Materials in a work center

Is there a way to lookup all the materials that are being produced at a given work center? is there a FM that I could use?
Thanks for all our help.
Vinay

Hi,
For MF60, settings should be done in OSPP , here give ur plant & movement type as 311
1) MF60 - in MF60, Global settings icon plays a major role & check the date which ur giving
2) take ur current plan orders and input in plan order option
3) then go to Global settings remove all ticks & execute
Regards
kumar
Edited by: kumar kumar on Sep 19, 2009 1:14 PM

Similar Messages

  • Tag Work center to Materials in Production Order

    hey everyone,
    I need to tag the correct work center to the prod order. One Production order has say 5 materials and they have different movements on it. We need to fetch the correct work center for each material movement. I am able to find work center for materials that have entry in the RESB table but for material that is final produced has no entry in RESB thus we cant tag it to any work center.
    Does any one know how to tag the produced material to the correct work center according to the operation on that production order.
    any suggestions would be appreciated.
    thanks !!

    Laura: Please don't post the same question in different forums. Thanks!

  • Associate materials with work center

    Hello,
    For our chemicals production plant, vessels in which HALB products are produced are defined as work centers in SAP. Our business has a requirement that certain vessels can only be used to produce certain materials. Is there a way to capture this requirement in SAP, i.e. associate a work center with specified materials? Help is appreciated.
    Regards

    Dear Khan,
    work centers are not specific to any material production, u can restrict work center usage for the perticular task list by maintaing the field in work center basic data screen task list usauge.
    sree

  • Dyanmic work center selection in production order based on material

    Hi ALL,
    We’ve a business requirement to support the following functionality.
    There are four similar type of milling machines say MILL1 MILL2, MILL3, MILL4, we create a single work center called MILLMC by specifying total capacity of four milling machines in the capacity header screen of work center with 4 individual capacities. And we mention work center MILLMC in the operation of routings for respective materials.
    However, during production order creation, there needs to be provision for detailed planning of work centers as per the following requirements
    In production order, some operations can be performed on any one of the machines MILL1 MILL2, MILL3, MILL4, so provision needs to be there to enter exact machine on which it is performed in the production order operation after the details are copied from respective routing during production order creation.
    In production order, some operations can be performed on only MILL3, so system should select only MILL3 in the respective operation of the production order
    In production order, some operations can be performed on either MILL1 or MILL2 or MILL4 and not on MILL3, so system should not select MILL3 in the respective operation of the production order.
    Please provide your valuable feedback to support the above requirements.
    Regards,
    Satya.

    Hi Satyanarayan,
      Please do refer to the below document. I think the same concept can be used for work centers as it is used for resources in PI industry.
    Resource Classification in Master Recipe for Planning
    Regards
    Kalyan

  • URGENT........ACTIVITY TYPE AND THEIR ASSIGNEMENT TO WORK CENTER!!!!!!!!!!!

    Hi Friends,
    I have A REAL URGENT REQUIREMENT as far as activity type and assignment to Work Center is concerned.
    I work for a client who is a manufacturer of Paint equipment. I'm responsible for capturing the cost of an assembly activity of spray guns, which is the last step of routing.  However, there are 4 processes/steps of routing which are outsourced to the subcontracting vendors. we recieve the facbricated, anodised guns which are assembled in our factory.
    I need to get the cost of assembly, which I have created as an actvity type in KL01 and planned for the same using KP26. However the system is throwing up errors related to costing, and I'm not sure about the assignment areas in work center.
    And above all I'm not sure of various fields in KP26 like capacity field and what do we assign.
    can anybody help me with the series of steps for me to be able to pick up the cost. or if there is any sort of material in this regards, plz mail it to: __ email removed by moderator
    regards
    sandhya

    Hi,
    You need to do the following:
    1) Create an Activity type for the Assembly activity.
    2) Define a Work Centre in PP (T-Code CR01) which represents the location where the Assembly is carried out.
    3) Define a Cost Centre corresponding to the above Work Centre.
    4) Plan for the Activity quantity for the combination of the Cost Centre and Activity type (KP26)
    5) Plan for the Overhead Costs which are incurred on this Cost Centre which need to be included in the Standard cost of the Assembly.(KP06)
    6) Assign the Cost centre & Acivity type to the Work Centre in CR02.(This is possible only after you do 5 above)
    7) Execute the Plan price calculation (T-code KSPI)
    After you do all of the above, when you do the Costing Run, all the relevant costs will be picked.
    Ofcourse all the relevant master data for PP like BOM, Routing with the relevant assignments of materials to operations, etc should be in place.
    Regards,
    Assign points if useful

  • Tag production order to Work center

    hey everyone,
    I need to tag the correct work center to the prod order. One Production order has say 5 materials and they have different movements on it. We need to fetch the correct work center for each material movement. I am able to find work center for materials that have entry in the RESB table but for material that is final produced has no entry in RESB thus we cant tag it to any work center.
    Does any one know how to tag the produced material to the correct work center according to the operation on that production order.
    any suggestions would be appreciated.
    thanks !!

    Hi,
    Yes, one production order has only one material produced. this material can be found in CO03. But i cant find the appopriate work center for this material. Do you know how ? Because this material has no entry in the reservation table.
    thanks
    Laura.

  • Work center-Machine wise report

    Hi Guys,
    I have a work center for ex CNC in which i have taken 3 machines,in capacities i define the individual capacity for each machine & iam also able to split the capacity amoung the machines,Now if i want to take a report to give to the work center supervisor -list of the operations that i have loaded in the work center,<b>is there any standard report available where i can even get the detail of the load in the machines of particular work center?</b> otherwise pls give me some workaround

    Hi vijay,
    what u need is, day or weekly wise  prodution load for each machine .. am i correct?
    u need a report containing details about  what are all materials to be produced and its all operations for  each machine.
    In that case  u have to develop some customized Zreport.
    regards
    pradeep

  • Work Center: Capacities vs Scheduling tab

    Hi everyone,
    I am confused on the link between Capacities tab and Scheduling tab when setting up the Work Center. When I run MRP and set it to Lead time scheduling and capacity planning, which figures (for setup, processing, teardown, etc time) are used for the calculation of start/finish basic date and start/finish production date? Is it the figures (setup, processing, teardown, etc time)from Capacities tab OR Scheduling tab in the Work Center? What is the link between Capacities and Scheduling?
    Also, in Scheduling tab, there is also capacity category which you have to input. Is this also linked back to all the capacity category stated in the Capacities tab? If we have more than 1 capacity category which do we choose to set in Scheduling tab?
    I would be very grateful for any input.
    Thank you very much.
    Cheers,
    Sue

    Hi,
    The link between the scheduling and capacity
    in Capacity tab we will give the capacities of particular machine ex work center is machine so we are declaring the capacity of the machine. saying I have capacity of eating 10 chocolates that is you're capacity.
    if machine is working defiantly labor will be there so we are defining the labor capacity also but for calculating the dates we are using the machine capacity only which we are defining in the scheduling tab
    in the scheduling tab we are declaring that for any MRP or Production consider the capacity of the Machine for calculating the dates like start date and finished dates.
    In the routing we are declaring for manufacturing of X quantity of materials we require machine time, labor time setup time etc
    EX:
    Machine Capacity in WC= 2 hour
    Labor Capacity in WC= 2 Hr
    so in the Scheduling Tab we will give machine to calculate the dates.
    In routing for Manufacturing of 1 ea we require
    Machine time = 1 hour
    Labor time = 30 mins
    Set up = 20 mins
    so if you have given demand for manufacturing of 10 EA run MRP
    then it will give 5 days to manufacture 10 EA because work center capacity is only 2 hour..
    simple logic for manufacturing of 1 EA it takes 1 hour of machine time so for manufacturing of 10 EA it takes 10 hours but my capacity is only 2 hours per day so 10/2=5 days.
    hope this may clear you're dout
    Regards,
    Ravi

  • Work Center specific Authorization

    Hi all,
    My specific requirement is we have 7 various plants and each plant having 2 work centers and planner groups like one is for Elect and other is Mech. Now my client wants that particular plant only have the authorization for its particular work center and planner group.
    Means if plant 1 having work center Elect1 and mech1, this plant is not authorize to make notification or order of plant2 work centers say Elect2 and Mech2. Is it possible? What am I suppose to do for that?
    Thanks,
    Anish

    Hi Anish,
    Nothing is required to be done by Functional Consultant. You just need to contact your basis team.
    You have to provide him role/profile for which you want to change authorization for auth object C_AFVG_APL.
    This auth object will have fields as below
    1) Plant
    2) Work center
    3) Action
    The following values are used for the actions:
    01: Create
    02: Change
    03: Display
    41: Assign PS texts
    42: Allocate materials
    43: Assign PRTs
    44: Assign activity elements
    You need to tell him for your role/profile - which plant, which work center and which action should be allowed.
    So accordingly user will have only those limited authorization.

  • Work Center - Material Number

    Hello,
             Is there any function module or any table available where i could check the materials assigned to a particular work center.
    I have a report to develop where i have the value of plant and work center. I need to display the material corresponding to this selection criterion.
    I have searched the forum, but could not find a suitable reply to solve this query, hence posting one.
    Thanks
    Nayan Kurup

    Hello Anil,
                    Thank you so much for the reply. I have already cheked this table ,and the data does not exist there.
    Any other sugestions ??
    Thanks
    Nayan

  • Require help on coast center and work center tables through sales order

    dear experts
    my requirement is to report the cm05(capacity planning ) transaction.
    The original capacity planning consists of workcenter details.
    but my client needs the report as follows
    on which sales order and on which work center we require the capacity of materials.
    any tables and fields for this report please.
    help needed.
    kindly update me.

    hi,
    Please explore table CAUFV View "Order Headers PP/CO" ,here you will find the relationships between the three.
    Regards,
    Neha

  • Operations Executed at a Particular Work Center for a Sales Order

    Hi All,
    We are using a MTO scenario. I have to get a report in which I have to list work center wise operations (and the corresponding material) which are carried out for a particular sales order.
    User will create a sales order, and then do Sales Order based MRP in MD50. System will do a BOM explosion for the header material and will generate planned orders for the production relevant materials. User will then convert all these sales order specific planned orders to production orders. For a particular sales order these would be many operations (at different BOM levels may be ) that would be carried out at a particular work center. I need to get a logic for generating this report. Is there any FM etc or table table-field fetchig logic....
    Regards

    hi,
    maintain initial screen entry as sale order.
    Pass values to AFPO table. Identify all AFPO-AUFNR values which satisfies AFPO-DAUTY = 10
    Transfer AUFNR values to AFKO and check AUFPL (Routing number of operations in the order)
    Transfer AUFPL  to AFVC and check the value of AFVC-ARBID (Object ID of the resource)
    Transfer ARBID to CRHD and check value of ARBPL (Work Center)
    Regards,
    Pavan

  • What is the link between material processing & work-center

    Hi all,
    I have two types of material & few work center.
    How can I determine, that which work centers could be applied over a specific material for the material processing.
    Regards,
    Saurabh

    Dear Saurabh,
    You may allocate one or more capacity categories to a work center.  Capacity categories are defined in customizing.  Examples are labor, machine, energy and so on. 
    You must maintain data to enable the system to calculate available capacity at that work center for that category.  Examples include calendar assignment, start time, stop time, length of breaks, utilization, number of individual capacities. This is maintained in the capacity header screen of the capacity category for the work center. 
    If you indicate that a capacity is pooled, then it may be used by several work centers.  An example is a setup team.  They can perform setups at several work centers but can only work at one work center at a time. 
    Routings within a routing group are used for producing similar materials. One routing group can also contain routings with similar production processes.
    The alternative sequence enables you to select alternative operations for a sequence of operations - for example in the case of different work procedures for different batch sizes or capacity bottlenecks.
    The parallel sequence enables you to process operations independently of others.  
    A routing contains the operations to be performed, their sequence and the various work centers involved to manufacture an item. 
    A routing can include the following:
    *The standard values (times) for activities such as setup and processing 
    *Work centers where the operations are performed
    *The material components allocated to the operations
    *Any production resources / tools necessary to perform the operation
    *Inspection characteristics for operations where inspection is carried out
    *Instructions of what to do at each operation
    *Skills required to perform the operation
    Reward points if it is helpful.
    Regards,
    Naveen.

  • Costing at work center

    hi guys,
    I have two materials and produced on one work center.But i do not want to do costing for one material.
    Please explain how to do it?
    Regards
    ramkrishna

    Hi Ramkrishna,
    You could deactivate the costing relevancy indicator in the routing opertion of the material for which you do not want operation costing.
    Regards,
    Prasobh
    Reward your points if this was helpful

  • Change Work Center on a Prod. Order

    Hi,
    I have been searching through the archives and found a lot of maybe, but no final ideas.
    How do you change a Work Center on a Prod Order?
    Anybody has a suggesfull way of doing it?
    Thanks
    Andy

    Andy,
    Try using BAPI_ALM_ORDER_MAINTAIN. The documentation states this BAPI is for maintenance orders, but we have used it to change the bill of materials and other parts of the production order.
    Glenn

Maybe you are looking for

  • Family Sharing on the Apple TV 3

    I Have multiple apple products, of which are some apple tv's. until a few days ago all the devices were using the same Apple ID which was mine. We recently decided to use separate Apple id's for our family members, and using family sharing among the

  • A short dump occurs when accessing SAP BI 7.0 using GUI 620

    hi, i'm getting this error while executing..DTP. solve this .....

  • Delivery copy control Issue

    Dear All, I created a new order type, Item category, Delivery type and delivery item category. Maintain copy controls  too. But system is not allowing to do delivery.Error Message ' Copying is not poss.because an entry is missing in Table TVCPL; ZTAN

  • Which Virsa product to download

    Hello everyone I am trying to  download Virsa compliance calibarator & Role Expert. I could not find much information in installation guide. Can anyone please let me know which Virsa to download for CC and RE. In SAP Marketplace ..i noticed the follo

  • Authenticate to proxy object

    Hello, I'm creating a Socket using a Proxy object (can either be a SOCKS or a HTTP proxy) inside a SocketFactory. Now how can I authenticate to this proxy if it requires username and password? (I'm not looking for a global solution as not all traffic