now choose that line ,select the Details---> Trigger Point f7. The system will says standard trigger point exists from which you can select the created Trigger Point (EXx Production)and save.
    18. MD02/MD04.
    19. Convert the Planned Order into Production Order and Release the order.
    20. Now confirm th ops.
    21. For the last op enter the yield and rework qty and set the status as PCNF.
    22. If the status of last op is PCNF then in the system a POP UP will appear as Activited by Trigger Point /Create order with reference/order number/sequence and op number which trigger point works and enter.
    I hope it will helps you, please get back to me if you have any questions OK pop me again.
    Regards,
    Madhu.G

  • Minimum Lot Size Ignored

    Hello All,
    To replicate scenario, I have created new material with minimum lot size 10 pcs and created independent requirement (LSF) and then created scheduling agreement.
    Independent requirements as 8 pc for every day.
    Now when I run the MRP and check in MD04, for the last requirement, planned order was raised for just 9 pcs, ignoring minimum order qty/minimum lot size functionality.
    Just for information, Lot size -EX, MRP type PD, Strategy group 10 (though these factor doesnot influence).
    Any more settings/customizing required?
    BR,
    Krishna

    Dear Krishna,
    I guess you must have activated the check box for Last Lot Exact for the Lot size - EX in T.code OMI4.
    If so means remove this and then check with new requirements and MRP run with planning mode - 3.
    Regards
    Mangalraj.S

  • Daily lot size not working for more than 5 days grouping

    Dear All,
    I want to create the procurement proposal for 6 days once. So I have created new lot size ZB by copying TB and maintained no of periods as 6.
    Assigned the lot size in Material master. After MRP run, the procurement proposal created for every two weeks on Monday. It is not created as expected (6 days once). Is there any other settings needs to be maintained to achieve the requirement?. The same problem happening for the no of periods 7,8,9 also with daily lot size.
    I don't want to use the planning calendar for this. Daily lot size is working only upto no of periods as 5.
    Could you please someone explain the standard functionality of daily lot size with combination of no of periods?
    Thanks in advance.
    Regards,
    Ganesh

    Ganesh,
    Check if your lot size is something similar to screenshot below. It is important that you have lot sizing procedure as 'Period lot size' and period as 'Daily lot size'
    With the above lot size (number of period as 8 days) I can see expected results.
    Regards,
    Himanshu

  • Min Lot Size and Rounding value

    Hello MM  Gurus
    need a small help!
    I m a bit confused regarding the  use of Min lot size and Rounding value in material master "MRP 1" view..
    can some body teach me a detailed functionlity for both..
    As both serve the purpose ..for e.g. my requirement is 7 and min lot is 10 system will create proc.proposal for 10
    in similar way if i use rounding value as 10 , then als system will create proc.proposal for 10 only even if requirement is 7.
    grateful if you could pl expain me the functionality of both...
    another query..if I use Min lot size in material master will the same will serve the puspose of  <b>min order qty ( maintained in PIRs)</b>
    i'lll appriciate with good reward points...thanks in advnace
    Br
    Sumit

    Helo Guys..
    Thanks for valuable inputs..
    i have assigned the appropriate rewards ..
    pl clear my this doubt also
    e.g. for a materials
    Min Lot size - 40
    Rounding value 25
    requirement is for - 35
    will it be 40 or 50 ..i understand 50..
    j
    ust anothe rquery..pl treat this separate issue..and separate rewards will be given
    <b>can I use max stock level w/o use of  lot size "HB"</b>
    e.g. if my max stock level is 80
    and min lot size is 30 and current stock is 60
    what'll be my proc proposal created by MRP , i dont want system to cross 60 stck,,
    Thanks in advance
    BR
    Sumit

  • /SAPAPO/RRP_PLANNING   calculation requirements lot size period

    Hi all,
    In badi:  /SAPAPO/RRP_PLANNING  Method: AFTER_NETTING I want to recalculate the requirement (QUANTITY in CT_REQ_IO) depending on the period type of the lot size ( SAPAPO/MATLOTSZ-PERVR ).
    So feg, requirements for 1 product for 1 day, the period type of the lot size = W week -> so I have to summerize all quantities for that product for 1 week.
    Is there a function module to do this? Because you can have week but also month, quater, ...
    thanks a lot,
    Caroline,

    Hi,
        Please see the BAdi documentation available also one example class is given from which you can use the code whichever is applicable to your requirement.
    Class Name: /SAPAPO/CL_EXM_IM_RRP_PLANNING
    Regards,
    Saurabh

Maybe you are looking for

  • Is it possible to add/remove photos in the default slideshow of the Apple TV?

    I know and understand that you can use a slideshow of your own via Home Share but is there a way to combine both the Apple TV's photos with your own? Maybe a dedicated directory for them without using personal photos or something similar. For instanc

  • How do you "un-unite" objects

    In Pages 5.+, you can "unite" objects. This is Apple's pathetic attempt at allowing linked text boxes, among other things. However, there is no way to "un-unite" text boxes. At least, I can't find one--aside from using the undo feature to undo everyt

  • Save As PNG script

    Hello, I'd like some help with this script if possible I wanted to save my open file to PNG format in the same location with the same name. I managed to do that with the scripts below. This is a script I found on the forum: #target photoshop main();

  • Calendar times do not match between iPhone and Outlook 2013

    I have Outlook 2013 sycing with iCloud (poorly but it works). There is a time zone issue between these two programs.  I live in Saskatchewan (-6) where we don't have daylight savings time.  I have Time Zone Support turned off on my phone, and the tim

  • Software

    What Bible software is available for the Palm Z22? Thanks Post relates to: Palm Z22