GR qty showing less than production order confirmation qty

Hello Experts,
Greetings.
My issue is while doing production order confirmation(CO12),for some materials it shows less GR quantity than the confirmation qty.I m wondering how it can be possible?
What could be the problem?
Plz advice.
Thanks
Nitin

Confirmed qty of each operation and delivery qty at the header are two different fields.   Confirmed qty will be the same with the yield to conf. during confirmation.  Whereas, the GR qty is equal to the total sum of quantity received from the order. 
Check whether during confirmation you create auto GR or not.  If yes, then check the COGI t-code.  There might be some error log of goods receipt in there.  If no, then check GR qty in document goods movement compared to confirmed qty during confirmation.
Hope it helps.

Similar Messages

  • GR quantity less than Production Order quantity

    Hello all
    I am working at a client where they produce Make-To-Order items specific to a Sales Order by triggering an Assembly Order (Production Order).
    Now I am facing a tricky situation & hence want some advice from you guys.
    In a generac scenario when an order comes for a MTO material ABC, a Production Order is triggerred for that item.
    I can navigate to this Production Order from the Sales Order > Schedule Line tab (Just FYI)
    Now once the Production Order is confirmed for each Operation on the floor using CO11N, the material is receipted in the Inventory & the requirement gets fulfilled.
    Now sometimes the Production Order is Goods Receipted for a Lesser quantity as compared to the Production Order Quantity.
    e.g. Sales Order Quantity = Production Order Quantity = 3 EA & the Delivered Quantity (GR qty) = 1 EA
    In such a case, in MD04 the system still shows an open requirement for 2 EA on the same Production Order Number
    Is there a way to trigger another Production Order for the remaining quantity automatically ?
    If anyone can share their thoughts proposing possible solutions to handle such a scenario, it would be a great help.
    I am an SD consultant & hence cant think ways to handle the scenario & propose it to the Business.
    Any help will be appreciated
    Thanks
    Vin

    Hello
    Thanks for all your replies.
    As of now the 1st scenario is no more an issue. The business process is modified to fix the problem.
    Now my main problem is the 2nd scenario which I will explain better here.
    In our scenario MTO items when placed in a Sales Order triggers a Production Order.
    This Production Order needs to be confirmed for each operation & at the final step the MTO item is pushed into the inventory.
    The Production BOM & the operation overview for the MTO item is as shown below:
    E.g.
    Operation Overview:
    Operation            Work center                  Control key
      0010                    Prod                               PP01
      0020                    Pack                               PP01
      0070                    Confirm                          PP03
    Routing:
    Item                Material             QTY        Unit            Operation
    0010               ABC                  100         G                0010
    0020               XYZ                  10           G                0020
    Now as shown above, the business users who produce the MTO item will confirm operation 10 & consume raw material ABC at the Work Center = Prod.
    Then at the Work Center = Pack, the packaging material is used & operation 20 is confirmed.
    Finally after the packing is done, at the Work center = Confirm, the operation 70 is confirmed when the MTO item is receipted in the Inventory.
    Before it is receipted at the Confirm work center, a user monitors the quality of this produced item. If it is good only then it is receipted in the inventory.
    Now depending on when the Sales Order is fulfilled, this MTO item will be shipped.
    Issue:
    Now when the MTO item produced passes thru the high level quality check, it gets receipted in the inventory at operation 70.
    However in a case where the some or all the qty of the MTO item ordered doesn't pass the quality check, they will be scrapped physically.
    Thus my understanding is that e.g. 3 qty of the MTO was ordered & 1 got rejected, then the user confirming the step 70 will enter YIELD = 2 ea & Scrap = 1 ea and do the final confirmation.
    This means that the original demand of 3 ea is still incomplete. 1 Ea still need to be made as a Sales Order Stock.
    Now the function needed is that the system should automatically generate a Production order for the remaining 1 Ea as a Sales Order stock.
    I dont know if this can be achieved by receipting the 1 EA as REWORK on the CO11n screen at operation 70.
    Also I am not sure if Production Order Split case would work in this case.
    I would need some input from all the PP gurus. Any solution which be close to what functionality is needed will be greatly appreciated.
    Thanks
    Vin
    Edited by: vinit parkar on Mar 3, 2010 5:04 PM

  • Production order confirmation in co11.

    In co11 ,   I want to post balance qty while doing the production order confirmation.  actually total qty issue is 10 but confirmed qty is 5 , here balance qty 5 shud be posted automatically while save the confirmation.

    solved . developed the custom pgm.

  • Serial Number. Production Order Confirmation. GR. UD. Sales Delivery

    Hi Gurus,
    Please help on this issue to get any user exits .....
    As part of Serial number management, we have a certain issues on serial number confirmation, goods receipt from production order and quality inspection with UD.
    Master data:
    Finished product material master, Workscheduling view, Serial number profile maintained " ASRN"
    Process flow:
    1) Avalon Specific Serial numbers generation for finished goods through production order release status.
                  (A11206000001)
                                        A  - Avalon
                                        1   - PCB Unit 1
                                        12 - Year 2012
                                        06 - Week
                                        000001 - Running serial number for the week.
    2) Production order confirmation through CO11n transaction.
    3) Production order Goods receipt through MIGO transaction against order.
    4) Quality Inspection with Usage Decision through QA32 transaction.
    5) Goods Issue for Delivery.
    SAP Product Error:
    1) System does not track and control the operation wise confirmed serial numbers during order confirmation.
    2) System does not track and control the finally confirmed serial numbers during order goods receipt.
    3) System does not track and control the last goods receipt qty in Usage Decision.
    4)  For semi finished product, if we maintain serial number profile in workscheduling view, system is not showing goods issue material list in Co11n transaction for the finished goods.
    5) Interfacing the serial number reading scanner with SAP,  is not working without entering material number and serial number manually.
    6) System does not tracking and controlling the last Usage Decision done serial number during Goods issue to Sale order Delivery.
    Regards,
    Santha

    Hi Santha,
    This is a bit vast, but I'll try to address at least some of the issues:
    1- serial number in operation confirmation is not possible, for the reason that serailization is part of stock management, and as WIP in an order, this is not stock yet. Actually you cannot confirm the manufactured material either, and those 2 go together.
    For tracking specificly WIP, there's something called WIP batches; you may look into it to see if you can use it.
    2- during GR system will propose those SNs that you have defined for the order at release or creation.
    3- ?
    4- GI in CO11N is provided only for BACKFLUSHED material components. Serialized materials CANNOT be backflushed.
    5- You can use a barcode reader to read the serial number (instead of keyboard entry) when cursor is on the right field in the respective screen.
    6- ?

  • Equipment as PRT's during Production Order Confirmation

    Hi Gurus,
    During Production Order confirmation I cannot see whether I have consumed equipments as PRT which are attached to operation.
    The operation is showing CNF status as well the Order.
    How can I see whether which Equipment was used for each operation since there can be more than one equipment as a PRT's for a single operation.
    Regards
    Nilesh

    I use Production Order confirmation hence saw it in CO14 and checked that PRT's are in PRT REL status..I guess this is what you mean to say right??
    Thank you so much for your response.
    Regards
    Nilesh

  • Header qty is less than the operation qty.

    To certain production order header qty is less than the operation qty. Please advise me.

    Dear,
    Base Quantity - Quantity of the material to be produced to which the standard values of the operation refer.
    Operation Quantity - Quantity planned for this operation.
    Base quantity and operation quantity may not always be the same, if we have partial lots delivered during the sequence of operations, the operation quantity will be equal to the lot delivered during the operation.
    Base quantity is dependent on the BOM, where it signifies the total quantity of output after using the components of certain quantity.
    In routing, you neeed maintained there operation quantity, and unit of measure of operation quantity accordingly with base quantity unit of measure.
    Check up the Processing formula used in the Scheduling tab of Work center (Use SAP002 = Machine * Oprn qty / Base qty / No. of splits)
    Hope clear to you.
    Regards,
    R.Brahmankar
    Edited by: R Brahmankar on Oct 7, 2008 11:37 AM

  • URGENT: Prob with Production Order Confirmation

    Hi Gurus,
    I have a problem with Production Order Confirmation.
    When I am confirming a Prod Order and if the components present are more than '999', then error is being thrown and Material Document Number is not being created.
    I want to split the records into 500 slots and pass them at a time for the creation of the Production Order so that it doesnt throw me an error while creating a Material Document No.
    While saving the Production Order confirmation order, it should split the records into 500 slots each and then create Material Document No for each slot.
    Can anyone please help me out in this regard, how to solve this.
    Thanks & Regards,
    Harish Kalla

    Hi Harish,
    This problem is addressed in OSS Note : 36353
    The Symptom reads like this
    ==========================================================================
    When you post documents using the AC interface (from SD, MM or other applications), items appear in the FI document which are identical in all or in almost all fields.
    This can also cause error message F5 727 ("Maximum number of items in FI reached"). The system issues this error if more than 999 items occur in an FI document.
    ===========================================================================
    This Note is an elaborate one..
    Hence, go through this and ask your FI Consultant to help you in this regard.
    All the best..
    Regards,
    Siva

  • Production Order Planned Qty

    For all items in Production Order, Base Qty column multiply by Planned Quantity field at top (a constant field) equal to Planned Qty column. However, certain items in one production order shows different Planned Qty, the numbers don't add up. I looked in the PLD template and it is pulling planned qty information straight from WOR1 - PlannedQty. I am curious, where does the calculation occur? Is it better to apply calculation instead of using the WOR1 field?

    In my case, some items in a particular production order shows the wrong quantity in Planned Qty. Can I assume it's a bug in SAP 8.8? I can only found one order with this problem. The rest seem fine.

  • Cancellation of Production Order confirmation (CO13) not generating TR/TO

    Hi,
    We are facing a typical issue in the PP-WM interface. When we create an order and confirm it (partial confirmation), the Goods movement happens (261 mvt type) as desired and the TO is created and confirmed in the background.
    But, when we try to reverse the movement type (cancelling the production order confirmation using CO13) then there are no TRs or TOs generated in the background (for movement type 262).
    When I manually try to post a material document for 262 movement type, it creates a TO in the background (as per the configurations that I maintained) but this does not happen when movement type 262 is called using PP interface.
    The movement type configurations are all done for Automatic TR and TO generations - this works with normal IM process (when we manually post using MB1A transaction) but not with the return Goods movement happening with PP.....here, the material comes back to the interim storage type 914. We then need to create a TO manually and confirm it to take the stock back in to the original storage type and bin.
    We want that when a process order confirmation is cancelled then the materials should be posted back in to the original storage type and bin (from where the material was issued against the order).
    For Info: COGI shows no errors during the 262 movements, also, material document is generated for 262 movement type but no TR/TO generated.
    Is there any configuration that we have missed?
    Thanks and Regards,
    Shankar

    Hi,
    Yes, you are correct in the understanding that the system creates quants in 914 when the production order confirmation is cancelled. But, it does not generate any TR or TO in the background to post the stock back into the original storage type.
    Can we not use the put away strategies so that the system determines where to place the material? My query is that despite all the configurations for automatic TO creation and confirmation for movement type 262, it does not generate a TO (or TR) in the background when a production order confirmation is cancelled using CO13.
    However, if I manually post a material using MB1A for 261 movement type and reverse it using 262, it generates a TO and confirms it as per the setting in configuration.
    The same thing does not work when we run it through PP (CO11N and then CO13).
    Any suggestions on how to approach this and where to check for missing configurations?
    Thanks and Regards,
    Gaurishankar

  • Need help on Production order confirmation cancel issue

    Hi,
    I need your help regarding Prduction Order issue.
    We have created Production Order and issued raw materials and we done paritial confirmation also. Now the order status is PNCF.
    After that we notice that it was wrong confirmation so we went CO13 we cancel those confirmations.
    But in our zprogram still those order is showing as paritial confirmation order.
    I need in which SAP table confirmation status stored and what will be the production order status after cancel the confirmation.
    and in which table cancel production order confirmation data will be availiable.
    please guide me
    sateesh

    HI,
    There is No Standard Status for Reversing or cancelling the Confirmation.
    Generally, When you confirm the status PCNF or CNF gets active.
    When you reverse it theybecome inactive.
    also let us know, whether You cancelled or reversed the confirmation or revesed the GI postings.
    If you have reversed the GI postings using Reverse Movement type or Materail documents, it is possible to have the PCNF order status unchanged.
    Regards
    Ratan
    Edited by: Ratan on Aug 28, 2009 7:23 PM

  • Activity monitor says I have 1 -3% of System Memory free, yet CPU usage shows less than 10% total of all processes

    Activity monitor says I have 1 -3% of System Memory free, yet CPU usage shows less than 10% total of all processes

    I think you should review what you wrote. There is no question, hence, my reply. I can't tell by the AM listing what applications are using memory. You need to click on the Real Mem column once or twice to display in descending order.
    Aside from what you see in AM, what exactly is your problem or perceived problem. You are very low on Free Mem at the moment the screen shot was taken. Those displays are not depicting your computer's instantaneous memory usage.
    About OS X Memory Management and Usage
    Using Activity Monitor to read System Memory & determine how much RAM is used
    Memory Management in Mac OS X
    Performance Guidelines- Memory Management in Mac OS X
    A detailed look at memory usage in OS X
    Memory Usage Performance Guidelines- About the Virtual Memory System
    Understanding top output in the Terminal
    The amount of available RAM for applications is the sum of Free RAM and Inactive RAM. This will change as applications are opened and closed or change from active to inactive status. The Swap figure represents an estimate of the total amount of swap space required for VM if used, but does not necessarily indicate the actual size of the existing swap file. If you are really in need of more RAM that would be indicated by how frequently the system uses VM. If you open the Terminal and run the top command at the prompt you will find information reported on Pageins () and Pageouts (). Pageouts () is the important figure. If the value in the parentheses is 0 (zero) then OS X is not making instantaneous use of VM which means you have adequate physical RAM for the system with the applications you have loaded. If the figure in parentheses is running positive and your hard drive is constantly being used (thrashing) then you need more physical RAM.
    Adding RAM only makes it possible to run more programs concurrently.  It doesn't speed up the computer nor make games run faster.  What it can do is prevent the system from having to use disk-based VM when it runs out of RAM because you are trying to run too many applications concurrently or using applications that are extremely RAM dependent.  It will improve the performance of applications that run mostly in RAM or when loading programs.

  • EPM 2013 Report is displayed as cut off and shows less than half the width of the report in IE 10 and IE 9.

    EPM 2013 Report is displayed as cut off and shows less than half the width of the report in IE 10 and IE 9.  This issue occurs for some users only.I tried the same url in google chrome and is working fine.
    Can you please help.
    Please find the attached screenshot.

    Hi BJ1986,
    According to your description, I think this issue is caused by the IE browser that runs the report. To trouble shoot this issue, I suggest that we can try to clear internet temporary files, cookies and others in IE browser. And also add this site
    as a trusted site in IE browser to check this issue again.
    If this issue is still existed, it can also be occurred due to the setting or third party add-ons of Internet Explorer (IE). In this scenario, you can try to run IE in compatibility mode to check the issue again. Or I suggest that you can refer to the
    steps below to troubleshoot the issue:
    Click Tools -> Internet options.
    Switch to the Security tab, click Local intranet, and then select Default level.
    Switch to the Advanced tab, and click Restore advanced settings.
    Temporarily disable third party add-ons. For detailed steps, please see the link below: 
    http://windows.microsoft.com/en-IN/internet-explorer/manage-add-ons#ie
    Hope this helps.
    Thanks,
    Katherine Xiong
    Katherine Xiong
    TechNet Community Support

  • Change Work Center during production order confirmation

    Dear All,
    I must to modeling this situation:
    I created an production order. In routing I used an work center A.
    After I confirmed a half of quantity, the work center A was damaged and I must to change it, with the work center B.
    The system allow this change, but when I checked the costing, the situation isn't real. The system counted the costs just for the work center A, and no for work center B.
    My question is: it's possible to change the work center, during production order confirmation and the costs updated with new cost?
    Thank you for your answer!
    Regards,
    Marian

    once a Order is released, the Process order detaisl for that order is frozen.
    however if you want to do it, change the order status to CRTD after reversing the Movements done.
    Do READ MAster data , this will copy the new Work center , redo the previously done Moevements.
    if the change is long term.
    or
    Just manually add the new work center and do the processing. if the change is temporary.

  • HT1848 On itunes, when synced to my pc, I show less than half of the music that is on my iphone 4. How do I get all the music onto my pc?

    I am about to scream if I don't figure this out or just decide to leave Apple and get a Galaxy phone. On itunes, when synced to my pc, I show less than half of the music that is on my iphone 4. How do I get all the music onto my pc? I have read many forums and tried many things, but apple/iTunes is not intuitive at least not on a PC. When I go to devices it won't let me select "transfer music". It's grayed out. Why is this and what can I do? I'd like to delete some of the music off of my iPhone but don't want it gone forever. Pleae help.

    Thanks Turingtest2,
    I appreciate your response. I have done all of the things mentioned, but still when I click on "devices", the "transfer music" option is still not selectable. I see it, but can't select it.  I am running Windows 7 on my PC.
    However, one thing I read makes me take pause. At one point I did erase my computer back to factory settings using the mirrored image. We backed up all information and put the important stuff back on, but I don't believe we did anything with iTunes, so it's a possibility that the music that is in my library now, may only be music I have purchased since then. But, (thinking out loud) that was a while ago and I am pretty sure I have purchased more music than what is in my iTunes library, since then.  Maybe I will approach it from that angle and see what happens.
    It just doesn't make any logical sense that syncing goes from computer to device. Ostensibly then, my iPhone would only have the music that is on my computer after syncing and that is not the case. I still have all my music on my phone. I can see the new music that's on my phone get added to my iTunes library when I connect, which would make one think that syncing occurs both ways. I don't know. It's maddening. Maybe I should just follow my husbands advice and go to an Android. LOL. Or maybe I will take my laptop and phone to the Apple store and make them figure it out. Ha.
    If you have any thoughts about this, let me know. Thanks again.

  • Measuring point update by production order confirmation

    Hi friends,
    I created a prt as equipment and assigned it to the routing. I created a production order and when i confirm the same i am getting following error as:
    Document MeasUnit has a different dimension to the characteristic unit
    Message no. IR071
    Diagnosis
    The measurement unit on creation of the measurement document must have the same dimension as the measurement unit of the characteristic of the measuring point.
    In this case, the measurement unit % does not suit the character unit EA of the measuring point 103.
    System Response
    Processing will not be continued.
    Procedure
    Use the possible entries help.
    Please suggest the solution.

    Hello Sir(s)
    i have gone through entire post for the subject related to measuring point auto update from production order confirmation.  I have tried the same but i dont know what i am missing.
    if i put some value like 1 or 2 and appropriate UOM then only my measuring document is being updated with the same value not with the actual confirmed quantity..  i have already maintained standard formulla in prt view.
    my basic requirement is to get actual value of produced quanity as counter update. means if 20 pieces have been produced and confirmed in co11n, then counter must bhe updated with the value of confirmed quantity.
    please advice what value should i put as usage in routing master to get actuall counter update.
    Will Highly appreciate your quick reply.
    Snapshots
    Regards.
    Mohammad.