KANBAN and Operation level confirmations

We are planning to use the SAP KANBAN. Our company uses SAP 4.7.
Currently they have visual KANBANs opearting in the factory.
We plan to use KANBAN with Production Order strategy. The problem is that ,  we have multiple opeartions within one KANBAN cycle.  And question is,  can we use SAP KANBAN with milestone confirmations? So that if KANBAN cart moves from one opeartion to another, opeartor can scan the barcode  or by some other means can confirm  that opeation  as a part of KANBAN and then  with final confirmation posts the goods receipt of finished product.
Any ideas?

Hi Mankai,
1) std SAP KANBAN on a status change do the final confirmation of the production order?
Answer
Yes, when you change the KANBAN status from Empty--> Full, then production order confirmation and GR against the production done automatically.
2)  when status is changed from inprocess to complete, can SAP do the confirmation of the production order?
Answer:
When you made KANBAN bin Empty, then system triggers planned /production order. When you start actual manufacturing
activity then scan the bar code and change the bin status from Empty --> Inprocess.
So when you see the kanban board you can visualize the what are the production order execution activity are actually started.
after completing the manufacturing activity then scan the bar code and change the bin status from Inprocess --> Full, then  system will do the confirmation of production order and GR done automatically.
First you define the status as Empty --> Inprocess --> Full.
Regards,
Vijay

Similar Messages

  • Why Template, request and operation level approval from 11g?

    Hi All,
    I''m very new to OIM 11g and could not understand the logic behind having three categories of approval workflow, sucn as Template, operational and request level approvals? In 10 g, on the contrary, we can achieve multiple level approval using one approval process against a resource object. Having said that, i think we can also achieve a multi level approval in one BPEL process using the serial or parallel type of approval. So, a single approval process, say request level approval process can be configured to catered to multiple level of approvals. If this is the case, i could not figure out the reason behind the availability of 2 further categories template and request level approval. Can anyone please shed light on the actual usage with a context and also render reference to a 10 g functionality for these approval categories.
    Thanks,
    Srini

    Request Level & Operation Level :
    Re: Difference requestlevel and operational level
    Template Level : It is also same as Request Level where you can reject the complete request in one shot. In latest version of OIM i.e. OIM 11g R2, you won't find this Approval Level.

  • Cannot attach documents at order operation level in PM order.

    Hi,
    We have recently upgraded to EHP6 and I have activated the EAM business functions including LOG_EAM_CI_6. In my PM work order, on the Additional Data tab, I can see the "Document Assignment" section at the bottom. Here I attach an existing document and choose Assign to Order. Then I attach another existing document and choose Assign to Operation (0010). After saving the order if I go back into it (IW32/IW33). the document assigned to order header is still there but the document attached to the operation disappears.
    I have defined the document type that I am assigning at header level and operation level in Customizing for Cross-Application Components under Document Management --> Control Data --> Define Document Types. I have also specified in Customizing that the assignment to objects PMAUFK (order) and/or PMAFVC (operation) is allowed for the document type of those documents.
    Can someone please advise what's wrong here ? I have to attach/assign docs to operations.
    Thanks,
    Sandy

    Hi Sandy
    Can you please make sure two things:
    1) IMG --> DMS --> Control Data --> Define Document Types --> Select Doc Type ---> Define Object Links. It must be something similar to this one. Without entering CREATE DOCUMENT settings, you may not be allowed to attach a document. That might be causing the issue. If you do not want from within IW31, someone is creating documents then make sure this setting has value =2.
    One more possible reason for this is 1:n field in this same setting. If 1:n is not selected, please read the help for that field and make sure the uniqueness of your document attachment to objects.
    2) IMG --> DMS --> Control Data --> Maintain Screen for Object Link
    For this one make sure that you have a screen entry for PMAUFK and PMAFVC.
    Now if attachment does not work, try creating a document and let us know what is the error message.
    And do you know that there is another way of attaching documents to the operation which is attaching them as PRT. Just select the operation, click on PRT button and select document and attach it.
    I hope this will help.
    Regards
    Savas
    Message was edited by: Savas Yazici

  • Assign role request through code not going to Operational level

    Hi All
    We are trying to assign roles through code using the OIM API's as suggested in the documentation
    "http://docs.oracle.com/cd/E27559_01/doc.1112/e28183/oim_up.htm#autoId40".
    We have 2 Approval policies one is at Request Level (i.e. Auto Approval) and the other is Operational level(Scope=ALL Scope) with workflow, So once the request is getting raised with the code successfully it is getting completed. The expected behavior is that it should go to the approval workflow attached at operational level.
    When we tried to attach a workflow at the request level, the request is going through Approval workflow attached at request level and once we approve at request level it is getting completed and not going to operational level.
    But we will have Request level as auto approved and Operational level with two level of Workflow.
    Thanks in Advance

    Check whether you have configured Request Type in your approval policy properly for operational level approval. In the Rule Components section check whether you have configured everything correctly. Also dont raise the request from system admin login as it will be treated as a direct provisioning request and your approval policies will not be invoked. Login through an end-user and test it

  • BAPI/FM for Confirmation of Production order at operation level

    Hi ABAPers,
    I am using the 'BAPI_PRODORDCONF_CREATE_ACT'for Confirmation of Production order at operation level.
    I am able to pass the Production order number and Active Operation get the confirmation done.
    But the Confirmed Qty is not being updating in AFKO table.
    The 'BAPI_PRODORDCONF_CREATE_HDR' cannot be used for Confirmation of Production order at operation level as there is no Operation/Activity(Vornr) field in the input table. Hence using this bapi confirmation of Prod order can be only at Order level.
    Can someone know any FM/BAPI which can be used for the Confirmation of Production order at operation level(not order level).
    Thanks in Advance
    Ramesh Babu Cikka

    Hi Ramesh,
    Please use FUNCTION 'BAPI_PRODORDCONF_CREATE_TT'.
    This will work as like as T/Code "CO11".
    I hope this will help you.
    Example :
      CALL FUNCTION 'BAPI_PRODORDCONF_CREATE_TT'
        EXPORTING
          POST_WRONG_ENTRIES = '0'
          TESTRUN            = ' '
        IMPORTING
          RETURN             = ZRETURN
        TABLES
          TIMETICKETS        = ZBAPI_PP_TIMETICKET
          DETAIL_RETURN      = ZBAPI_CORU_RETURN.
      CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'
        EXPORTING
          WAIT = 'W'.
    Lanka

  • Auto execution of CO11N using scanner for operation level Prod. confirm

    Hi PP champs
    I am looking for a potential development for my current project and i am sure somebody can help me in this.
    - Automatic operation confirmation for Production Order using the scanner. Client's requirement is that they want to do the operation wise confirmation .If my Prodcution Order print is Barcoded , will it be possible for me to go for Auto execution of CO11N , In which system should follwn the operation sequence also.
    I am having a doubt for the possibility to record the actual time also during a specific operation
    Pl share your valuable inputs for the same..
    Thanks in advance
    BR
    Sumit Sharma

    HI Sumit,
    if I understand you correctly you want to use an external system with scanner to request the confirmation.
    You can use BAPI or IDOC for this I think.
    See transaction BAPI to get a list of all possible BAPIS for confirmation.
    Regards,
    Sabine

  • Error in operation level result recording

    Hi,
    I need held; result recording of inspection type =03 (operation level Quality inspection)
    A product manufacture via three operations (10, 20, 30)
    All operation quality inspection active let operation no-10, all products reject and confirm as rework.
    Next operation level quality record is done but confirmation not allow Reason is operation -10, rework quantity, (Actual quantity is more than planned quantity)
    How to add the quantity after reworks for next operation quality inspection?
    Pl helps me finding the solution.

    Hi,
    As per your more clearence , As per Example  production order Quanity =1, passes 3 operation10,20,30
    Operation=10 require rework as per quality ,
    Operation =20 system raise the error message = Operation =10 rework .
    If want to operation =10 ok Quantity =1 then system raise error messges =Actual quanity more than planned Quanitity
    ( 1 Rework + 1 Ok ) .
    Supose rework order create and confirm then next 20 & 30 operation how complete .
    Real scenerio :- Rework on operation =10 then again Quality check then goes to 20 operation Quality check pass / Rework if rework then again quality pass then goes to next operation level
    I hope under stand my problem
    Need help- please

  • In process inspection - Rejection Booking at operations level

    Hi All,
    Need some help regarding inporcess inspection.
    As we aware about '03' insp type is not stock relevant
    The requirement is , i having operations are like 0010 ,0020 ,0030 ,0040,0050 in Production order in Routing
    Now while operation wise confirmation i want to book the rejection and that needs to get effect on further operation confirmation.
    For example : Suppose I have confirmed 50 TON against operation 0020 , hence at the time of confirmation 0020 i want to book the rejection 2 TON
    Hence while confirming 0030 system should not allow to cofirm 50 TON , system should allow to confirm only 48 TON through CO11N and Some where that rejection has to be display in report.
    Is there any provision in standard to enter rejection at operations level.
    Stock posting not required , Only qty tracking required like operation wise confirmation.
    Please advise to make this scenario success.
    Thanks,
    Abhishek

    Hi Abhishake,
    As in inspection type 03 lot you dont have stock posting option, you can scrap the rejected material operation wise in CO11N at the time of confirmation (Mov Type 551).
    As scraped material will no more in system, you can also look forward for bi-product assignment in bom if you don't want to go with first option.
    Also you can check for early lot creation if can solve the purpose, as in this case you will get inspection lot of inspection type 04 at the time of release of production order and stock will be adde to quality inspection as you do confirmations operation wise.
    Regards/Rohit

  • CO11N - Order and Operation status

    I use co11n to confirm the operation in order. When i do final confirmation of the first operation the order header status changes to CNF whereas it should be PCNF.(operation gets the status CNF)
    Ideally the order status should change to CNF only when all the operations are confirmed.
    Pl let me know the reason for this behaviour of system (ECC 6.0)
    Thanks
    Rohit

    Hi All,
    Check out in this way....
    A confirmation documents the processing status of orders, operations, suboperations and individual capacities.
    You can enter a confirmation
    - For an Opeartion (co11/co11n)
    You have the following options:
    - To confirm quantities, durations, activities or personnel data.
    - To make a confirmation at a particular point in time (for example, at the start of setup or the finish of processing) enter a 
    confirmation.
    - When you confirm time events, the system calculates the required duration. For example, the setup duration is the time between setup start and setup finish.
    - For an Order : CO15
    If you enter a confirmation at order header level, the system confirms all the operations that have a control key in which 
    confirmation is optional or necessary. The quantitiesconfirmed in the operations are proportional to the quantities confirmed in the order header.
    Reward if useful.
    Regards,
    pherasath

  • Operation level Component Assignment

    In MTO scenario with VC and Engineering, the sales order specific engineering BOM is
    derived through VC and around 80% complete at the time of sales order creation.
    Engineering activities are carried out and sales order specific production BOM is derived
    very late in the process.
    So, operation level component assignment is not at all possible in advance.
    need to get different components assigned to different operations at at time of
    production order creation/change automatically.
    Is there any function module,exit or Bapi or some other method with help of which
    operation level component assignment can be done automatically in the production order.

    Hi,
    Just a quick thought:
    If your order is having status CRTD or REL (but without any confirmations, goods issue, settlements) then you can use the Read PP Master Data (Order header - Functions - Read PP Master Data) & this will re-read your routing & BOM. But for this to work for you, the routing should be updated with the assignments.
    So what you could do is start processing your order as late as possible, thereby you can re-read the BOM & Routing as the modifications take place.
    But if this is not possible in your scenario, then i am not aware of a BAPI or a FM which adds components to different operations in production order, you might evaluate writing a BDC program for the same. Anyways will update you if i manage to find a BAPI or a FM for this.
    Hope the above helps.
    Regards,
    Vivek

  • What is a Legal Entity and Operating Unit??

    Hi,
    Could someone let me know what exactly is a Legal Entity and Operating Unit. The definition or explanation in the documentation is not satisfactory or clear. What are the differences between the above.
    And where in the per_all_assignments_f table is the Legal entity stored. I know that the Legal entity is stored in the Statutory information in the assignments screen. Also can someone let me how based on the company code in the organization the legal entity is linked. Where in the tables is this link maintained?
    Could someone let me know the above.
    Thanks
    Shekar.

    Dear Shekar
    what exactly is a Legal Entity and Operating Unit?
    ANS: According the Book or user guide definitions says:
    GRE/Legal Entity: Use this classification to represent the following organizations:
    Ultimate Legal Entity: this represents the enterprise, and typically, the enterprise is the highest (global) level of a business organization.
    Legal Entity: this represents the designated legal employer for all employment-related activities. The legal authorities in a country recognize this organization as a separate employer. In an organization hierarchy, a legal entity may report to an operating company or to the ultimate legal entity.
    Consolidated Legal Entity: this organization acts on behalf of multiple operating companies that are not legally registered, or simply on behalf of the enterprise in a country.
    See Shekar the Legal Entity is taken under Classification is we know that the organization is going to show the Taxation to the Government. where as if u take typical UAE countruies here every store is an LLC and they submit the taxing for every store or shop.
    Where as Operating Unit is generally used for the different lines of business which are under that Business GRoup
    Say for an Example:
    ABC is the Company name and that has its root in UAE, Qatar and Oman
    then it is like ABC Business Group > UAE Legal Entity > REtail/Property/Furniture etc are the Operating Units.
    Hope this information is helpful and clear to you or else let me know if you have any concerns.
    Coming to the Company Code we use the code for the Inventory Organizations so that the clients will not get confused with the existing code and the system code so generally we use the same codes for it.

  • PM: change all Orders from sub-operation to operation level

    Hi Folks,
    I've a requirement to change all PM-Orders from Operation-SubOperation to only Operation Level.
    Example:
    Op SubOp --> New Op   (no subOp)
    10__10__-->____10
    10__11__-->____11
    10__12__-->____12
    10__13__-->____13
    10__14__-->____14
    20__10__-->____20
    20__11__-->____21
    Does someone here know, how I can make do this in an easy and save way?
    The only way I see is to make an own report with calling BAPI BAPI_ALM_ORDER_MAINTAIN.
    Have someone another solution
    - SAP-Standard-Report?
    - LSMW?
    Regards

    Hi Raghu,
    Many Thanks for your quick reply.
    Okay ... no LSMW.
    And also no Standard-Reports?
    Do you think, making my own program is the best way?
    Regards,
    Daniel

  • Difference between sales order schedule line and item level data

    Hi All,
    Could you please let me know what is the difference between sales order schedule line and item level data?
    Thanks,
    Ramya

    Hi Ramya,
    Sales order schedule line contains del date, order qty, rounded qty, confirmed qty, delivery qty, schedule line category, purchase requisition etc.,  ie It contains the full details of sales order data with respect to the scheduled line of delivery.  The total quantity of a sales order item can be subdivided into schedule lines that contain the various subsets with the corresponding delivering dates.
    Sales order Item level data contains details of the item in the sales order like material code, net price, net value, UoM, PO details, reason for rejection if any, material group,billing date, plant etc., ie this
    contains the full details of item irrespective of scheduled line.
    Regards,
    R. Senthil Mareeswaran.

  • User status at operation level

    Hi,
    I have created one user status profile and attached in order type. In this profile I have included Operation and Order header as an "Allowed object type"
    My problem is when I am changing  user status at order level , it is not getting changed automatically at operation level.
    Pls suggest me the solution.
    Thanks

    Hi,
    I dont think it is possible .
    A suggestion not sure if it works .
    Assign user status profile operation wise and then have some development to check the operation status and
    then update production order status with same user status you mentioned in operation.
    FM: STATUS_CHANGE_EXTERN will help you to change the user status of order.
    Regards,
    Vishal

  • How to find out the IPS and DS Service Pack and patch levels in windows server.

    Hi,
    I have installed the Information Platform Services 4.0 and Data services 4.0 in windows QA system, now we need to install the same version of IPS & DS  in windows PRD system for this how could we find out the exact version of IPS & DS  ( Service pack and patch levels ) and where we can find the same.
    Many Thanks,
    Sudheer

    Hi Sudheer,
    On a Windows Operating Systems you can check the “Programs and Features” in control panel.You can see a list of both the Name and Version number of SAP BusinessObjects that is installed.
    option 2:
    Open CMC go to Settings. In the properties, you will find the Product Version.
    Please check below SAP notes for more information.
    http://service.sap.com/sap/support/notes/1602088
    Regards,
    Pavan