Project- Builder: Person Assignement tab for Activties

Hi All,
Pls help on the following:
1.In the 'Internal' tab for activities, there is a field 'Number' where we can specify the number of capacities required. But there is no validation against this when I actually assign resources to the activity in the 'Person Assignement tab.
i.e I can assign 5 people for this activity even though I mentioned Number as 1 in the internal tab.
Is there a way to enforce a validation here?
2. Resource allocation has two different behaviour when I do through Person Assignment tab and 'WorkForce Planning' screen. Is there any specific reason for this?
3. If i want to replace the WBS actual dates by the actual dates of activity, I need to go to Edit>Reconcile Dates>Determine Actual Dates in the Project Planning Board. Can I automate this while saving the project?. I checked the user-exits and BADI - PROJECTDEF_UPDATE. But found out that the date fields cannot be updated using these. IS there some other way?
4. In the Workforce planning: Project View, Can I split the work in the duration based on my working hours from HR? Now I have to manualy do the split.
Appreciate your response on any of the above doubts.
Regards,
Remya.

Hi remya,
My reply is limited to point No.3 of your posting.
SAP's logical construct is such that WBS is more than the sum of activities assigned to it. That is why, system doesn't allow automatic updation of WBS actual dates based on confirmation of all activities assigned to it. Please remeber that the given WBS could have subordinate WBS elements with different statuses  apart from the activities assigned.
Basic rule is as below:
You can maintain actual finish date for a WBS only if all the subordinate WBS elements have actual finish dates and all activities assigned to the WBS have status "Confirmed".
However, when activities are confirmed "Tentative actual finish date" is updated at WBS level which can be subsequently copies as actual dates manually.
From the above, I hope, it is clear why defaulting of actual finish dates for WBS is not permitted.
For the remaining issues in your posting I need more time.
If this clarifies the issue, please acknowledge the same.
Muraleedharan.R
091 9880028904

Similar Messages

  • Person assignment tab

    Hi,
    Iu2019m not able to get person assignment tab for the activity in cj20n.
    I have maintained work and workcenter for each activity.
    Can any one help me on this, I have checked note 543362 and have maintained the same.
    But i dont know what is missing.
    Thanks,
    Chandru

    Hi Chandru
    Actually the note 543362 (written by me)  should give you all the information. Anyway double check the following again.
    1. Is the flag 'capacity requirement' of network  set?
    2. Is the scheduling for network done?
    3. Is the work for activity maintained?
    4. Which work center is maintained for involved activtiy. Call CR03 for this work center.
      4.1. In work center, in the capacity  tab. Is the formular for field 'Other formular' maintained. Default is SAP008
      4.2. Click of button 'HR assignment', is the HR resource assigned?
    If all the checkitems do not help, you can open a customer message to let SAP have a look.
    Kind rgards
    Zhenbo

  • How to change the default date in Person assignment tab?

    Hi experts,
    Does anyone know how to change the default date in person assignment tab in cj20n? Currently, the system always take the scheduled finish date to the date of the person assignment tab. Can I change it to the start date?
    Thanks and rgs,
    Michelle

    Hi Michelle,
    Goto SPRO->Project system->Dates->Scheduling->Specify Parameters for Network Scheduling, Here you can control the workforce planning dates.
    Hope this is useful...
    Regards
    Aatish

  • Person Assignment tab in network activity

    The person assignment tab in internal network acitvity has a daily view. Shows dates for only 1 day at a time
    Can anyone please tell me how to change this view from daily to weekly?

    Hi,
    Pl elaborate , we do not understand the requirement.
    regds,
    Deependra

  • CJ20N -  person assignment tab data

    hi,
    We need to retrive data from CJ20N -  Person assignment tab details. Please help, from which tables we can get those details...
    Thanks,

    hI,
    In fact I want to get first person name which assignmened, in CJ20N -  "Person Assignment" tab of WBS->network activity
    here is the below table is showing in CJ20N, we have to retrive "Atkinson" name ...please help
                                                                                    Spl    Person      D Date       Time  Work      Un. Duratn  Un. Reqmts      Un.
       1      Atkinson      04.08.2009 00:00     160.0 HR     80.0 DAY     160.00  HR 
       2                         04.08.2009 00:00     261.0 HR     32.6         261.00     
       3                         04.08.2009 00:00                                 0.00     
       4                        04.08.2009 00:00                                 0.00     
       5                        04.08.2009 00:00                                 0.00

  • Component configurator issue - Account assignment tab for SC in SRM 7.0

    Hello Experts,
      We have to disable some fields from account assignment tab of SC. We have identified the webdynpro application as /SAPSRM/WDC_UI_DO_ACC. We started the component configurator /SAPSRM/WDCC_ACC_DEF_SC and under the view V_DO_ACCOUNTING made the fields "DISTR_INDICATOR" and "COPY_TO_CLIP" as invisible.
      The problem is that these fields are still visible in the account assignment tab of the shopping cart.
      Do we need to do any other follow-up activity to disable the fields? Please guide.
    Thanks & Regards,
    Sarath

    An easier way to hide the two elements for you is to enhance the view "V_DO_ACCOUNTING" and remove the drop down and the button. Save and activate the enhancement.

  • Person assigned to a work center

    Hi,
    We are using work force planning to assign resources to activities. We have some problem with one of the work centres. When we click on the person dropdown box in the personal assignment tab then we would expect to see the individuals that are in the work centre associated with the activity. We can see six persons from project builder and when we checked work center master data we could see only four persons.
    When checked thoroughly, the data at work centre master data is picked from HRP1001 and its showing only 4 persons. At the project level, the data is picked from the same table but initially fetches with work centre as input and then capacity ID as input. Finally it combines the data (6 Persons) and show from CJ20n and its different from the work centre data.
    is this the standard behavior or we missing something
    Regards,
    Laxminarsimha

    I think you have assigned two person at capacity category level for that WC.
    Open your WC  in CJR3 --> Click on capacity header icon -->on new screen click on HRMS link button  ( check no of person assigned here  it should be two )
    With Regards
    Nitin P.

  • BAPI to upload Person Assignment data under network activity

    Hello All!
    Can anybody tell me the appropriate BAPI that can upload the data of Person Assignment tab under network activity of Project System(TCode:cj20n)? I.E. data like Split Person Date Time Work Un and others data.
    Thanks in advance.
    Regards.
    Sarbajit

    Hi Majumdar,
    you can find it by running transaction ST05 against CJ20N.
    try bapi-
    BAPI_PROJECT_MAINTAIN
    Regards,
    NaPPy

  • Create Person & Assign to Activity - CATS

    Hi Experts,
    I need to create persons and assign it to the internal activities in person assignment tab and use for CATS.
    We are not implementing HR module. Please suggest and advise.
    Thanks & Regards,
    Kabir

    Hi Kabir,
    1. You can create person through Mini-HR. T.COde is PA30. you have maintain following ifotypes 0,1,2,6,7,105 & 315. No need of HR module
    2. Create activity type in CO & maintain rate in KP26
    3. Create workcenter and assign person & activity type in it.
    4. Attach this workcenter in Internal activity
    5. Do the workforce planning in CMP2
    6. Book the time in timesheet using CAT2
    7. Transfer the time to PS using T.code CAT5
    Hope, this will help you.
    Regards
    Prabu

  • Person name was greyed out in Person Assignment

    Hello All,
    For internal activitiy, there was "Person Assignment" tab and there is a list of people who got assigned to the activity. However, some people's names just greyed out and we cannot make any changes to them.
    What are possilbe reasons? How to correct?
    Thanks
    JM

    >
    Aittal Alok wrote:
    > Hi,
    >
    > Against those persons who are greyed out, cost posting has already taken place.
    >
    > regards
    > Alok Mittal
    What kind of cost posting?
    Does posting period matter?

  • Splits (Person Assignment) in Network Activity

    Hello Experts,
    I have planned 10 hrs work in a network activity. After that , In the person assignment tab of Network Activity, I have assigned a person and gave work as 15 hrs.
    When I press enter, I got an information message " The work of all the splits is greater than the work in the operation"
    How can I make this information message as error message? I could not find in the configuration.
    Any thoughts would be appreciated.
    Regards
    Srinivasan Desingh

    Hi Srini,
    Any message if you want to change that from warning or error and vice versa......you have to change  the message category in the customozation of " Define system  message attributes".
    SAP provides these kind of customization for puchasing, process order, inventory and some other function modules.... Unfortunately PS module doesnot have this option.
    But it is possible to do so....with the help of ABAP consultant.
    Here are some of the inputs....
    Goto SE80...ABAP workbench
    Call for Repository browser
    and then enter package and CY and drill down box which is appear in the left side of your screen.
    You can see your message 411 at the right hand part...
    With the help of ABAPer...it is possible to do so...
    Hope it will helpful for some extent.
    Regards
    Vetri

  • Account Assignment tab in VA01

    Experts,
    The Account Assignment tab for a SO header shows the Cost Center field when an Order Reason is maintained and this is done through config. Is there a way to display the Cost Center field in Account Assignment tab without having to depend on the Order reason field?
    NW

    Please through some more light on that.
    As per my under standing you want to populate the Value from one field to another field.
    If is it so you can do that with the help of good ABAPer who can populate the value from one Location to another Z-Location.

  • Project Builder Source Control With CVS

    DOe anyone know how to setup Project Builder to use CVS for source/version control or is there a good guide I can download?

    Hi,
    Project builder does not support Source control afak.
    Frank

  • How to change company code in Assignment tab (CJ20n-project builder)

    Dear All,
    Is there any config to maintain company code in assignment tab (project builder) ? We have a problem in our project. It shows that in basic data, user put company code A (in basic data) but in Assignment tab they put different company code let say B. When we do settlement , two accounting document created to company code A and B. By right it should be only company code A. In addition, we cannot change the company code, when the status is already Release (REL).
    Please help how to change the company code B to A and how to reverse the accounting document that has been created under these two accounting document.
    Thank you.
    Best Regards,
    nies

    Now I understand your scenario, you have the Requesting Company Code and the Company Code Different.
    You usually use this primarily with IM module if you want to manage the asset under construction (cross company) belonging to a different i.e., company code (Requesting ) than company code on main WBS.
    You can not change the company code (Assignment Tab) as you already have actual posted against it.
    You've also created an AUC (in wrong company code) and even if you reverse the settlement you would not be allowed to delete the AUC or the delete the settlement rule (its grey out as its already used)
    What I can suggest is to reverse the settlement, lock this WBS which was created wrongly, create a new WBS and then continue with you regular process.
    Above are my views but you can expect views from others.
    Regards
    Sreenivas
    Please close the post if satisfied.

  • Person assignment  for activity

    Hi All,
    I'm looking for  a function  to get the person assignment and update the data.
    We are using ECC 6.0 EH4, Does anyone have any idea which function  does  this functionality ?
    Please advise,
    Amit Yosha

    Hi Amit ,
    There is a consulting note 543362, which clarifies your questions.
    Essentially there are following points:
    1. the work center need to linked with HR.
    2. Enter the work center for the activity.
    3. Maintain the work of the activity and run the scheduling, so that the capacity is determined.
    Now you see additional tab 'person assignment' of the activity.
    kind regards,
    Zhenbo

Maybe you are looking for

  • Data Recovery On an iBook G3

    I had an iBook G3 in college (2002, exact model @ http://bit.ly/VGVpSh), and when it died I purchased a new Mac and shoved the iBook in a box (About 7 years ago). It died from the logic board/display issues that all those dual-USB iBooks had. I actua

  • Can't save a PDF as reduced size PDF?

    Acrobat X complains i do not have sufficient permissions but i am on an administrator account? Also is there a way to save just one page out of a PDF?

  • When i connect my ipad to the laptop ,it doesnt get connected

    when i coonect my ipad 2 to da laptop its doesnt get connected but wen i connect it to my pc it gets connected hence wt m i supposed to do to coonect ym ipad to the laptop

  • Why do we need get and set methods?

    It is considered good design practice to keep all class data private and provide get and set methods for accessing the data in a controlled manner. So, instead of directly accessing the class data, you use getter and setters. I do not really feel the

  • Help with converting an object to something else

    How do I go about converting an Object from a Vector back into what it originally was?