Dear gurus,
Iam using change number to create Inspection plan. System is displaying always Valid to date as "31.12.9999". But as per business requirement of the client, validity period is 3 yrs. How can i change the date.
1)     Can i cahnge at change number level?
2)     or At inspection plan level?
Iam giving you the details of the field at Inspection plan level.
Transaction: Qp01
screen no: 1200
screen Field name: PLKOD-DATUB 
Program name: SAPLCPDI
Package: CP
Pls guide me how to get valid date as 3 yrs plus valid from date.
thanks and regards
Venkat. V

Hi,
For change number effetivity we can think of another alternative.
1) Create one change number and create a inspection plan with group counter 1.
2) Create another change number and create another inspection plan with group counter 2.Second change number   
     validity should be from 01.01.2012
3) When a goods receipt is done system automatically assigns the inspection plan with group counter 1 till 31.12.2011.
4) When a goods receipt is done on 01.01.2012 system will create the inspection lot with status created as there are
     2 inspection lots from 01.01.2012.
5) Go to the first inspection lot and change the status to 1 and assign second inspection lot which is valid from 01.01.2012.
CSN

Similar Messages

  • Inspection Plan - Change order date Combination issue

    We are facing 1 issue in our system.
    The Inspection plan assignments with new change orders is not assigning the correct inspection plan.
    Example:
    Plan                       Change Number               Valid from Date
    1                              CO-1                                1/01/2007
    2                              CO-2                                1/01/2008
    3                              CO-3                                1/01/2010
    The plan selected when Change order CO-2 is cut in, is plan 1 but should be Plan 2. We believe the date on the CO does not drive the selection of the most current plan. When plan 3 is implemented after plan 2, Plan 2 is selected.
    Any one has faced this kind of issue in your exp?
    Edited by: Tom_Eric on Apr 28, 2010 10:49 PM

    No reply

  • Inspection plan validity change

    Dear Gurus,
    I have uploaded my inspection plans with valid from date 01.07.2010, due to certain reasons I need this valid from date to be earlier, how can I change it?
    Regards,
    MaX

    Hi,
    functionally it is not possible to change the valid to date. but technically , by table entry it possible. table name plko and field datuv.
    partha

  • Inspection Plan status (Header details)

    Hi
    I want to change Inpection plan status(Inspection plan -Headerdetails)  from 4 to 1, this I want as a mass process
    Can any body help
    Regards
    Vivek

    Hello Vivek,
    Follow the steps,,,
    Run CWBQM
    Enter Current Working Area as "Q_TSK_000000000010"
    Press Enter
    Select the Task list Type as "Inspection Plan"
    As you need to change it for all inspection plan in the data base, don't use any other filter criteria just Press "F8" to load the task list.
    In the next appearing screen EWB: Headers Overview the 18th column is for STATUS.
    Select this column
    Then Select all line items (Short cut key to do such is (Ctr+F2)
    Then follow the path Extras--->Mass Change
    Enter New Value here
    Check and then Execute.
    Regards,
    Shyamal

  • Master data changes not updated in Inspection Plan- QP01

    Hi
    We created all the QM master data . After that we did some changes in inspection chars and in the sampling master data.but the values are not reflecting in the Inspection plan . How to update the changes in the inspection plan. We are trying to find indIvidual as well as Mass update
    Any input will he highly appreciated
    Thanks
    JJ

    Dear JJ
    Another easy method will be maintaining MIC as referenced mic. instead of maintaining it as complete copy model you can make it referenced. any changes in the mic can be updated automaticalyin the inspection plan using the referenced functionality.
    The issue being wherever the mic goes will be changed,
    Regards
    gajesh

  • Function module to download Inspection plan data

    Is there any function module to downlaod the data of PLKO and PLMK tables data i.e. Inspection Plan data.
    Thank you.

    Hi,
    To downlaod PLKO data use this FM CM_PLKO_READ
    and for PLMK try this one QPAX_PLMKB_READ_FROM_PLKO.
    Hope it helps.
    Regards
    Hiren K.Chitalia

  • BAPI INSPECTION PLAN

    I am Creating the Inspection Plan by using the BAPI's but
    (BAPI_INSPECTIONPLAN_CREATE) i got this error message.
    here FU26FR is the INpection method and master inspection characterstic.
    the error related to inspection plan charactrstics
    how to over come this error please tell me.
    for good answer i will give the reward points
    message :
    Specify a valid data import mode for master inspection characteristic FU26FR

    Hi,
    Check the Bapi documentation....
    Enter the reference for the master inspection characteristic in the field CHA_MASTER_IMPORT_MODUS (mode for reference to the master inspection characteristic).
    "L" for reference
    In this case, the master inspection characteristic must be completely maintained. In parameter INSPCHARACTERISTIC, you must only enter data in the fields, in which data cannot be transferred from the master inspection characteristic.
    "C" for copy (flexible reference)
    In this case, the data is copied from the master inspection characteristic to the inspection characteristic.
    "N" for creating a flexible reference
    In this case, no data is transferred from the master inspection characteristic. You must enter all fields in parameter INSPCHARACTERISTIC.
    For "L" or "C", you can copy the control indicators for the inspection characteristic directly from the master inspection characteristic. For "N" or if you do not enter a master inspection characteristic, you must enter the control indicators individually or enter a key for the control indicators in field PRESET_CTRL_INDS_KEY, if you have defined this key in Customizing.

  • Inspection Plan

    I am creating the  Inspection Plans by using the BAPI_INSPECTIONPLAN_CREATE.
    I got the below errors please provide the solution for this.
    1)The valid-from data has been set from today's date
    2)Enter another operation number
    3)Enter another operation number

    hi rk.....
    First One is just a Information message and last two is because of invalid activity or operation id entered wrongly...
    Also u can have a look at my code for uploading inspection plan using bapi....
    [Click here to view code...|https://wiki.sdn.sap.com/wiki/display/Snippets/ABAPProgramtouploadQMInspectionPlanUsingBAPI]
    Also take a look at the template and sample data file attached at the given link...
    Regards
    KArthik D

  • Inspection Plan/Revision level

    Hi PP Gurus,
    I have a Problem in Inspection Lot.The system is not reading the new Inspection Plan.
    The material is assigned to a Revision level with valid from date 10.12.2007 and the earlier Inspection Plan(Group 21) was also created on 10.12.2007.Now this inspection Plan( Group 21) is deleted and New Inspection Plan(Group 100) is created with the Valid from date 10.04.2008.
    I have created an Inspection Lot dated 12.04.2008, Now the system is not reading the new Inspection Plan(Group 100).And the system is giving error "No Insection Plan found" while recording result on the inspection lot.
    We cant change the material ECO revision date as this would contravene our traceability record and  since, the Revision Level is maintained at Global level so cant afford this to change for other Plants.
    Kindly help me to assign the new Inspection Plan to the Inspection Lot.
    Thx in Advance
    Regards,
    Rakesh wade

    Hi,
    I do not know the impact of revısıon level on İnspaction lot.
    But, with reference to the Revısıon Level only the Confırmation wıll work both in Descrete and aswell as in REM.
    Say ıf yor Revesıon Level ıs AB, and the date ıs 01.03.2008, then during confirmatıon the sytem will explode the BOM with referenec to this Date.
    It may be possıble that there may not be any BOM available on that date then there wıll not be any Components suggested for GI or backflush.
    Probably you can corelate the same thıng to your ınspectıon lot... ( inspectıon lot not available etc..)
    Hope thıs helps..
    Regards,
    Siva

  • EHS - QM Interface. Inspection Plan Creation

    Hi all,
    Has anyone used EHS-QM interface before?
    I am tryng to create inspection plan characteristics from specification database and it is not working properly.
    The customizing that I have done is:
    1. We have Specify Environment parameters (i.e. EHQMEP_CONTROLKEY)
    2. We have verify Product Safety, Quality Management and Material Management pre-requisites
    3. We have filled Mapping Table (CGQM) with and standard value assignment type (SAP_EHS_1013_016) and a class characteristic (SAP_EHS_1013_016_EC_TEMP)
    Then in CG02 we have:
    1. We have completed a specification in CG02 with Usage QM and a Validity Area
    2. In CG02 we create a inspection plan and select rating QM or Group all ratings
    3. No Inspection Plan to be created is available
    Any clue on what the problem migth be?
    Best Regards,
    Alberto
    Message was edited by:
            Alberto Garcí

    Dear all
    1.) it might be helful to open a new thread regarding your topic in parallel EH&S FORUM
    2.) To my knowlegde witH SAP ECC 6.0 EnhancementPackage 5 EH&S QM interface has been enlarged. I am sorry. My inquiry in internet regarding that was not successful. PLease check SAP Markeptplace as I am pretty sure that there was a change/enhancement
    3.) we are not using this intertace but have played around a little bit.
    The interfaceh EH&S => QM is in my opion "not well" designed. First of all:
    a.) you need to trigger it manually (use of transaciton CG02)
    b.) to my knowledge no change in EHST is tarbnsferred automatically to QM; e.g. if flash point has changed or density etc. the user is in charge to make sure that the data will be tranferred into QM
    c.) the "trick" to map validity areas to plant (excatly it is a plant plant mapping)  is not goiod approach. Reason:
    Normally a density is defined with usage "PUBLIC/EG_WORLD). The meaining is:
    1.) can be used e.g. in Materiaql Safety data sheet (public document)  and other EH&S document
    Now you can use (you must not) priorized ratings (e.g. rating QM does have higher priority as PUBLIC) in EH&S logic to transfer data from EHS& to QM but to my knowlegde you must make the "plant" <=> "PLant" by "hand" using furtehre validity areas.
    That means fi you would like to use density 1 g/cm3 for all plants (and the QM inspecions plans) then you must enter any plant of relevance as validity area to map that to the inspection plan (which to my knowlegde once again is plant specific).
    I am not sure if the EH&S QM interface supports you really to "start" immedeatly the generation of inspection plans regardgin all plants,. The link to SAP online help above will lead you directly in the right chapter.
    Regarding phrases: sorry the analysis of thsi interfaxce has been done long ago; but phrases are "textes" which can have "any length". It might be a problme to map that to QM Plan. If you check that link above you will lead to this statement:
    n the Function module column you can use a function module to define yourself how specification data is to be converted to an inspection characteristic.
    As an example, use the function module EHQM09_BUILD_CHA_NO_COMP to develop analogous modules.
    Therefore if necessary you could exchange this fuinciotn module by a customer specific one.
    May be this helps
    C.B.
    PS: Regarding changes in EH&S QM Interface ECC 6.0/EnhPack 5: : may be refer to http://www.scribd.com/doc/58761766/37/Quality-Management
    PPS: may be of interest could be: http://www.consolut.com/en/s/sap-ides-access/d/s/doc/Q-EHQM0904

  • How to map revision level materials to already created inspection plan?

    Dear All,
    I have created single inspection plan for many existing raw materials. Now it has been found that each raw material have different revision level as well as valid from date.
    My inspection plan is created on 02.07.2014 and each raw material has different revision level with valid from date which is also very old (like 11.03.2012 for revision level 09).
    My Requirement is:  how to correct my inspection plan?,  so that it will work for each assigned raw material and there will not be any material revision level wise problem created for the inspection lot so that my inspection lot should be created in REL status in QA32 transaction i.e. inspection lot is assigned automatically as per standard SAP functionality.
    Thanks,
    Narresh

    Hi Amol,
    Thanks for your reply.
    In this business scenario, we are not creating inspection plan for each raw material because there is similarity in inspection for 40-50 raw materials and total number of raw materials are around 500. This will be very difficult and unnecessarily data creation in the system.
    As per my understanding revision level is for material master revision and if material master changes then how it affect so much on inspection plan? also is it means that for every revision in future we will have to create new inspection plan?  hence I believe that if I will make back dated inspection plan for raw materials then it may work. Is my understanding is correct?
    Expecting much better solution from QM experts.
    Thanks,
    Narresh

  • Inspection plan not found

    Hi,
    no inspection plan is found for inspection lots created with origin 04 or 08; but they are found for 89.
    I already checked:
    - task list usage assigned to i type in customizing
    - material set up for 08 and 04 with i plans
    - validity date changed in inspection lot according to i plan
    Any more ideas?
    Thanks.
    Jessica

    Well. what you have to go by is what the actual inspection lot is telling you.  If it says it is looking for a task list usage of 3 then it is looking for a task list usage of 3.  So there must be another reason why its not selecting it.  I'm assuming you tried to manually assign the plan in the lot and it failed.
    In the plan header, did anyone set a quantity value for the plan?  At the bottom of the header you can specify a quantity range and then the plan is only used for lots within that quanity range.  (89's aren't stock relevant this might not be an issue, hence that might be why they work).  Using this field you can set up multiple plans.  One for receipts less then 100 units. One for receipts from 100 -1000 and one for receipts > 1000.
    I'm wondering if the lot size and plan size are incompatible?
    Make sure you don't have a 'preferred' inspection type being used that doesn't have a different usage. (Of course then the lot shouldn't show usage 3 in it then).
    There is no reason you shouldn't be able to use one inspection plan usage for all your inspection types.  I've done this before. Many clients want the 89 inspection and 04 inspections to utilize the same plan.
    Craig

  • Regarding Inspection Plan

    Hi All,
    Need clarification regarding Inspection Plan. We observe that in our company the inspection plan are created double record for a material. Actually we have two z-tcodes for creating  inspection plan. The 1st is scheduled job  which creates inspection plan automatically and with the second tcode ,we create inspection plan manually.
    I would like to know what is the impact if we have 2 inspection plans for the same material. May i know why the program is creating double inspection plan though already one inspection plan is existing.   Please suggest us how to avoid this.
    Thanks in advance.

    Hello Aditya,
    first of all you should check the following:
    The plan header (PLKO) has the following key fields Client (MANDT), Plan type (PLNTY), Plan number (PLNNR), Plan alternative (PLNAL) and Plan counter (ZAEHL) if you have created identical entries this would lead to a dump with DUPREC.
    Then you have one other tables you should take into account:
    Material plan assignment MAPL
    and finally check the validity dates and if change numbers are used.
    As long as there are no 2 identical plans, this shouldn't lead to any problems.
    Maybe this is the information you need.
    Regards
    Isabelle

  • INspection plan selction

    Hi,
    I want a clarification. A material is having a Inspection plan -task list with 3 group counters. When the inspection lot is created against process order, what is the group counter will be selected.
    How is selection triggered to select the inspection plan.
    thanks and regards
    Muruegsan

    Hi,
    If the following fields are same for all three inspection plan, then it will show all three inspection plans and you have to pick one manually.
    If the following fields are same for all the group counters,,,,,,,
    - Lot size
    - Usage
    - Status
    - The valid from date is prior to the inspection lot
    - Material is assigned to all three.
    And if any one from above fields differ from the rest will be filtered accordingly.
    r.g.
    If the Usage is not matching with the inspection lot for  group counter 2, it will filtered
    If the Status is not released for group counter 3, it will be filtered
    Now according to this example only group counter 1 is eligible to get attached will the lot, so it will be attached.
    I hope it clears your understanding, if ant further clarification required pls revert.
    Regards,
    Shyamal

  • Seasonal Inspection plan

    Hi Friends,
    1.   My clients requirement is he wants the inspection plan seasonwise. as the tolerances of the characteristics are changing seasonally.
    2 Whether identical inspection plan with periods validation possible?
    how to map this senario?
    Regards,
    Anil Mahajan

    Hello Anil,
    you could maintain this scenario using the Change management, using the engineer change management you can plan changes of an inspection plan, or characteristics in the future. Accordingly if you change the plan using the change number these changes will get active when the change number is made valid.
    The positive effect of this is that you can track all plan changes and view the valid plan to a certain date.
    Regards,
    Isabelle

Maybe you are looking for

  • 2 Questions on Maps in iOS 6 on iPhone 4

    I know that certain iOS 6 Maps features are not available on on iPhone 4, but my questions are: 1. Is there a way to add the Maps to the lockscreen as advertised, or is that a 4s and above thing as well? 2. Is there a way to plan a trip with multiple

  • Date format in obiee reports

    HI guys i got two obiee server running in our env . both are identical . on one server when ever we rite any report with date column in it it comes up with dd/mm/yyyy output on another server if we right any report all the date column comes with dd m

  • I get error 2324 when trying to update itunes.  Suggestions?

    I get error code 2324 when trying to install the latest itunes.  Any suggestions?

  • Calling procedure with 2 parameters from a dynamic link

    I have just another question- I have a procedure testing_del_archive which is being called with 2 parameters...from a dynamic link in my SQL Query. The following is my code.... SELECT re.report_exec_id, re.exec_userid, NVL(re.batch_exec_date, re.begi

  • Should i buy kollection or webassist super suite

    hi, i going to buy either kollection or super suite to help me with my dynamic web development as ive heard tney are the top 2. i dont know which one to get though, and ive noticed super suite is more than twice as much! i know i should learn php and