Fund Managment : TCode 'F-02

In Tcode 'F-02'.
I want to post some doc type without affecting the allocated budget.
If somebody can help me with the BADI.
I have found one FMAVC_ENTRY_FILTER but its not giving the desired output when i mark skip posting flag as 'X'. its still posting the data and reducing the allocated budget.
regards
vivek

any idea???

Similar Messages

  • Status of PO becomes F in fund management

    Hi,
    recently we have upgrade SAP from ECC6 to EHP4 and found some of the PO's Status becomes F in fund management, so we are not able to make service entry sheet and payment as system asking for further budget though actually POs value has not reduced fully.
    Plz help to remove the status F from FM so that it can be able to make payment.
    P K Sahoo

    Hi, try to reconstract PO(I don't remember tcode, but you can find it in spro like M*4N)

  • Fund Management- Business place

    Dear Team,
    In fund management, i am creating request of payment Tcode F871, fi document is created in background and get parked, such request is released Tcode F874 and ultimately posted Tcode 870.when posted FI document which was parked while request creation gets posted.
    My question is about the field " Business place" and " Section Code" which is neither available at the time of creation of request nor available at the time of posting of request.
    SInce Business place field ( BUPLA) is blanck, TDS certificate can not be generated.
    Please advice how to get " Business place" field in F871/ F870
    Thanks,
    Nilesh Pitale.

    Hi,
    maybe this document will help you more:
    http://perlhosting.net/download/968192356.html
    SAP78V

  • BPC Retraction for Funds Management

    hi guys,
    is there any FM or programs that we can use to retract data from BPC back to ECC6 for Funds Management module

    In my project, customer has same requirement. We retracted BPC data to FM module by:
    Option1 - FMCYCOPI_BW is a standard function, but issue: it can't provide detail information if there's error happened.
    (1) Download BPC data to a BW Cube. (This step is not mandatory)
    (2) in FM, use TCODE FMCYCOPI_BW to extract BW query (on that Cube) and generate FM documents.  // you need to do some configure in SPRO FM.
    Option2 - you can capture error while creating FM documents.
    Write ABAP codes to retract BPC data and generate FM Documents.

  • Usage of FMBV in funds management

    Dear Experts
    Iam creating one po at the time the following message displayed
    ITEM 010 2000 /4105200000/ COMMITMENT BUDGET FOR 2011EXCEED .
    But i opened FMBV T code and gave funds management area, fiscal year and commitment item and funds and executed , the problem automatically solved . I dont know what is the relation this t code .
    Can any one tell me the usage of FMBV Tcode in funds management ,
    Thanks & Regards
    Vijay Kumar

    Hi,
    FMBV executes a program to reconstruct AVC ledger for Former budgeting in FM (for BCS there is a similar transaction FMAVCREINIT). This transaction has to be executed sometimes in oredr to correct inconsistencies in budget control tables.
    Regards,
    Eli

  • Funds Management Commitment

    Hi,
    In funds management (BCS) in case of inventory I have activated AVC from PR level. After making PO commitment for PR get reversed and new commitment for PO get generated. but after issuing material to department, commitment for GR get reversed and new commitment for PL GL get generated. this leads to total reversal of commitment at balance sheet GL. due to this budget get opened again for new PR. to avoide this I required to block commitment through tcode FMX1. but this to be done manually every time after issuing material. I want to make it automated means commitment should be blocked automatically after issuing material. please suggest.

    Hi,
    I made PR for Rs. 100. In this case commitment is booked for GL say 132000 (inventory).
    After that I made PO for same amount. So PR commitment get reversed and PO commitment booked for Rs. 100.
    In case of GR PO commitment get reversed and commitment booked for GR entry for Rs. 100.
    Then I issue that material to GL 412000, CC 190150 then GR comitment for GL 132000 get reversed and new commitment for GL 412000 get booked.
    It means PR budget is again open for posting.
    +100 PR
    -100 PR (after making PO)
    +100 PO
    -100 PO (after making GR)
    +100 GR
    -100 GR (after issue of material)
    to avoid this opening of PR budget again I need to block budget by passing manual entry through tcode FMX1to GL 132000.
    I want to make this FMX1 entry automated. can we do this. please suggest.

  • System error in Funds Management update

    Dear you,
    Have anyone seen the following when updating FM from FI document:
    "System error:Funds management update (FMRI, CHECK_WE_RE)"
    Any ideas what to do?
    Thanks
    Sonja

    Hi there,
    The update problem occurs both if we try to post with FB50L or if I try to make a transfer of FI postings in FM. This all happens in the new installation where we plan to use new GL and FM.
    This note you gave did not ring a bell for me
    The error message is FI057. But we have not yet found a suitable note.
    Therefore any ideas are still welcomed.

  • Funds management cube getting data from 4 ods, data not seen in cube

    Hello all,
    I am working on funds management cubes (0PU_C02 and 0PU_C03). These two cubes get data from like 7 or 8 ODS. Can someone tell me which are the ODS which feed to respective cubes. I have the mappings done but i am getting very confused.
    In the ods 0PU_O44 there is RLDNR for Ledger and I can see that data in ODS but when i run load to cube I dont see the ledger data (its direct mapping there are no routines or rules).
    Is there any sequence with wihic we have to load the data?
    Thanks
    Message was edited by: Raj M

    Hi Raj,
    I was going thru the forums who has knowledge in Public sector when i came accross ur forum.Can i get your email id..i have some questions to ask regarding student administration.
    thanks.

  • |Funds Management - relating to PR/PO

    I am getting another error in Funds Management:
    Posting date must be used for update of value type 000100 update profile 50
    Message no. FI_E008
    Diagnosis
    FM areas with assignment to the update profile must have all their value types defined as 'posting date' on the ledger level when activating to period-based encumbrance tracking (PBET) on the ledger level.
    Procedure
    Find all the FM areas using the update profile in transaction 'OF37'.
    Use transaction OF36 to ensure that all value types in the FM area(s) are using 'posting date' for the ledger that is being activated to PBET.

    Hi,
    It's what the system says. You have to ensure, that you don't overwrite profile 0100 in OF36 with other date, than posting date.
    Regards,
    Eli

  • Funds Management cut over of Open PR and PO

    Hi,
    In case of cutover, we are using following link to update FM account assignment in open PR/PO.
    SPRO>Funds Management Government>Actual and Commitment Update/Integration>Internal Data Transfer to Funds Management>Supplementary Account Assignment-->Select Documents
    and
    SPRO>Funds Management Government>Actual and Commitment Update/Integration>Internal Data Transfer to Funds Management>Supplementary Account Assignment-->Convert Worklist
    1) But in this case, for open PO of which GR is not done FMRP_RW_BUDCON report is not updated after doing above mentioned process. when I make GR, commitment get updated in FMRP_RW_BUDCON report. This does not show actual status of budget consumption as budget consumption is shown at the time of GR only.
    2) If GR is already done for PO and after doing above mentioned process, if GR get reversed then Negetive commitment shows in FMRP_RW_BUDCON report and after deletion of that respected PO, commitment of PO gets zero. But negetive GR commitment remains open which leads to wrong status of budget consumption. e.g. GR of Rs 5000 is reversed. Then report shows two documents as -5000 for GR reversed and 5000 for PO commitment getting open. IF I reversed this PO then PO commitment of 5000 become zero. but GR reversing amount -5000 still remains open. So it shows less consumption of budget by Rs.5000.
    Do I am missing any process. Suggest.

    Hi,
    Firstly, after you convert the open commitments, you'll need to run FMAVCREINIT to reconstruct AVC. FMRP_RW_BUDCON will then reflect the converted commitments.
    Secondly, based on your posting, it seems that you do not want PO commitments (VT 51) to be counted as budget consumption. You can achieve this in the ledger 9H configuration:
    Public sector management > Funds management government > BCS > Availability control > Settings for availability control ledger > Define filter settings for commitment/actual values. You will want to exclude both value type 50 and 51 from ledger 9H. After you change the setting, you will need to run FMAVCREINIT again.
    Hope this helps.
    Regards,
    Ming

  • Error while Activating Activate Global Funds Management Functions (PSM-FM)

    Hi,
    I am getting the below error while activating Activate Global Funds Management Functions (PSM-FM) in Funds Management.
    Aktivierung des Haushaltsmanagements ist nicht erlaubt
    Message no. ZZ003
    Kindly help me in fix this issue....
    Thanks
    Kishore

    Hi,
    Thanks for your reply. But can you clarify me why we need to delete the row Z_LEAVE in SE11 for FMISPS table. Because here ABAPER is objecting to do this as they feel there may be some impact if we delete this.
    Kindly clarify me
    Thanks
    Kishore

  • Error while settlement of WBS - Funds Management

    Hi,
    We have maintain derivation rule as - WBS to Fund Center. This Fund center is DUMMY because we need not want to control WBS through Funds Management.
    There is always one Cost center in each WBS. while settling this WBS we are getting error as -
    Asset ABC 000127000000 0000: no subnumber with FM assignment DUMMY / /
    Message no. AW851
    ABC - Company code
    000127000000 - asset number
    DUMMY - Fund center
    suggest.

    alex ice wrote:
    Hi, 1 change FC in AS02 to dummy if it applicable.
    > 2 Check note 618269 it applicable.
    > 3 remove FC from asset master data
    Hi Alex, how are u!?
    I've got the same issue than Harsh Vaidya in my system ...
    Ive already read this notes: [618269|https://service.sap.com/sap/support/notes/618269] (no apply to me, because Joint Venture Accounting isn't active), [844262|https://service.sap.com/sap/support/notes/844262], [1473357|https://service.sap.com/sap/support/notes/1473357], [446029|https://service.sap.com/sap/support/notes/446029] and [440396|https://service.sap.com/sap/support/notes/440396]
    All very interesting notes :P
    But... I couldn't find the solution
    I try to TRACE from FMDERIVE too, but when I go to KO88, FMDERIVE's trace doesn't track anything.
    Any help to throw some more light on this thread, would be very useful.
    Thanks a lot!
    Regards from Argentine.

  • After Funds Management activation we got error in travel managment

    Hi All,
      After activating funds management in the system, while creating a travel request we got the following error. Anyone can help on this, for idenifying the problem.
    In the travel request portal we are getting this error :
    " com.sap.tc.webdynpro.modelimpl.dynamicrfc.WDDynamicRFCExecuteException:      No expense type for estimated costs has been defined. Cannot save   , error key: RFC_ERROR_SYSTEM_FAILURE     and          No expense type for estimated costs has been defined. Cannot save   , error key: RFC_ERROR_SYSTEM_FAILURE "
    regards,
    Sabari Prabhu.

    Hi
    I have a question, I udnerstand in (Create one expense type "Estimated Costs") but my question is in using transaction
    When you start using the trip transaction and select a travel request the system send you to the TP04 transaction... now
    with this new function, I have to use the transaction PR05 its right? becouse the TP04 ask the VORS expense type, and sap says to dont delete record
    Please could you tell me with wich transaction you start to create a travel request? I have the same problem of the screen but Im not sure to use the TP04 transaction wit this solution
    Thanks a lot

  • PSM-FM-Reversal of funds management document after change in acc.assignment

    Good day we recently went live with a component of Funds Management i.e. Availability Control on Cost centers and cost elements. We update BCS with the plan values and actual/commitment items in Finance/CO. We do our planning in CO.
    The solution is working reasonably well but we have encountered a problem for which we are unable to find a solution. The problem is best illustrated with an example;
    1. Create purchase requisition with Account Assignment Category "K" = Cost Center with transaction ME51N
    2. Account assignment = cost center and cost element. A funds management document is created upon saving of the transaction.
    3. Purchase Req. is released with a release strategy (transaction ME54N)
    4. After purchase requisition release the account assignment for the cost element is changed by the user. This occurs sometimes during the execution of the business process.
    5. When a purchase order is created with reference to this purchase requisition with transaction ME59N  the system references the original funds management document which means when the account assignment was changed the funds management document was not reversed and a new funds management document created for the changed account assignment.
    6. The BUDCON report transaction FMRP_RW_BUDCON thus displays the commitment under the incorrect commitment item as the change in account assignment is not reflected in Funds Management. We have a one to one relationship between cost elements/commitment items and cost centers/funds centers as per the derivation strategy.
    My question is;
    Is this normal standard SAP standard behavior or are we missing some configuration that will enable the creation of a new funds management document and if so where do we configure such?  I must mention our solution is completely SAP standard. 
    Thank you in advance.
    Best Regards
    Mike Olwagen
    Manager SAP Solution Support
    City Power (JHB) (Pty) Ltd

    Hi Mike, nice to meet you.
    I think u should do an entire test with TRACE on, and u will find the problem, and how to fix it (at FMDERIVE of course).
    First: Have a look at note [666322|https://service.sap.com/sap/support/notes/666322], go to FMDERIVE and turn ON the trace.
    Then, run all the process ... from ME51N to the end...
    I agree with Eli, u must allow overwriting of existing values at FMDERIVE rule...
    Regards,
    Osvaldo.

  • Commitment Item in SD Billing document (Fund Managment) ECC6

    Hi,
    We are upgrading from 4.6C to ECC6 and have activated Fund Managment (EA-PS).
    At the time of carrying out the Billing in SD we are getting a error that no commitment item available for gl account but if I use the same revenue account and create a FI invoice (FB70)  then the CI is getting derived thru the derivation rules (Rule:CI from Cost Element).
    I would like to know why the CI is not getting derived during Billing in SD module.
    Thanks
    SS

    Hi,
    Thanks for your message.
    I have maintained a derivation  Rule:CI from Cost Element, so that the CI will derive from this derivation rule.
    As mentioned if I use same revenue account and create a FI invoice then the CI is derived as per the derivation rules but while carrying out the SD billing then the error comes.
    Kindly clarify.
    Regards
    SS

Maybe you are looking for

  • Download internal table data into excel sheet with column heading and data

    Hi,   I am having one internal table with column headings and other table with data. i want to download the data with these tables into an excel sheet. It should ask the user for file name to save it on their own name. They should give the file name

  • Dynamic VLAN Assignment + NPS

    Hello, I'm planning a deployment with the following: 5508 WLC running 7.0.222.0 NCS 1.0.2.29 50+ 3502i AP's Windows 2008 R2 running NPS EAP-TLS for authentication The end goal is to have a single SSID and utilize NPS to dynamically assign VLAN's depe

  • Variant files in Miscellaneous folder

    Hi, This is regarding 4.7 version. I am trying to configure Best Practices - India (Baseline package) manually. Unfortunately the DVD on which the Best Practices documentation was sent is damaged and hence I am not able read some 'variant files' requ

  • HRMS Configuration Workbench - yes or no?

    Does anyone have knowledge of HRMS Configuration Workbench being used for an Oracle HRMS and Payroll implementation? If so, what are the pros and cons? And would you recommend it as the preferred method for implementation? I am about to begin an impl

  • My new hp photosmart printer 7525 will not print to photo paper always prints on regular paper tray

    I have the hp photosmart 7525 wireless printer. When I try to print a picture it doesnt use the photo paper, it keeps using the regular paper.  I have Windows 8.