Material planning currency in assignment tab of Internal activity

Hello Friends,
In the network configuration profile using OPUU, I have included material cost element in the activity parameter tab of internally y processed activity having control key PS01.
The inclusion of cost element as above will allow user to plan material value in the assignment tab of the internally processed tab.  However, the currency displayed for planning is USD and that too is grayed i.e. non editable. Necessary screen shot is appended.
Can we change this default currency to object currency? Our is a global system in which is controlling area currency is USD but object currency is country specific i.e. for India INR, for SG the same is SGD, for Thailand it is THB etc.
Thanks and best regards

Hello
Thanks for your feedback.
Can you provide authentic SAP documents to estabilish your argument ?
That will be very helpful to me.
Thanks once again and best regards
Bharat Parikh

Similar Messages

  • Person Assignment tab in network activity

    The person assignment tab in internal network acitvity has a daily view. Shows dates for only 1 day at a time
    Can anyone please tell me how to change this view from daily to weekly?

    Hi,
    Pl elaborate , we do not understand the requirement.
    regds,
    Deependra

  • Material Document Acc. Assignment TAB

    Hello All,
    In transaction MB51 i used the plant and the movement type selection criteria to get a document list of all the materials that were shipped using that movement type.
    I clicked on the document from the list to see the details. On the bottom half of the screen there are 5 tabs, Material - Quantity - Where - Partner - Batch - Acc Assignment
    I want to know whether the Cost center and profit center assigned in acc. assignment field are assigned to material or a movement type? If I need to change that assignment how should I do that.
    Nik83

    Hello Suraj,
    What you said is right but this is what is happening, when the outbound delivery is executed the profit center entered is the same profit center that is assigned to the material in the material master. However in acc assignment tab of MB51 the cost and profit center are different. This is exactly what we want!
    I just want to know how this is done.
    The movement type is a free good movement and as such is a marketing expense. So the profit center assigned to material is lets say P1 (which is hooked to cost center C1) and this is what is entered when creating outbound delivery however on the account assignment tab you would see P2 which is profit center for marketing expense and the cost center would be C2.
    Do you know how this can be achieved?
    I ll repeat this is exactly what we want to happen.Some other consultant before me made these settings and I just want to know how this happens as I ll need to do the same for some new materials and movement types.
    Points will be assigned generously
    Regards
    Nasir

  • PS Workforce planning, Person Assignment in internal activity.

    Hello PS colleagues!
    I’m trying to use the workforce planning functions but I can not get the screen for person assignment in the internal activity.
    I have done this, IMG I go to this path:
    Project System -> Structures -> Operative Structures -> Network -> User Interface Settings -> Layout of Activity Detail Screens -> Define layout activity detail screens
    Then I create all tab, I copy the standard to my network profile and there is tab 8, in standard is call ”Admin.” then when I try it out it do not appear in the project, I use project builder.
    Does any one what more I need to do for this to work??
    Please help me out with this.
    Best Regards
    Jose Marin

    Check the consulting note 543362
    This note explains the steps/configuration node that needs to be in place for workforce planning
    Regards
    Sreenivas

  • Rejected Quotation number is coming in account assignment tab in sales orde

    Hi Friends,
    I have created one quotation 'X 'and after that I created one more quotation'Y' with the reference of original quotation'X 'and rejected the earlier created quotation 'X'.
    After that I created sales order'Z' with the reference of quotation 'Y' but while i go to account assignment tab at ' order field' at sales order item level than the cancelled quotation no. is there coming.
    As per my knowledge quotation  no. 'Y' should flow in sales order account assignment tab in 'order field'
    My question is why rejected quotation no. is flowing there in account assignment tab in sales oreder ??
    And what is the use and impact of sales order field under account assignment tab at item level in sales order??
    This is scenario of MTO and we are using billing plan at sales document header level.
    Regards
    SV
    Edited by: sv.sap09 on Dec 6, 2010 1:22 PM
    Edited by: sv.sap09 on Dec 7, 2010 7:31 AM

    FYI-
    "Order field" at item level in sales order - account assignment tab refers Internal Order number ( created by using Tx:KO01), this is not SD orders.
              You might have same number range for Internal Orders & quotations. Hence confusing with the number.
    Quotation number will be available only in document flow & document status table VBUK. will not be displayed in order transaction.
    Regards,
    Reazuddin MD

  • Requirement assignment tab in Maintenance  Work order

    Hi Gurus,
    I have a query ..I want to know the customizing settings for Requiremnt assignment tab in internal operation tab for internal operations in maintenance work order .
    Thanks ,

    Hi sundar ,
    This Path is available in ECC 603 and we are using ECC6 . so not able to get the Path .
    Anyways Thanks for your Help .
    I have one more query  regarding this:
    When I assign one Resource to Reqmnt assignment tab and give any date of  friday then the date is automatically switches to Monday's date . the Work schedule for that person is from Monday to Friday but then also it shifts the date to Monday .
    Can you please suggest on this .
    thanks !!

  • Person assignment tab

    Hi,
    Iu2019m not able to get person assignment tab for the activity in cj20n.
    I have maintained work and workcenter for each activity.
    Can any one help me on this, I have checked note 543362 and have maintained the same.
    But i dont know what is missing.
    Thanks,
    Chandru

    Hi Chandru
    Actually the note 543362 (written by me)  should give you all the information. Anyway double check the following again.
    1. Is the flag 'capacity requirement' of network  set?
    2. Is the scheduling for network done?
    3. Is the work for activity maintained?
    4. Which work center is maintained for involved activtiy. Call CR03 for this work center.
      4.1. In work center, in the capacity  tab. Is the formular for field 'Other formular' maintained. Default is SAP008
      4.2. Click of button 'HR assignment', is the HR resource assigned?
    If all the checkitems do not help, you can open a customer message to let SAP have a look.
    Kind rgards
    Zhenbo

  • BAPI to upload Person Assignment data under network activity

    Hello All!
    Can anybody tell me the appropriate BAPI that can upload the data of Person Assignment tab under network activity of Project System(TCode:cj20n)? I.E. data like Split Person Date Time Work Un and others data.
    Thanks in advance.
    Regards.
    Sarbajit

    Hi Majumdar,
    you can find it by running transaction ST05 against CJ20N.
    try bapi-
    BAPI_PROJECT_MAINTAIN
    Regards,
    NaPPy

  • CN01 assign Material Component to internal activity

    Hello gurus;
    In transaction CN01 / CN02 can I assign only one Material Component to internal activity without Bill of Material (BOM)?
    It is possible? How can i do?
    Best regards,
    Mariano

    Virendra;
    Thanks for your response.
    I saw the SAP Help portal in [http://help.sap.com/saphelp_46c/helpdata/es/4c/227a7746e611d189470000e829fbbd/frameset.htm]
    and I must use a Bill of Material to assign material component. There is no other choice
    This is the point where I disagree with SAP, cause the client says that they use Operational Networks, cause it's more simple to assign components to activities.
    Best regards.
    Mariano

  • Internal activity material cost not displayed in report s_alr_87013558

    Hi all,
    I have an material attached to the internal activity.
    this internal activity is inturn attached to a network
    which inturn attached to a WBS.
    After the PR and PO creation of the material attached
    the cost report s_alr_87013558 shows values in the
    WBS element not in the network activity to the material
    was attached
    How to catch the cost value to network activity instead of WBS elment
    Can anybody have a clue why it is happening
    Thanks and Regards
    pv

    hi sreenivas,
    thank you for the suggestion
    in budget report the actual and commitment value is pulled
    to respective network activity or wbs element depending upon the account assignment category during the automatic PR
    creation from CJ20n
    In my scenario during automatic PR creation it is Q(project make to order) instead of N(network).
    Can you throw some light to this where in
    i can generate auto PR with account assgnment category N
    for a material attached to network through internal activity
    Note:
    to catch the cost we also need to activate the cost rel indicator in purchasing doc tab for material in cj20n
    regards
    pv

  • Material planning field in Activity

    Hello All
    When we select activity and go in detail screen, go to assignments tab - there will be a material planning field.
    I am not able to see that field, is that a configuration , if yes where is the setting.
    Thanks,
    Karthik
    Edited by: SG_Karthik on Aug 3, 2010 1:46 PM
    Edited by: SG_Karthik on Aug 3, 2010 1:46 PM

    I have modified our network profile to include a material cost element for internal processed activities, but the material planning field does not show up.
    I checked field selections, but it's not an available field to choose, which I presume is dependent on the network profile config described above.
    Does the cost element used in the network profile have to be a specific type of cost element?
    Is there anything else I could check?
    Thanks.

  • Project- Builder: Person Assignement tab for Activties

    Hi All,
    Pls help on the following:
    1.In the 'Internal' tab for activities, there is a field 'Number' where we can specify the number of capacities required. But there is no validation against this when I actually assign resources to the activity in the 'Person Assignement tab.
    i.e I can assign 5 people for this activity even though I mentioned Number as 1 in the internal tab.
    Is there a way to enforce a validation here?
    2. Resource allocation has two different behaviour when I do through Person Assignment tab and 'WorkForce Planning' screen. Is there any specific reason for this?
    3. If i want to replace the WBS actual dates by the actual dates of activity, I need to go to Edit>Reconcile Dates>Determine Actual Dates in the Project Planning Board. Can I automate this while saving the project?. I checked the user-exits and BADI - PROJECTDEF_UPDATE. But found out that the date fields cannot be updated using these. IS there some other way?
    4. In the Workforce planning: Project View, Can I split the work in the duration based on my working hours from HR? Now I have to manualy do the split.
    Appreciate your response on any of the above doubts.
    Regards,
    Remya.

    Hi remya,
    My reply is limited to point No.3 of your posting.
    SAP's logical construct is such that WBS is more than the sum of activities assigned to it. That is why, system doesn't allow automatic updation of WBS actual dates based on confirmation of all activities assigned to it. Please remeber that the given WBS could have subordinate WBS elements with different statuses  apart from the activities assigned.
    Basic rule is as below:
    You can maintain actual finish date for a WBS only if all the subordinate WBS elements have actual finish dates and all activities assigned to the WBS have status "Confirmed".
    However, when activities are confirmed "Tentative actual finish date" is updated at WBS level which can be subsequently copies as actual dates manually.
    From the above, I hope, it is clear why defaulting of actual finish dates for WBS is not permitted.
    For the remaining issues in your posting I need more time.
    If this clarifies the issue, please acknowledge the same.
    Muraleedharan.R
    091 9880028904

  • How to change the default date in Person assignment tab?

    Hi experts,
    Does anyone know how to change the default date in person assignment tab in cj20n? Currently, the system always take the scheduled finish date to the date of the person assignment tab. Can I change it to the start date?
    Thanks and rgs,
    Michelle

    Hi Michelle,
    Goto SPRO->Project system->Dates->Scheduling->Specify Parameters for Network Scheduling, Here you can control the workforce planning dates.
    Hope this is useful...
    Regards
    Aatish

  • Inspection lot of type 04 in "assignment" tab in Process order

    Hai,
    How do I make the Inspection Lot that was generated based on 04 Inspection Type in the Process Order - "Assignment" tab?
    Thanks in advance,
    Sonali

    Hai,
    Thanks for your reply. I could find the entries for all inspection types under Production order type (for example, PP01) in the config , but could not find entries other than 03 inspection type in PI01 order type (Process Order). Is this standard? How do i get all inspection type entries in Pi01 order type? At least, 04.
    Also, if I have both 03 and 04 active for the material, then which inspection lot the system populates in the "assignment" tab?
    Thanks
    Sonali

  • Change the Profit Center in Sales Order line item's Account assignment tab

    Hi Gurus,
    I need to change the Profit Center at Sales order Line item in Account Assignment Tab. Currently  The Profit center is coming from Material Master for the Line Item's Material as default but I have to change / overwrite  that.
    Can any body provide me how can i achive that means
    Any User exits, substitution or any thing ?
    I tried MV45AFZZ but i am not able to find out the right place where I can change COBL-PRCTR.
    Sony

    Hi
    There is perform which moves the values to VBAP field.
    This PRCTR field is stored in VBAP (i.e., SO line item table)
    USEREXIT_MOVE_FIELD_TO_VBAP
    Hope it works.
    VVR

Maybe you are looking for

  • Godaddy IMAP email no longer downloads with iOS 8.1

    no problem sending, however, no new email will download.  I rebooted, deleted account, added it (which it adds fine), it just no longer downloads email.

  • Error compiling movie. Unknown error - When exporting

    Hi everyone. Exporting movies in Premiere PRO won't work for me. This error shows every time I export movie. - Source File: C:\Users\addo\AppData\Local\Temp\Merianna_5.prproj - Output File: C:\Users\addo\Desktop\Sequence 03.m2v - Preset Used: Custom

  • Execute_query error

    Hi master Sir I use enter_query through button and give 10 in deptno textbox But I execute_query through button no give result An use form menu then give result easily what happen Enter_query code Go_block(‘emp’); Enter_query; execute_query code Go_b

  • Western Digital crash log mystery

    I'm have a Western Digital 1 TB MyBook Studio drive I'm using for Time Machine. It SEEMS to be working okay, but I noticed in the crash log that the following item shows up pretty much every day: WDMyBookService2008_01_20_083439MyName-Power-Mac-G5.cr

  • Importing Oracle Designer Processes into BPEL Designer

    Hello, We have several business processes defined and documented in Oracle Designer 10G , we were looking for a way to import these brocesses into Oracle BPEL. Is there any utility /tool to do this? Thank you. Syed Ahmad