Hi,
The requirement in my project is the following:
I have a lead time for one material of 10 days. After two months I have recieved 2 PO's, one with 14 days and other with 12 days. The new lead time should be 13 days.
There is any way to calculate this and update the material master?
Thanks in advance,
Guiza

Guilherme,
WPDTC is the TCode that you run to calculate the planned delivery time.  This transaction is available as of version 4.7.  Currently we are upgrading from 4.7 to ECC 6.0 and it still exists in 6.0.  There is a good description at this link in the SAP Help Library.
[http://help.sap.com/saphelp_47x200/helpdata/EN/f3/41b53c4d36265ce10000000a114084/frameset.htm|http://help.sap.com/saphelp_47x200/helpdata/EN/f3/41b53c4d36265ce10000000a114084/frameset.htm]
This program gives you a report of what the planned delivery times are in the info record, material master, vendor, and the calculated PDT based on documents and actual deliveries in the system.  You select the items you wish to change and click the Change Planned Delivery Time button.  You get a pop-up to verify you want to change the values.  Basically, this is a mass change tool for planned delivery time similar to physical inventory transaction MIBC - Set Cycle-Counting Indicator that calculates and changes the material master indicators.
Hope this helps,
Paul

Similar Messages

  • Is there any method to stop rescheduling of the PO Need By date from ATP if there is any holiday specified in shipping calender. The requirement is to update the schedule ship date on Sales Order but the lead time of  Purchase Order should not increase

    We are currently not able to manage schedule ship date proposed by ATP when our warehouse is closed. For example , we would like that ATP doesn't propose any schedule ship date for the first of May , which is a non working day in France. The constraint is that we don't want our purchase need by date to be impacted by the process.
    I tried to closed one day in FR1 calendar and, after testing with order management, it appears that ATP didn't propose the closed day, so that's fine, but, our purchase order lead time was increased of 1 day and this is not what we expected.
    Can you help us to find the right process.
    Thanks

    Hi Sandeep,
    when we try to Rescheduled out the PO and the request is errored out the with the error:-
    Start of log messages from FND_FILE
    reschedule fails
    old date in planner workbench: 19-MAY-11
    new date: 07-JUN-11
    header: 417474
    line: 605652
    po number: 2049031859
    shipment no: 1
    The need by date/promised date in the source instance is not the same as the need by date/promised date in the destination instance.
    In the source instance,
    The need by date is 19-MAY-11, and the promised date is 19-MAY-11
    End of log messages from FND_FILE
    ---------------------------------------------------------------------------

  • User exit or Badi for changing the lead time in ATP check in VA01/VA02

    Hi All,
    Currently, SAP standard functionality takes up the lead times maintained in material master to create the schedule lines in the sales order in VA01. I am looking for some user exiit/Badi/Enhancement point where I can change the lead time. This is somewhat urgent so any help in this regard is appreciated.
    Regards,
    Sandeep
    Edited by: Sandeep Gaitonde on Sep 1, 2011 9:16 PM

    Hi Sandeep,
    These are the user exits will trigger in va01 .
    SDTRM001 Reschedule schedule lines without a new ATP check
    V45A0001 Determine alternative materials for product selection
    V45A0002 Predefine sold-to party in sales document
    V45A0003 Collector for customer function modulpool MV45A
    V45A0004 Copy packing proposal
    V45E0001 Update the purchase order from the sales order
    V45E0002 Data transfer in procurement elements (PRreq., assembly)
    V45L0001 SD component supplier processing (customer enhancements)
    V45P0001 SD customer function for cross-company code sales
    V45S0001 Update sales document from configuration
    V45S0003 MRP-relevance for incomplete configuration
    V45S0004 Effectivity type in sales order
    V45W0001 SD Service Management: Forward Contract Data to Item
    V46H0001 SD Customer functions for resource-related billing
    V60F0001 SD Billing plan (customer enhancement) diff. to billing plan
    Please check this and post .
    Regards,
    Madhu.

  • PO lead time report

    Hi Gurus
    What report can be run to provide the average time taken from PO creation to Goods reciept? IE how do we measure actual delivery lead time
    Thanks in advance
    BR

    Hello
    Thanks for reply.
    IF this is not , could you pl let me know the correct procedure and any standard report for measuring the Delivery time for Purcsase Order based on materials.
    As per your exnample , why a person should enter the delivery date manually , it should should come by system based on PDLT maintained ..
    for tht reason only we are looking to review our materials to update correct PDLT.
    thanks..

  • Lead time issue

    Dear Sap Gurus,
    Is there is any report or in table  to check all the transportation Lead time settings  setting for particular plant  for all customers ? Because i need to upload several new Lead Time  due to the updation in transportation
    I want  compare the differences in system and the new Lead time whih is going to be updated.
    Thanks
    Guna

    Hi,
    Try joining VBAK, VBAP, LIKP and LIPS tables.
    take sales order number, confirmed quantity and document date from VBAK and VBAP tables and populate accordingly Actual PGI date and planned PGI date from LIKP and LIPS table. You can also take BKPF and BSEG if required. From this you will be able to find the time required between punching the sales order for confimed quantity and delivery to the customer.
    Thanks
    Anil Hooda

  • Lead Time Demand on REORDER POINT REPORT ??

    Hi ALL,
    Hope you all doing greate , I am very new in Re order point Inventory Planning Method. I have done all the configuration as;
    i - Creates an Item and assign it to the specific IO where I am selection the Planning method as Reorder point and enter the other paramters under the lead time tab I am seleting the total lead time as 5.
    I have define safty stock as 100  quantity.
    I have configure the Forecast Set and forcast under it which contain an Item with Current Quantity is 1000 now I have call the Report to run so I am getting the rest of the thing except value Lead Time Demand ??
    kindly help me in this regards, I would be so kind of you.
    Thanks
    Mohammad Younus

    Hi,
    There is a standard report that shows the actual average LT compared to the master data definitions. You can also see the details, and even update master data automatically if you want; WPDTC.
    Regards,
    Mario

  • Lead time Report

    Hi,
    Would like to have a report on Lead time between PO Date & GR date.
    Ideally the report should show the PO Number, Date,Material, Mat. Doc Number & GR Date.
    Though ME80FN shows by clicking the PO history, But our user would like to have in a single line item.
    Is there any other Standard Report  to get the above data?
    Regards,
    Vengat

    Hi,
    There is a standard report that shows the actual average LT compared to the master data definitions. You can also see the details, and even update master data automatically if you want; WPDTC.
    Regards,
    Mario

  • Supplier Processing Lead Time with ASCP Unconstrained Plan

    Hi All,
    Is it possible for unconstrained plan to consider supplier lead time constrained which we define in ASL?
    I have defined an Unconstrained Plan & the plan is not considering Item Level , ASL Lead times & generating the planned Orders to meet demand due dates by compressing the Lead time.
    Constraint option is not checked in plan options.
    Appreciate your advise on this issue.
    Regards,
    Pranay Saxena

    Hi Pranay,
    An unconstrained plan cannot have ANY constraint.
    So it is not possible to have just the supplier lead time as constrained.
    Alternatively, if that is what is your requirement, you may run a constrained EDD plan with just the material constraints enabled and the "Enforce Purchasing Lead Time" Flag checked.
    If the supplier capacity is NOT set.. it will be treated like infinite..
    This way you will force the engine to respect the lead times from ASL and acheive a near unconstrained plan.
    Another alternative is use constrained plan as explained above and set the profile MSO: Lead Time Control to Do not Violate Minimum processing LT... in this case even the processing LTs for the MAKE items are also respected.
    Hope that helps.
    Regards,
    Mohan Balaji
    NOTE: Please mark the post as Helpful or Answered if the update has really helped you. This would also bring the thread to logical conclusion and will be helpful for the viewers.

  • Need Automatic Lead-time scheduling in Planned Order using MD11

    All,
    Our users have a requirement that when they create a planned order using MD11, they would like system to do automatic lead-time scheduling based on the "basic finish date" entered by the user. Currently the system is taking 3 days from the in-house time maintained in material master to calculate the basic start date. But users want to use the 100 days that have been maintained in the routing.
    Currently users have to click on "manual scheduling" on the planned order for system to pick up 100 days from routing which is an additional step for the users. Hence users want an automatic way in which system would do lead-time schedule when they enter the basic finish date.
    Thanks,
    Swapnil

    Dear Swapnil,
    In my understanding it is the standard SAP behaviour even if you have made the necessary settings in OPU5 for the planned
    order type.
    If my understanding is correct, then as per this setting the MRP behaves for the particular plant and order type combination.
    Whenever you create a planned order manually you have to do a detailed scheduling and then you get the production dates
    for the planned order.(This might be because generally when a planned order is converted into production order the system
    carries out a lead time scheduling.- Check the same and correct me if I'm wrong)
    Even if you update the material master through CA97,you will not get the detailed scheduling done along with the production
    dates.So you have to perform this manual activity during MD11.
    What is the reason of setting the in-house production time as 3 days,if the exact production time is going to be more?
    Check and revert
    Regards
    S Mangalraj

  • Mass change - Lead Time

    Hello,
    Do we have a standard transaction for mass change of lead time for material-plant level for all materials in a plant. This should also consider lead time for DC.
    Regards
    Prashant Kedare

    >
    Prashant Kedare wrote:
    > Hello,
    >
    > Thank you for the replies so quickly. But the planned delivery time is to be maintained only for materials from external vendors. How about receiving goods from a Warehouse which takes 1-2 days for receipt of material. Where do we set this parameter and how do we mass change it?
    >
    > Regards
    > Prashant Kedare
    In MASS,  use Total RL time = MARC-WZEIT for updating total replenishment lead time and just update materials which are for external vendors.
    Use GR Proc. Time = MARC-WEBAZ for updating Gr proc. time field records and you can give range of materials for which records needs to be updated or created.

  • Every time I update LR to a new version I seem to need a patch to make it work..... once again here I am SOS! I've just update LR to the 5.7 version and It wont let me start it: The application was unable to start correctly (0xc000007b).

    Every time I update LR to a new version I seem to need a patch to make it work..... once again here I am SOS! I've just update LR to the 5.7 version and It wont let me start it: The application was unable to start correctly (0xc000007b).

    Your system is missing a couple DLLs that LR needs, but the fix at Adobe is to copy them to the LR folder which gets replaced for each install, so you have to redo it after each LR install.  It would be worth documenting the process and saving the DLLs so you don’t have to ask about it each time:
    http://helpx.adobe.com/lightroom/kb/error-unable-start-correctly-0xc00007b.html
    You might also use the AIO210 program to add them as detailed in this YouTube video—maybe this is a more permanent fix, but since the files are from media-fire be very careful about what you do so as not to install a virus on your computer. 
    I’d scan the downloaded ZIP you download with whatever virus and internet security software you have and don’t be fooled by extraneous popups you might see during the download process.  I was able to download the aio210.zip after authorizing one Captcha window and closed at least one bogus popup trying to get me to install other software.  I also scanned the downloaded zip with two virus scanners and both said it was clean.  Here is the YouTube video, where the link to the ZIP to download is in the description once you expand it:
    https://www.youtube.com/watch?v=vlT0N2CX50g

  • HT5654 Just tried 3 times to update iTunes on my PC running Vista.  There was an error.  It stopped the installation.  Now iTunes will not start at all.  The error message tells me to reinstall which I tried but did not work.  What should I do?

    Just tried 3 times to update iTunes on my PC running Vista.  There was an error.  It stopped the installation.  Now iTunes will not start at all.  The error message tells me to reinstall which I tried but did not work.  What should I do?

    Hello, Jdragone. 
    Thanks for the question.  Start with completely uninstalling iTunes and all of it's components in the order specified in the article below.  Once this is done, download and install iTunes.
    Removing and reinstalling iTunes and other software components for Windows Vista, Windows 7, or Windows 8
    http://support.apple.com/kb/HT1923
    If you receive any errors when uninstalling any components of iTunes, try the steps in the article below for each component that gives you an error.
    "The feature you are trying to use is on a network resource that is unavailable" alert appears when removing Apple software in Windows
    http://support.apple.com/kb/TS3704
    Cheers,
    Jason H.

  • HT6001 I have tried numerous time to update iTunes to Version 11.1.4.  Each time it has failed. I get the message of "This application has failed to start because MSVCR80.dll was not found".  Also I get a message of "Error 7". Advise please.

    I have tried numerous time to update iTunes to version 11.1.4.  It has failed every time.  Now I can't even get into iTunes on my PC.  The message I get is "This application has failed to start because MSVCR60.dll was not found.  Re-installing the application may fix the problem."  Okay. Which application?  What steps are needed for this process?
    Also, I get this message "iTunes was not installed correctly.  Please reinstall iTunes.  Error 7 (Windows error 126)"  Could someone please assist me in the steps necessary to remedy this issue.  Thanks.

    For many users at this point in time (iTunes 11.1.4.62) uninstalling iTunes alone is not enough and they may need to undertake further steps...
    Go to Control Panel > Add or Remove Programs (Win XP) or Programs and Features (later)
    Remove all of these items in the following order:
    iTunes
    Apple Software Update
    Apple Mobile Device Support (if this won't uninstall move on to the next item)
    Bonjour
    Apple Application Support
    Reboot, download iTunes, then reinstall, either using an account with administrative rights, or right-clicking the downloaded installer and selecting Run as Administrator.
    The uninstall and reinstall process will preserve your iTunes library and settings, but ideally you would back up the library and your other important personal documents and data on a regular basis. See this user tip for a suggested technique.
    Please note:
    Some users may need to follow all the steps in whichever of the following support documents applies to their system. These include some additional manual file and folder deletions not mentioned above.
    HT1925: Removing and Reinstalling iTunes for Windows XP
    HT1923: Removing and reinstalling iTunes for Windows Vista, Windows 7, or Windows 8
    tt2

  • MM Report for Reorder and lead time

    Hi,
    Can anyone suggest me a report that can show information by materail such as min./max. quantity, re-order or safety stock, and replensihment lead time.
    Thanks
    Atif

    you can create the query using MARC or just go se16 adn enter the MARC table and pull the data.\
    Displayed Fields:   8 of   8  Fixed Columns:                2  List Width 0900                                                                               
    Material             Plant  Reorder Point     Safety stock      Min. lot size     Max. lot size     Total RL time Min SafetyStock                                                                               
    MATERIAL            Z001               0.000             0.000         5,000.000       350,000.000   0                       0.000

  • Lead time values are not appearing in the report for current year.

    Hi friends,
    Iam checking a report in production.  where lead time values are displayed as 0 for 1 key figure lead time3 (w/0 dim) . i found there is a formula for this it shows like NODIM ( 'Lead Time 3' ).and there is a value for cal.lead time
    how can i get values in the report.
    Thanks ,
    VRV.

    Hi,
    Although your question is not clear, I understood that the formula built on that KF is NODIM. Basically it means, units of measurement is not considered when calculating.
    Eg: 5 Minutes + 5 Kilograms = 10
    You please try to analyze your KF by the above logic. Then you would be able to figure out why the data is not appearing in the report..
    Assign if helps...
    Regards,
    Suman

Maybe you are looking for

  • Mac Mini 2012 - Windows 8 Not Supported??

    Hi all, I have a late 2012 Mac Mini, which seems to support Windows 8 as far as I can tell.  However, when I go to the boot camp assistant, it says, "This mac can only run Windows 7."  What's going on? Does anyone else have this issue? Thanks

  • CS6 Blackmagic

    Hello everyone, I'm having a serious issue and I was hoping someone on the forum maybe able to help.    Here's the specs before I get to involved: HPZ800 Windows 7 64-bit Pro Dual 6 core Xeon X5690 3.47Ghz Processors 48GB Ram 128GB SSD C: 5TB RAID 5 

  • Web site has A with symbol over it, but this is not shown in iWeb only when published

    iting the website of Robert T Mallory, DMD, a family dental practice in Helena, Alabama.  It is our mission to provide our patients with the most personal care at the highest quality possible.  We will strive to educate, motivate, and treat our pat

  • Publish to Apex - User has no privileges on the selected workspace

    Apologies for this novice question,... (re: Apex 4.1.0) I am trying to publish output from SQL Developer into Apex via the "Publish to Apex" option, but get the error: ORA-20001: User <XXX> has no privileges on the selected workspace. ORA-06512: at "

  • Power interuption  during update now only line on bottom of the screen

    power interruption while updating mac mini  as it turned back on only white line on bottom of the screen tried unplugging and rebooting  nothing seems to work.  line has been there for over an hour