Material To be Valuated in Project System

Hi All,
We are implementing PS,MM,SD,FI &CO for a companay which works essentially on engineer to order scenario and using vlauated projec stock & actvity account assigned networks
Inhouse production is through typical assembly processing process - Where input & output materials are transferred through BOM PS Transfer from WBS BOM.
Input materials are issued to activity; work performed by work centers are entered by confirmation; at completion of work out put materials is 'Received from activity'. Both material issue and receipt are done wrt reservation.
When this is done, as per standard process, the cost addition (and hence value addition) is to activity and thereby to WBS element. The output material is not valuated. All the cost(or values) become project value which will reflect in WIP calculation. WIP is calculated as month end process.
At month end if the company wants to know the current asset from project and relevant stocks:
= WIP of project + Inventory value of the mmaterials.
Pl. note that only input materials i.e. raw materials and Bought out materials will have inventory value; the output material will not have any value.
The process is alright and I think we are alos complying to Accounting stanadard for project system - directive from Institute of Chartered accounts - India.
This process was first aceeptable to customer; but now they say -  the out put materials should be valuated. So that, when inventory value is taken - it is RM+BO and valuated semifinished +valuaed finished materials
One big reason they say is that they have to show inventory value to the Banks.
Now I need clarification in following points
1. How to valuate the out put material when working only with project system. (apart from using user exit )
2. If this is done, the project cost/WIP calculations will show ups amd downs - as goods receipt with valuated value will be with sign - this will reduced the cost. This will cause variuos problems - almost no standard SAP PS cost report will reflect the reality - WIP can not go up and down...This is illogical.
3. Have you faced similar situation in implementation - that - Banks can not be conviced about this PSway of WIP calculation? Taking into consideration that project implementation is in India - an experienced reply can be very helpful
Thanks and regards
A.Saravanan

Dear Pradeep,
When we work with network/activity/wbs element, Finished material is assigned to activity with sign. This means GR can be done. Technically system treats lke by-product. This material will not be valuated with in put costs...since there is no logic...For our convention, one WBS element, one network or one activity can be used to book all related costs..but still GR will happen with valuation as per valuation variant in NW only. This is quite logical and correct.
So...customer wants to know the cost of manufacturing a complex project assembly..then process under one WBS element..cost accumuated at that WBS element is cost of mfg. I have kept such finihed material std price at Rs.1. (Ideally it should be '0'.). Meaning material will not valuated.
Now if customer wants to knwo the cost ...look at WBs element
If needed, you can do unit costing and update the value in a suitable field in material master.
Therefore, I have kept all the semifinished/finished material std price at Rs.1.
This way..std functions of PS like RA, costforecasting are work properly.
For WIP calculation, this is of standard method and WIP will be current asset of company..this will be acceptable to Banks...one concern I had..cross checked with a Banker.
Another issue was sub-contracting. In India during S/C..we have Delivery challan and legal requirement of excise. We developed a program integrating dc, excise challan, transfer posting, goods issue against reservation and mateials assigned in activity. For user it will appear as one transcation, and system will propmt/list appropriate excise challan No. based on dc no & material as input...(I hope i remember right).
Again here GR of seni/finished naterial was atRs.1. since Service cosst, matarial issue cost get booked at activty.
Thanks and regards
Saravanan.A

Similar Messages

  • Material or any links regarding Project systems

    Hi Guys,
    Can u provide me the basics and the detail info abt the Project systems,and also the datafowand terminology in the project system.
    Cheers
    Sunil Reddy LCP

    Hi,
    Please refer to the below URL which is quite exhaustive.
    http://help.sap.com/erp2005_ehp_02/helpdata/en/04/926eae46f311d189470000e829fbbd/frameset.htm
    Hope this will help you.
    Best Regards,
    Rakesh Pradhan

  • "Taxes for SEZ" and "Opg Stock of Material for Non Valuated Project Stock"

    Hi Guru's,
    Need two clarifications specific to SEZ:
    a. When an SEZ unit buys any materials from a DTA unit, and if the supplier issues ARE1 form then there is no Excise duty charged on such purchase. Similarly VAT is also exempt and CST is exempt if the SEZ unit issues Form I. However in case the SEZ unit is not NEF +ve after 5 years, then all these benifits taken on ED, CST, VAT etc needs to be paid back to the Govt.
    Hence how is it possible in SAP to capture all these benfits (ED,CST,VAT) in the MIRO Invoice posting stage, so that the details are available when needed?
    b. We are using Project Systems and the project is non-valuated. So in our case all material which we buy for Project is consumed at the GRN stage and there is no valuated inventory.
    However for "Annual Performance Report" it is mandatory to give the Opening stock of material.
    Can anyone throw some light how this can be calculated when we the Project is non valuated?
    Regards,
    Prasad

    Hi,
    This is little difficult to manage a material as valuated and non valuated. To make it non valuated you have to use a material type which is managed only on quantity basis and not on value basis like non valuated stock. Then you can do a material to material transfer posting. I haven't checked this scenario. For more info on this please refer these links:
    http://help.sap.com/saphelp_dimp50/helpdata/en/4c/227bb446e611d189470000e829fbbd/content.htm
    http://help.sap.com/saphelp_di471/helpdata/en/4c/227bdb46e611d189470000e829fbbd/content.htm
    http://help.sap.com/saphelp_di471/helpdata/en/4c/227ba746e611d189470000e829fbbd/frameset.htm
    http://help.sap.com/saphelp_di471/helpdata/en/4c/227be846e611d189470000e829fbbd/frameset.htm
    http://help.sap.com/saphelp_di471/helpdata/en/4c/227b8d46e611d189470000e829fbbd/frameset.htm
    Regards,
    Atal

  • Buget Exceed problem regarding material transfer in project system

    Hello Sir,
    I have a problem regarding budget in project system.
    when i do budget and release . and do any transaction
    with that budgeted wbs element in particular project.
    i get budget excced errors usally.
    however, budget remains more than exceeded buget.
    Let us touch with a example in brief, we have a buget for a L&T project 10 Lakh.
    Buget                                         Release                                          actual cost                                            total cost commitment
    10Lakh                                       10Lakh                                             8lakh                                                         1Lakh
    when i transfer a material from another project to this L&T project material worth is 50thousands.
    i get a errors for L&T project budget exceed with 40thousands.
    however in project budget remains 1Lakh remaining .
    why system shows errors for this material transfer worth rs 50thousands
    Please help me regarding this problem where is 1lakh budget
    with regards
    sanjay agrawal

    Hello sir,
    there is no any problem regarding budget supplement but if project sometimes
    remains 20lakh buget price remaining out of 50lakh.
    and need 1 lakh material price for transfer in project
    then why need to do budget supplement for 1 lakh if project
    remains 20lakh price rest.
    please guide me for above problems
    with regards
    sanjay agrawal

  • Problem regarding SAP Project System & Material Management

    Hello Experts,
    please check our process as below:
    Order confirms than sales order and project will create
    material of BOM is assigned to any activity in project so these material (RM) will be procured and consumed
    assign activity for all work done on material to produce FG or SFG.
    confirm activity whenever any work done like fabrication done so confirm and its cost comes to WBS.
    than we have to subcontracting process so dispach SFG from this and receive after activity done by third party.
    than more work is done and confirm these activity. than after all work done we get FG in stock. than delivery from project.
    We are facing issue in above business process of our client as below:
    1. process of subcontracting using project system as we are not using production planning. how we get any SFG for subcontracting process.
    2. if we confirm all activities and consume all Raw Materials than how we will get finished good in our project stock for delivery.
    3. after delivery from project how sales order affects with regards to completeness of this sales document.
    Please help for this.
    Note: Remember we are not using PP cos customer require detailed report of these process and capacity planning etc.
    Thanks
    Sunil

    Hi Sunil,
    Assume this is my project structure & attached components. I will procure this components externally. After GRN, This components will be issued to network with 581 Q movement type.
    Now we need to assemble this raw material to produce our FG, As these SFG are in our project stock. What we need to do for assembly process through PS.
    Also throw some light over benefit of using PS-BOM interface ( CN33 ) for attaching material components.
    Project
    WBS
    Network
    Activity A
    Gears
    Qty - 1
    Activity B
    Blades
    Qty - 2
    Activity C
    Stand
    Qty - 1
    Activity D
    Connectors
    Qty - 1
    Regards
    Gaurav Ahuja    

  • Project System Budget Control against Material Reservation

    hi all
    I need to control project system budget to stop/control creation of material reservation if budget is exceeded. I know that standard SAP PS budget availability control configuration could not handle material reservation.
    Will SAP Funds Management do the trick? any insight is greatly appreciated.
    Thansk,
    Tony

    Hi,
    Good afternoon and greetings,
    Wishing you a very Happy New Year 2007
    Please go through the following OSS Note
    Note 167405 - Totaling up zero values not possible
    Please reward points if found useful
    Thanking you
    With kindest regards
    Ramesh Padmanabhan

  • Report Painter Drilldown on Cost Element for Project Systems

    I am currently working on a report for Project Systems. I am trying to copy the functionality of the Internal Order summary (60I2-001) into report group 6P3. I was able to copy the whole layout and also the values of 6oI2-001 into a copy of 6PP4-001 but when I double click on "Balance" it is bringin up the ALV report that 6PP4-001 is using. I would like to call another report which looks like 6LS0-001 but contains Project System info made in report painter when I double click on Balance. Is this possible? Please let me know how.

    Hi Avinash,
    See my replies below.
    1 a & B: You are planning Qty on NWA and capturing costs - labor & Equipment on NWA elements.
    When  you are having elaborated to NWA-Element level, split your total work on each NWA-element and post labor cost. Thus you will have planned Vs actual costs at one place.
    coming to equipment cost - are you capturing using PO through GR?.
    2.a : Option1- create a separate WBS elements for materials and plan cost at WBS level. That value would be your total planned cost of material procurement as estimated. Under this WBS elements create NWAs and assign the materials. With this set up you can assign material and procure so that will have actual costs coming from GR.
    Option 2: Create a one General Cost activity and assign the total planned cost of material on this NWA.
    When you assign the material components, diligently you have to reduce the equivalent amount from the general costs activity. Also note that on component screen, you have to check box "Cost relevant" so that material cost will add to Cost NWA. Let the different materials  have their own valuation class and have default CEs accordingly. that would not be big issue.
    Please discuss with your MM team to get more information. Also my suggestion is to leave blank CE field in configuration.
    The option2 is very cumbersome and high risk but one have to be very cautious to reduce the value from Cost NWA in order to sustain the planned material costs whenever they added.
    3. I have answered the relevance of Cost relevance check box in above.
    Hope above makes sense.
    Thanks,
    Sudhakar

  • About reversal of Outbound delivery generated from Project system due to sale return

    Hi SAP Expert ,
    We have made delivery from project system using t.code CNS0 and billing document is generated with reference of sales order. Now Goods is return by customer due to some technical reason, We created return sales order with reference of billing document  and Credit memo with reference of Return sales order.
    What is T.code for making return delivery or reversal of  Delivery /PGI generated from Project system in sap r/3 ?
    Pls. suggest to me.
    regards
    VKM

    Hello,
    it depends whether in the billing document the material codes identifies the goods delivered and to be returned or not.
    If it's so, you can create a Return Sales Order with reference to the billing document, create the return delivery, and then the credit memo.
    If it's non so, you can create a Return Sales Order with reference to the billing document (but without copying the material items, and entering manually material code and quantity to be returned), then create the return delivery. Then you can create a Credit memo request with reference to the Billing Document or with reference to the Return Sales Order.
    To create the return delivery, you can run VL01N with reference to the Return Sales Order (just like for outboud deliveries), or from VA02, following the menu path "Sales document --> Deliver".
    Best regards,
    Andrea

  • Unit of measurement in project system

    Hi Experts,
    Its relevant to PS module. Base unit of material is KG whereas sales unit is M2 and conversion is maintained between both. Now I am using sale unit (M2) while entering material componenets in project. Then I am raising PR, PO, GR in project and withdraw the material in sale unit M2. But system updates the report in KG (under purchasing data tab in project). When I get material report, system shows reqmt qty in M2 but received qty in KG. Its confusing and doesn' serve the reporting purpose. Can we do something so that received and withdrawn qty will appear in M2 (sale unit) rather than KG (base unit)?
    Regards
    Dinesh Chauhan

    Hi,
    You inventory is maintain always in base unit of measure.
    You can maintain different unit in material master like,
    Order unit(Purchasing view) : - For Purchase Order
    Unit of issue(Plant data1) : - For issue material.
    You can see material stock in both unit of measure in MMBE.
    After enter material code you can see material stock, by changing material unit of measure you can also saw material stock in specific unit of measure.
    Maintain Order unit of measure in purchasing view and also active variable active unit( Enter 1 = active) in purchasing view
    Regards,
    Mahesh Wagh

  • In which tables (ABAP) the Project System Information Will be stored

    Dear Guruu2019s
    Happy New Year
    In project systems can we able to see, against the projects and against WBS what all the sales orders, Employees and material etc... That we assigned, in which STD report we can check all these assignments, from which tables (ABAP) it picks up the data to populate in the STD report.
    I need the Tables for preparing the Z- Report. Please help meu2026
    Regards,
    Bhanu Prathap

    The most common overviews with respect to sales and distribution can be obtained from CN54N/ CN55N or you can also use CNS54 / CNS55. Tables for the same are VBAK/ VBAP.
    For materials you can refer to CN52N overviews for material components and CO24 for missing parts.
    For resources, CN50N provides the capacity requirements and CMP9 workforce planning.
    Venu

  • Pricing Schema for Project System

    Dear Sappers,
    I'm configuring Pricing Schema for Project System(PS) module.
    The requirement is, the schema will be in such a way that it supports both excise, CST, VAT and service tax.
    In PS module the user raises a Purchase Order having procurement of material as well as taking service from Vendor.For this in PO he will maintain both material as well as service.
    I'm configuring the Pricing schema in MM - Purchasing - Condition.
    My question is for materials procurement, everything is working fine.But for service respect to activity number I want to maintain service tax and other cess in condition record.
    But to maintain service tax & other cess for activity number, I want the access sequence of sevice to be in Purchasing.I've taken the standard table for Plant, Vendor, Purchase Organinzation and activity number combination from External Service management and making a new access sequence in MM - Purchasing.All fields are coming but for Activity number, it not taking the document structure and showing error.
    How to overcome this??
    Any suggestions will be highly appreciated.
    Warm Regards
    PKB

    Hi Pankaj,
    Thanks for your suggestions.
    As per you reply, the access sequence is already maintain in External Service Management.But I want to bring the same combination Plant, Vendor, Purchase Organizartion and Activity number that is Table 97 to MM - Purchasing - Conditions- Access Sequence.
    I've tried to do it, but when I'm creating in MM - Purchasing, all document structure is copying except activity number.What I analyse the error is due to application area.Activity number is MS (External Service Management) area but i'm trying to do in M(Purchasing)
    Even though when I enter manually MS for the access sequence system is not taking.
    Suggest me.
    Warm Regards
    PKB
    Edited by: Pranaya Barik on Dec 11, 2009 12:09 PM

  • Project system: Purchase requisition coming from PS

    Dear Experts,
    I have a tricky problem. I want to exclude a specific number range for purchase requisition coming from the Project system.
    The current number range I have for the purchase requisition is let say: 10000000 - 19999999.
    I want to use another number range (50000000-59999999) for the purchase requisitions as an impact of material components of an network activity.
    What I've tried but it is not working properly:
    1. TC: OMH7 - I created a new number range as I mentioned above
    2. TC: OMEB - I've copied the document type NB to a new document type ZNB (NB = ZNB)
    3. TC: OPTT - as last step I've assigned the document type ZNB to the order category 20 (network)
    Please advice ASAP
    Thanks a lot in advance

    It should work as it works fine for me.
    1. You create the Internal number range (50000000-59999999) first and number it with an ID.
    2. Create the ZNB document type and assign the number range number (i.e., two-character ID)
    3. Assign this ZNB in OPTT
    If I've repeated what ever you've done/said, check the settings once again. It should work.
    Regards
    Sreenivas

  • Change material type and valuation class

    hi
    my client want to change material type and valuation class in their production system. but the material no. and some transaction had done by this material. anything i need to concern? especially, in FI part. thank

    Hey Changing of Material Type is one step
    Changing of valuation class is other
    and underneth that changing of account is another attached to the valuation class.
    The basic requiremnt will be that client want to change the G/L code attached to the valuation class.
    If you have already done some transaction it is not fininacialy right to move valuation classes.
    Tell in detail what is the requiremnt.

  • Roll out  Project systems

    Hi,
    Could you share with me regarding the main configurations and checks to be done while roll out the project in the point of Projects Systems(PS) module
    Thanks
    sudheer

    Hi Sudheer,
    Link: http://help.sap.com/
    Path: SAP Best Practices --> Baseline Packages --> Based on SAP ECC 5.00 --> Select Country: for eg, Localized for India --> Technical Information --> Building Blocks --> Select Country for eg, India -->
    Topic: J12 - Project System
    Here you will get both Configuration guide & Development master list
    Also kindly visit following link
    http://www.sapprojectsystem.com/
    You can get reference material.
    Regards
    Tushar
    P.S.Reward points if you find answer useful.

  • Interface Project System to Catalog OCI

    I am trying to implement SciQuest within Project Systems SPRO >  Project Systems > Material > Interface for Procurement Using Catalog (OCI) and I am difficulty navigating around SciQuest site.  The actual punch out works but when I click on 'Add to Cart' an IE session opens.  Has anyone experienced this type of behavior in other catalogs?  Is there certain configuration that the vendor (e.g. SciQuest) has to adhere to since this is done directly in R/3.  I am familiar with SAP SRM which is web based and this just works, however, when I do this in R/3 it is acting as if it was web based as is not.
    Any help would be greatly appreciated.
    Kind Regards,
    Sabina McLaughlin

    I haven't worked/implemented OCI but your post made me to search some resources on this.
    Found few OSS  (mentioned below) notes related to Catalog connection and hope this provides you with some leads.
    1092900
    1092923
    Link in SAP Help.
    http://help.sap.com/saphelp_crm20c/helpdata/en/0F/F2573901F0FE7CE10000000A114084/frameset.htm
    Regards
    Sreenivas

Maybe you are looking for