I need to tag the correct work center to the prod order. One Production order has say 5 materials and they have different movements on it. We need to fetch the correct work center for each material movement. I am able to find work center for materials that have entry in the RESB table but for material that is final produced has no entry in RESB thus we cant tag it to any work center.
Does any one know how to tag the produced material to the correct work center according to the operation on that production order.
any suggestions would be appreciated.
thanks !!

Laura: Please don't post the same question in different forums. Thanks!

Similar Messages

  • To find 'Maintenance Work Center' for Equipment (without Production order)

    Hi,
    I have a Report for - 'Equipment BOM' - IB03.
    Problem: How to find the 'Maintenance work Center ' For Equipment ? (IE03--> Organization > Responsibility> Main. W.Cntr)
    [ Note: For Client -->  It's not necessary that each Equipment has Production Order, Few Equipments are taken only for Repair purpose, Equipment is there in table - EQUI,
    So - Not possible to fetch from AUFK, HIKO or any other order tables. ]

    I have a Report for - 'Equipment BOM' - IB03.
    Problem: How to find the 'Maintenance work Center ' For Equipment ? (IE03--> Organization > Responsibility> Main. W.Cntr)
    [ Note: For Client --> It's not necessary that each Equipment has Production Order, Few Equipments are taken only for Repair purpose, Equipment is there in table - EQUI,
    So - Not possible to fetch from AUFK, HIKO or any other order tables. ]
    EQUZ-GEWRK has the main work center. Pass the equipment number and valid-to date to get the main work center.
    Cheers
    Sujay

  • Block PP Work Center capacity  when breakdown maintenance order create on that work center

    Hi All,
    My Client want to Block PP Work Center  capacity when breakdown maintenance order create on that work center, how can i do it ..
    Please help me.
    Payal

    Dear Sir,
    I have Done Every think but still Production Order is create.
    CM50
    OIOI
    CO02
    Payal

  • Change Work Center on a Prod. Order

    Hi,
    I have been searching through the archives and found a lot of maybe, but no final ideas.
    How do you change a Work Center on a Prod Order?
    Anybody has a suggesfull way of doing it?
    Thanks
    Andy

    Andy,
    Try using BAPI_ALM_ORDER_MAINTAIN. The documentation states this BAPI is for maintenance orders, but we have used it to change the bill of materials and other parts of the production order.
    Glenn

  • Changing operations work center during creation of  PM order

    Hi all,
    I am looking for BADI or EXIT in order to change operationS work center which created from maintenance calls.
    Does anyone know such possibility?
    Assaf

    Assaf,
    Have a look at BADI IWO1_TL_INTEGRATION2.
    Also see [OSS Note 925072|https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=925072]
    Which system are you running?
    PeteA

  • No Funds Center error while creating Production Order in CO01

    Hi SAP Consultants,
    I am trying to save production order in transaction CO01 but I am getting error saying "No funds center entered/derived in item 00001"
    Diagnosis
    In company code (&2) the component Funds Management is active. This requires the entries or the derivation of a funds center.
    You can use the following elements to derive the funds center: company code / account  or CO object .
    Procedure
    Enter a funds center or ensure that the funds center can be derived from the possible assignments by:
    assigning a funds center in the commitment items- master record or maintaining the assigning of a funds center to the CO object.
    My company is a public sector company and Funds management is active.
    Any help would be appreciated.
    Thanks in advance.

    Hi,
    Kindly check for item 0001 in the Material Master which Profit Center is maintained and check if a Funds center is assigned to it. This should solve your problem.

  • User exit/Badi for changing operation work center based on service product

    Hi,
    I have an requirement to change the operation work center based on the service product in IW31/IW32 transaction. I am using the BAdi 'IM_SM_BADI_READT399A' for changing the main work center. It changes all the operation work centers except the first one. But I need to change it all the operations.
    Thanks in Advance.

    I am using the enhancement spot 'IWO1_TL_INTEGRATION2' for changing the first operation work center

  • Batch determination of configurable materials in production order

    Dear All,
    I'm facing the follwoing problem i have a configurable material which contains another configurable material in its BOM the item catergory for the configurable item is N , the problem is that during batch detrminittion of the material in the production order the system issues this message ' Batch entry/batch split not allowed for component xxxxx
    Message no. CO584'
    however the batch determination for other material types is workinf fine
    please advice
    regards,
    Ahmed Sobhi

    Hi Ahmed Sobhi,
    Please check these steps that you have done exactly like this;
    For that you have to do five important steps or features you have to know OK.
    1) Batch number assignment: We use this function to assign a batch with a number that uniquely identifies it OK.
    2) Batch Specf: To describe each batch uniquely using like Characteristics and characteristic The values. are allocated in the material master.
    3) Batch status management: To indicate weather a batch is usable or unusable: We can set (a) Manually in the batch master record or at goods receipt and (b) Automatically in the usage dissension in quality management.
    4) Batch Determination: We can use this function for various criteria to search for batches that are in stock (a) movement type: When posting goods issues (b) When combining suitable components for order types.
    5) Where used list: The batch where used list shows the path of the batch from its procurement to its delivery to the customer.
    6) Active Ingredient Management: This function is to administrate and process materials with active ingredients that are to be handled in batches OK.
    Condition types: Say for x material if we want to determine the batch at the movement type/ plant/order type.
    Access Sequence: It will checks weather the batch determination is done with movement type/ plant/ material &
    order type/ plant/ material.
    Strategy type: We will assign here condition type and Access sequence and as well we have to maintain Class type: 023
    sort sequence, batch split
    Batch Search Procedure: Here we will define the search procedure and using the condition type here OK.
    Batch Search Procedure Allocation and Check Activation: Here we will assign the search procedure to the movement types and for order types as well
    HERE THE BELOW FOLLOWING DATA WILL GIVE YOU RIGHT UNDERSTANDING OK:
    a) It will looks for the search procedures.
    b) It searches through the strategy types in the search procedures for a valid search strategy.
    c) Characteristics from the selection class of the search strategy looks for batches with suitable specifications.
    d) Then it will looks for weather the batches are available.
    e) It sorts the batches that are available according to the sort rule from the search strategy.
    f) Then the system selects a proposed quantity with proposed quantity from the search strategy OK.
    Go -
    > Logistic General -
    > SPRO -
    > Batch Management you can find every thing there it self OK.
    I hope it clears you, any questions revert me back OK.
    Regards,
    Madhu.G

  • Profit Center Display Unnormal  IN  Production Order

    If I choose Special as type for  Production Order, Profit Center wont display normally, it'll display nothing or something from the previous/next  Production Order .
    And I'm using the DI to create Production Order , but there's only one field availble that is  ProductionOrders.DistributionRule .In this way , full  DistributionRule  (2 dimenssions) cant be displayed.
    thanks.

    yes, Im gonna use ui to cover that place and make the value as same as the field OcrCode
    Is Profit Center has something to do with the accounts? there should be , I'm not aware of it .

  • Need the report  for staged materials in production order

    Hi
    My user is staging the materials multiple times for the one production order.Due this reason multiple TR were generated .Because of Multiple TR , user is generating  multiple TO for issuing the material to a production order.
    Is there any way to stop the  staging process for the materials already staged.I would like to know whether there is any report which give the details of staged materials and corresponding TR & TO for a production order.
    Thanks
    Sankar

    Hi
    Warehouse activity Monitor is best tool/ report , which give the details of staged materials and corresponding TRs & TOs, to stop/cancle you have to use related WM transactions.
    To setup WM moniter user below document
    http://help.sap.com/printdocu/core/print46c/en/data/pdf/LEWM/MMWM.pdf
    Thanks
    Madhu

  • Working with Projects instead of Production Order

    Hi Experts,
    In one of our manufacturing companies we are trying to implement SAP B1. The company has MS Access currently. We work with projects and each sales order consists of many projects. Taking it to SAP B1, there is the option of production orders but that works with Item no. for final product with BOM. Our product is not consistent and every time the product can change according to customer requirement. That means if we go with the SAP's production order functionality we will end up creating many (ghost) items everyday, and that (item) would be of no use next day. What can we do to solve our problem with SAP B1? Or SAP B1 can not handle projects? We are ok to work with SDK but not with a big cost.
    Please help if possible.
    Thank you.
    Kind Regards,
    IC

    Hi,
    There are actually many things which needs to be basically studied before a workable solution can be determined and its applicability can be assessed.
    For sure, there are lots of Items involved and each Project(Lets say BOM) has different combination of items which are not standard but frequently change.
    Here first it needs to be determined, do we need to keep a track on the items, its value and the left over ones as well, because items would be involved in the combination which would either be purchased or kept in inventory for future purpose.
    Secondly, can it be feasible where we can define a standard BOM (project) which has the normal ingredients(items) to make the final product and then based on that some changes can be made when Production Order is created (like changing the child items (excluding some and including some).
    And also, can there be some process by which we can add the volume of items in the database using some external tool, like SDK or an add-on.
    Actually, there are lots to be thought about and tested. I would prefer if someone who has implemented such scenario/business gives you some guideline about his procedure.
    Kind Regards,
    Jitin
    SAP Business One Forum Team

  • Reserved materials for production order

    hi all,
    i am creating a report.if i give production order number it should get the details like reserved material,plant,quantity,everything about that.
    give me an idea about that.

    Hi,
    Check with 2LIS_04_* DataSources.
    Thanks
    Reddy

  • Work Center Block

    Hi Experts,
    We have one scenario
    W/C in PP(wc category m/c) = Equipment in Plant maintenance
    Is it possible to block the W/C automatically whenever there is creation of maintenance order for equipment(w/c for PP) so that it is blocked in routing and can not be used in production.
    Thanks in advance,
    Amit Kataria

    Dear,
    You can lock work center. if work center is lock, now production order will be created with locked work center.
    If you require that whenever maintenance order created against specific equipment in which locked work center used, system will not allow to create production or production order execution. In SAP Maintenance, there is integration with PP that whenever maintenance order created, system will not allow to execute production order. Kindly consult with you PM consultant in this regard.
    Thanks
    Muhammad Ashfaq

  • Change work center

    Hi all,
    Please excuse my ignorance in what is probably an easy operation.
    What is the transaction code for changing a work center that a production order is setup default to be completed in?
    For example if i have product 'A' that is usually completed in work center '1' but I want to change the data so that next time and every other time I create this product it identifies work center '2' on the production order.

    Hi Gman,
       For producing "Product A" currently you are using work center 1. Instead of using this work center 1 you want to use work center 2. To change the work center, you need to change the routing for the "Product A". Go to CA02  and enter the material and select the routing and press operation, in the operation you will see the work center 1. Change the WC1 to WC2 and save it.
      After changing this, when ever you want to produce "Product A", system will select WC2.
    Hope it clears your doubt. Revert back if you have any questions.
    BR / US

  • WIP AT WORK CENTER

    Hi All,
    How to get details for Work center wise WIP per product / order?
    Thanks & Regards
    Varma

    To get a report of WIP values per Plant, material and order number, you need to run the Production order overhead and then run WIP (in a test mode if you do not continue to settlement) the standard WIP report will give you:
    value of WIP, plant, material, and order number 
    Summarize it as you want.
    WIP is calculated for the ORDER while work centers are at a lower level, so you won't get WIP in a Work Center.
    Althea