Hi Gurus,
Im working on a scenario werein I need to change the Defect recording after I need to change the disposition of the material. The process is, the lot will be rejected, and will go to a certain Location. In this location, the user will decide whether it can be rework, return to vendor or use as is. User will need to key in in the system.
At first, I though I can just use of changing the usage decision. But they say they need the disposition per item in the defect code. But once I have done usage decision, Defect cannot be changed.
Please help to identify other process that I can do.
Thank you,
Raymond

Dear Raymond
Then in that case the only solution will be to activate notification.Please follow this process
1) Maintaina default notification type in the inspection type in the config
2) When defect recording is done automaticaly notification will be created
3) When UD is given notification also gets closed automaticaly
4) Go to notification ( in UD screen , select the defect and click on Notification and put the notification back in process (menu button > function> Put back in process
5) Here you can edit the defect or add defect and automaticaly gets assigned to the inspection lot
Please check and revert back
Regards
GN
Edited by: Gajesh Nagesh on Feb 3, 2010 6:14 PM

Similar Messages

  • Cancelling material document after usage decision

    hi experts,
    how to cancell a material document after usage decision has been made (quality to unresricted stock).
    thanks in advance
    regards
    jai

    Hi,
    whenever you do cancellation for material doument then its always done for the same stock type for which you have made GR....
    If you wanna do from it then Choose cancellation and material doc and enter the mrtl doc no.
    and execute ...
    Hope it helps..
    Regards,
    Priyanka.P
    AWARD IF HELPFULL

  • Need to send data, after Usage decision in quality inspection (QA11)

    Hi all,
    After Usage decision in quality inspection (QA11), i need to send some data like material number, qty etc to external database or to external party. is there anyway i can achive this in real time? real time means, it should send the appropriate data to external party after usage decision is made.
    Thanks
    Pabi

    Hi,
    You can change results recording in case the MIC in the inspection plan of the lot are marked as "long term characteristics", else it wont be possible to change result recording.
    you can change the UD code only after giving the Usage decision.
    you cannot change the defects recording.
    Thanks
    SUMIT

  • QM: Material Transfer without Usage Decision

    Dear all,
    I need your help in mapping following scenario.Senario is like:
    Material is received from supplier with quality certificates. Material receipt is made on the basis of supplier certificate. Sample from received stock is send to third party lab for testing. Meantime material received is used for production. After some days result from third party lab is received. If report is negative then compensation is to be claimed for used quantity and rest of the material is to be returned to supplier or can be used if supplier agrees to compensate for poor quality.
    Should I use long term characteristic for this and if yes then how it is to be used.
    Early response is solicited.
    Thanks,

    Hi (Better if you mention your name),
    In your scenario, you can use the long term characteristics for recording results even after usage decision and can take the usage decision, but ensure that you`ll not do any stock posting until you get the report from Third party Lab. After you receive the test results from it, then you do the stock posting for the unrestricted use (for used materials) and return delivery (for rejected materials).
    Reward if cleared n close the thread.

  • Printing of Inspection Report After Usage Decision

    Hi,
    I want take the print out of Inspection Report after Usage Decision completed.......... Can you plz guide the complete Confiuration & related transaction codes for this........
    Regards,
    Raghunath

    Inspection report can be printed from QA33 t_code.
    There are some pre requesites for this,
    i)   In material master 'Inspection with task list' and 'Check characteristics'  should be activated.
    ii)  Inspection plan for that material should be present.
    iii) Record results for these inspection characteristics and take Usage decision.
    iv)In QA33 t_code, u can see 'inspection report tab' . click on that tab.
    v) Give output device and see print preview.
    U can see inspection report with all details.
    Plz. revert back

  • Issue while doing material posting through Usage Decision

    Hi all,
    I have an issue while doing material posting through Usage Decision. Please find below the details.
    Inspection Lot  10000604689
    Material        1730PCPBS.0031
    Batch           QP611097      GQ02
    Out of total qty of 2100 we need to post the following
    To unrestricted use                     2,098
    To sample usage                         2
    Following error appears,
    Deficit of SL Stck.in qual.insp 1,638 NO : 1730PCPBS.0031 62GQ GQ02 QP611097
    Message no. M7021
    Diagnosis
    Shortfall below the specified stock level or quantity amounting to 1,638 NO.
    System Response
    If the message is an error message (E), the above is not allowed.
    If the message is a warning message (W), the system will allow your input, but the warning is intended to prevent you entering a wrong quantity.
    Procedure
    In the case of a warning message, check the quantity entered.
    In the case of an error message, change the quantity or terminate processing.
    I have checked that quantity 2100 of material 1730PCPBS.0031 is in QI stock. Kindly advice what is the issue and why we are getting the error?
    Regards,
    Brijesh

    Hi Brijesh,
    What is the status of inspection lot?
    One of the possibilities I think could be inconsistencies between MM and QM.
    Have a look on SAP note 48815- Checking possible inconsistencies between MM and QM.
    Regards,
    Anand Rao

  • Sample  still showing in quality inspection stock after usage decision completed

    After process order completed, we have received 100 units as a quality inspection stock.  After usage decision,( QA11), I have posted 98 units to unrestricted use and 2 units to the  to sample usage
    98 units successfully move to unrestricted stock.
    However 2 units for sample still showing quality inspection stock.
    I have checked MB51, mat document number for sample is 4900000160 and movement type is 331
    Do you have any idea why sample still showing in quality inspection stock. It  should consumed and zero out the quality inspection stock in MMBE

    Hi,
    Please check you MIC's control Indicators.
    Is it tick on Destructive insp. under Sample tab ?
    Please tick it and try again with whole process.
    Destructive Insp. : You specify whether the sample is to be destroyed after inspection. This means that is no longer available. This quantity is used in the usage decision as the proposed quantity for the posting to sample.

  • EWM with QM -Inspection label not getting printed after usage decision

    Hi Experts,
    We checked configuration settings related to this but we could not find missing configuration. Right now we are not able to print label after we take usage decision. Please let us know your inputs on this.
    We are using /SCWM/QINSP for usage decision.
    Thanks & Regards,
    Prashant

    We changed the printer name in condition record and we could print the label.
    Regards,
    Prashant

  • Reverse Production Confirmation After Usage Decision (UD)

    Hi All ,
                 We are using Quality Inspection Type 04 ("Good Recipt production Inspection ") . We have Done some wrong Entry in Production Confirmation after that quality person also did Usage Decision for the inspection Lot. now we want to cancel this confirmation . will some one help me how we can reverse UD (Usasge Decision) and Cancel the production confirmation .
    Thanks In Advance .
    Regards

    Dear Jaideep,
    Check out this,
    Do you mean to say you want to cancel the document for which 321 movement has been made where the stock has been
    cleared from quality to un-restricted?
    This is not possible,unless if you have used SAP notes,
    Note 1108313 - Cancelling usage decision and lot
    Note 175842 - Inspection lot: Reversal of goods movements from UD.
    Otherwise cancel the confirmation and the error movement 102 will be going to COGI.
    Do 102 through MB31 against that order and delete the 102 error from COGI.
    Check and revert back.
    Regards
    Mangalraj.S

  • Financial posting after usage decision.........

    Hi there ,
    Please tell me where I Can see the financial posting & variance after the usage decision has been done for an inspection lot in QA11 ?
    Thanks
    Kaushik

    Financial Posting will take place after MIGO & MIRO
    The financial posting will be as under:
      1. When GR is posted 
          Inventory Account dr (Transaction Key BSX in OBYC)
                To GRIR account (T.Key WRX in T-code OBYC)
      2. When Invoice is posted
          GRIR account Dr.
          Vendor account  Cr.
    Regards,
    Rajesh Banka

  • Update purchase order history after usage decision from quality

    Hi guys,
    I'm working with active ingredients, after entering the % of the active ingredient in quality, then making the usage the decision, I need to update the history of the purchase order for the quantity posted.
    what I mean is that if I received 1000 KG of a raw material, then in the quality check I found that the % of the active ingredients is 90%, I update the purchase order quantity to 900 KG, I know that this is made by using transaction MWBQ, but what are the settings I have to make at the very beginning before using transaction MWBQ
    Regards,

    check the below forum link related to this.
    Re: use of Tcodes: MWBQ & MWBE

  • SAP QM Issues regarding follow-up action after Usage Decision

    Dear Gurus -
    Kindly need your expertise to resolve these issues regarding follow-up action.
    1. After taking the UD i need to trigger the follow-up action to send an email with the long text to a group of people. As per standard SAP the email goes to the person taking the UD. Kindly can some one explain what & where do i need to make the changes. Also please let me know what is the customized Email ID table where mail ID's will be stored which fuction module can extract.
    2. Can i also use the same functionality for partial lots during inprocess inspection. I need to send an email to a group in case the valuation is rejected for that operation.
    Any response is highly appreciated.
    Thank You.
    Edited by: sunil t on Jan 6, 2010 7:03 PM

    Hi
    Please go through my recent thread
    Incomming Inspection Auto mail if Rejected
    Regards
    Sujit

  • Usage Decision to post new material.

    I need a FM which posts material as New Material  when the Usage decision is made. I get the Usage decision and the material number(new)from the shopfloor and post it using the  t-code qa11. Any help will be rewarded.

    Function Modules
    http://www.erpgenie.com/abap/functions.htm
    http://www.sapdevelopment.co.uk/fmodules/fmssap.htm
    http://www.erpgenie.com/abap/index.htm
    http://www.geocities.com/victorav15/sapr3/abapfun.html
    Rewards if useful................
    Minal

  • Usage Decision Results to any stock update?

    Dear SAP Experts,
    I want to know , when usage Decision is taken in QM, stock will be updated or not?
    After usage decision say few quantity is scrapped and given usage decision code for the same. I want to know this decision will update to stock or not? if it doesnot update the satock automatically, then what standard movement types are used to post this scrapped quantity.
    Please help, and its urgent.
    Thanks & Regards,
    Mohd Ismail.

    Hi,
    I want to know , when usage Decision is taken in QM, stock will be updated or not?
    May or may not be! 
    Stock posting through QM and UD are 2 separate events although executed through same TCode.
    If you want that stock should be posted automatically in to unrestricted or into block with UD at the same time, you can do that setting in QS51 against appropriate UD code.
    If the system status of inspection lot contains UD ICCO SPCO, that means stock posting and UD both have been done
    After usage decision say few quantity is scrapped and given usage decision code for the same. I want to know this decision will update to stock or not? if it doesnot update the satock automatically, then what standard movement types are used to post this scrapped quantity
    I could not interpret this correctly.
    Seems that you are narrating a case where UD and stock posting are done and later you want to scrap the material
    You can simply do it through MIGO using 551 movement. (Scrapping against cost center from unrestricted use)
    But changing once given UD, will not perform any movement again.

  • The Usage decision cancellation & quantity reversal

    Daer All,
    While cancelling the Goods receipt, system gives the error Deficit of SL Stck.in qual.insp 10 M : 5000017/1 PMT1 RMST as the usage decision of quality lot generated for the goods receipt is done.
    I want to cancel/reverse the usage decision made & the quantity release from the lot to be initialised, so I can cancel the Goods receipt.
    I have applied the Note 175842 & User Exit QEVA0008
    But when I cancel the usage decision in QA11, only the usage decision is cancelled. The quantity which is moved to un-restricted stock after usage decision is not reversed.
    I want to reverse the quantity, so i can cancell the goods receipt.
    Regards,
    Prakash

    Hi Prakash,
    Please note that SAP doesnt provide an option to reverse a UD once its done.
    Now to solve your issue, Since you have already done QA inspection the stock is moved to Un-res.
    So when you cancel the Material/GR document, select the stock type as un-res then system will allow to post the document.
    Regards,

Maybe you are looking for

  • New iPod Touch 32gb stalls after starting sync, error 54, manual synce gets dumped

    I just got this thing at Walmart last Sunday and its been driving me nuts all week! It's the brand new iPod Touch 32gb 4gen. When trying to sync it will start to load music then stall. Sometimes it gives error code 54, sometimes says it cant convert

  • Solaris 11 host no longer sees a ZyXEL wifi network router

    This issue is on a Toshiba Tecra M10 running Oracle Solaris 11.1 SRU 0.5.11-0.175.1.0.0.24.2 The once functional wifi network iwh0 (net1) no longer sees a ZyXEL NBG-416N wifi network router. The e1000g (net0) can connect to the router when direct con

  • IPhone recovery causes PC crashes

    Hi guys I just got my brand new iPhone 3GS and attached it to my PC (Win XP, iTunes 8.2.1). While doing the automatic updates, my PC crashed and rebooted automatically. After restarting everything, iTunes reported that a recovery is required. I start

  • Very urgent : 0 records for 0COSTELMNT_TEXT in RSA3

    hi guys, No records found for  0COSTELMNT_TEXT  & 0ACCOUNT_TEXT. It show 0 records after extraction and also in rsa3 in r/3 side. problem is with texts, attributes are loaded for the same. any ideas .... advance thanks

  • TAN and CIT(TDS) details not coming in Form 16A (SAP 4.7 version)

    Team, I have maintained the deductor TAN details in J_1I_SECCO_CIT table. I have also maintained the CIT(TDS) under the Company Code> Additional Details > in TDS No. Field. However, when I preview the TDS Certificate in J1INCERT, I am not able to vie