Message CO437, Process order

Hi Experts,
Where we can change message CO437 from warning to error. I checked in OPJB but did not find. The message is there in SE91 transaction.
In which transaction we can see the message CO347.
Pl help me to change this message.
Thanks & Regards,
Vikas

Hi,
This message description looks like this (from t100 table)
EN       CO                     347     Unit of measure & does not support decimal places
Please let us know from which transaction you are gettin this error
Y u wnat to change this in to warning and its a std message which gives information that unit of measure is not allowed for decimal places.
For this you need to maintain number of decimal places in CUNI transaction for that unit.
.If it is from MM01 or MM02 in additional data you need to maintain the fraction in conversion fields.
For example:1 Kg =10.5 Pc,you need to maintain in material master as 10KG=105 pcs
Hope it helps

Similar Messages

  • Message Type - Process orders

    Hi Gurus,
    What is the message type and Idoc type for the process order? I found the message type LOIPRO for the production order, but didn't found for process order.
    My requirement is to send the process order details to a logical system when the process order is created / released or changed.
    Thanks
    nagarajan

    Hi      Nagarajan Ramudu         
    Program: RCCLORD-Generate Production Order IDocs
    Fm: CLOI_MASTERIDOC_CREATE_LOIPRO
    Message Type         LOIPRO (Production Order)
    Process code ABI_AIDN_IN (inbound)
    check below useful link:
    Re: Process Orders, send idoc (LOIPRO) while creation/modification(COR1+BADI)
    With above info you can resolve the your issue
    Thanks
    Ramesh

  • REGARDING PROCESS ORDER CREATION

    Hi All,
    While creating the process order for material, system showing the message that "Manual process order cannot be created for this product". But if we try with another user id, i could able to create the order for the same material.
    Plz suggest the solution to get rid of this error.
    Thanks
    Arvind S

    Hi,
    The message "Manual process order cannot be created for this product" clearly indicates that the user is not authorized for Manual process order creation by COR1 transaction for this material and may be this material is planned through MRP or SOP etc. and in critical or certain situations manual process order creation is allowed to another user/user id for the same material ( type of materials/material code).
    Some time organizations put such restrictions through enhancements. You can search the exact reason or logic of restriction by the help of ABAP consultant.
    Regads,
    Narresh

  • Error Message while cretaing a Process Order

    Hi all,
    While trying to created a Process order I am getting this message.
    You cannot make an assignment to make-to-order stock
    Message no. CO684
    Diagnosis
    The component cannot be allocated to an individual stock because make-to-order production and engineer-to-order production cannot be executed with this order.
    A possible cause is that you are trying to create an order with reference to a sales-order/project, where an account assignment to a sales order/project is not allowed in the settlement profile that is assigned to the chosen order type. This is inconsistant.
    Please advice.

    Dear,
    Go to t-code OKKP and clicking sales order check box First enter into OKKP t-code then select your the controlling area, then select activate component controlling indicator double click on it ., then you will found sales order check box.
    In addition to that please check these Note 307059 and Note 317715 and 432109, 861670.
    Please try and come back.
    Regards,
    R.Brahmankar

  • Cost error message at the point of saving a Process Order

    Dear Experts,
    Raw Materials R458 and R467 are processed to produce semifinished material S229
    While creating a Process Order for material S229, at the point of saving the process order I get the following error messages:
    1 No cost element segment exists for 21501000 on 07.07.2011
    2 Cost Element Group 2950 does not exist
    At the point of saving, cost gets calculated by the system.
    Which account(s) is this cost posted to?
    Is it the ''Offsetting entry for inventory posting'' account  of the Raw materials R458 and R467? or
    Is it the ''Offsetting entry for inventory posting'' account  of the Semi material S229? or
    Is it the Cost Center to which the Resource is assigned to?
    How can I view this calculated cost value within the particular account?

    Hi,
    1. For error No cost element segment exists for 21501000 on 07.07.2011
    Can you check whether you have maintained valuation type in the accounting tab? Also have you maintained costing tab? If you have maintained then go to OBYC that is in GBB with account key VBR GL may have not maintained. Ask your FICO guy to check this.
    2. For error Cost Element Group 2950 does not exist
    Go to below link
    Cost element group does not exist. S_ALR_87013620 report
    Regards / US

  • Process Order Warning Message while doing the Goods Receipt

    Dear All,
    While doing the GR against process order via t.code MB31, we are getting a warning message which reads u201CProduction date of bch 110420 (17.06.2011) does not match the prod. date entered (26.08.2011)u201D this happens only if the batch number already exists in the system for the same material code , in this scenario if the user ignores the warning message & posts the document the existing batch number production date also will be over written with current/inputted manufacturing dateu2026 this will collapse the batch traceability. Is there a way to customize where we can have a different production date for same batch number?..
    For example:
    Batch Number: ABCD
    Production date 10.02.2011
    Batch Number: ABCD
    Production date 11.02.2011
    Batch Number: ABCD
    Production date 12.02.2011
    Regards,
    Sivanandan

    I'm sorry to say that I find your requirement to be absolutely not logical; a batch is, by definition, a homogenous quantity of a material, that you want to separate by it's characteristics from other, different, quantities of the same material.
    If you decided that manufacturing date is a characteristic of the batch, then it has to be unique for one batch.
    So, as I see it, you have two options: either decide that manufacturing date is not important and do without, or have different batches for the different dates.

  • Warning message during batch determination while doing GR for process order

    Hi Experts,
    During delivery against process order for all SFGs and FGs, we are getting warning message u201CInvalid batch according to selection criteria in batch determinationu201D.
    Following settings maintained for batch determination in process order.
    Condition table for order/material type maintained
    Access sequence maintained for order/material type
    In strategy type above access sequence has been maintained. The common class and sort sequence created for all materials in the plant have also been assigned to this strategy type. In batch split changes allowed box has been checked and quantity proposal maintained as 1.
    In search procedure control maintained for order/material type. Search procedure has been assigned to all process order types and check activated.
    In spite of the above when GR for order is taking place , system is throwing warning message.
    GI of components is being done through backflush and without any warning message.
    Please advise how to ensure proper batch determination during GR against order.
    Regards
    Sm.

    Issue resolved by removing required indicators from characteristics which were not being valuated but were maintained in the class assigned to SFGs/FGs.
    Regards
    Sm.

  • IDOC: Process order: Message type LOIPRO

    Hi
    I would like to know here no other way to download LOIPRO idocs as soon as the process order or production order are created/changed.
    Currently i'm using program rcclord and rccltran to create idocs. The problem I see here is that during every execution ALL orders, disregarding of the status (i.e. closed orders as well), will be exported.
    G.
    Message was edited by: Giovanni Baumann

    Hi Baumann,
    You can use the BADI WORKORDER_UPDATE
    I am using this for releasing Process Orders. I hope this will help you..
    *Appending the Selection Screen fields.
    *Process Order
      s_rspar-selname = c_selnam1.
      s_rspar-kind    = c_kind.
      s_rspar-sign    = c_sign.
      s_rspar-option  = c_option.
      s_rspar-low     = im_ord_header-aufnr.
      APPEND s_rspar TO t_rspar_tab.
    *Material Number
      s_rspar-selname = c_selnam2.
      s_rspar-kind    = c_kind.
      s_rspar-sign    = c_sign.
      s_rspar-option  = c_option.
      s_rspar-low     = im_ord_header-matnr.
      APPEND s_rspar TO t_rspar_tab.
    *Planning plant
      s_rspar-selname = c_selnam3.
      s_rspar-kind    = c_kind.
      s_rspar-sign    = c_sign.
      s_rspar-option  = c_option.
      s_rspar-low     = im_ord_header-werks.
      APPEND s_rspar TO t_rspar_tab.
    *Order category
      s_rspar-selname = c_selnam4.
      s_rspar-kind    = c_kindp.
      s_rspar-low     = im_ord_header-autyp.
      APPEND s_rspar TO t_rspar_tab.
    *MRP controller
      s_rspar-selname = c_selnam5.
      s_rspar-kind    = c_kind.
      s_rspar-sign    = c_sign.
      s_rspar-option  = c_option.
      s_rspar-low     = im_ord_header-dispo.
      APPEND s_rspar TO t_rspar_tab.
    *Logical System
      SELECT  SINGLE rcvprn INTO v_opt_sys FROM edp13 "#EC *
       WHERE  rcvprt = c_rcvtype AND mestyp = c_messageid.
      s_rspar-selname = c_selnam6.
      s_rspar-kind    = c_kindp.
      s_rspar-low     = v_opt_sys.
      APPEND s_rspar TO t_rspar_tab.
    *Message Type
      s_rspar-selname = c_selnam7.
      s_rspar-kind    = c_kindp.
      s_rspar-low     = c_mesageid.
      APPEND s_rspar TO t_rspar_tab.
    *This statement will submit the programme RCCLORD using the table RSPARMS
    *which holds the fields to be filled in the selection screen for RCCLORD and return
      SUBMIT rcclord USING SELECTION-SCREEN 1000
                     WITH SELECTION-TABLE t_rspar_tab
                     AND RETURN.
    Cheers
    Prasad

  • Regarding Error Message while releasing Process Order

    Dear friends,
                              While releasing process order i m getting following error message.
    " Storage location in PUB(loc1) is not same as storage location (loc2)''.
    how to remove this error and release the order.
    Thanks & regards,
    Sandip Sonar

    Hi Sandip,
    The error message LP 099 'Stor. location in PUB X is not the same as prod.stor. location Y' is issued when the system finds  inconsistancy in your customizing of the couple storage location - Production supply area for your components in your process order.                                                                               
    The logic of the storage location determination is the following ...
    The issuing storage location is determined in three steps:                                                                               
    1. First, the issue storage location of the material to be issued   (MARC-LGPRO) is transferred to the material master from the  MRP    data if it is filled.                                                 
    2. The system overwrites this value with the issue storage location from the bill of material (RC29P-LGORT, STPO-LGORT) if it is     filled.                                                               
    3. If the operation to which the component is assigned in production  order contains a work center with supply area, the storage    location is transferred from this supply area (PVBE-LGORT).     However, this transfer is only carried out if storage location  data (MARD) is maintained for this storage location for the    material.                                                                               
    The logic of the supply area determination:                              
    Priority of supply area determination for WM staging is as follows :     
    1. Supply Area of Work Center               (highest priority)   If no supply area defined look to                                     
    2. Supply Area in item of Bill of material  (second priority)   If no supply area defined look to                                     
    3. Material Master View MRP2                (third priority)         If no supply area defined -> Error message LP 099                                                                               
    I hope this helps in sorting the issue.  
    Regards,
    Mauro

  • Process order SLOC maintenance error message

    Good Day SAP expert!
    Previously when we were in SAP4.5, when an SLOC is manually assigned to a component inside the process order, we get a warning message if the material is not yet maintained in the SLOC.
    In ECC, we get an error message that the SLOC is not found for a certain material. Can this message be configured to give only warning instead of error?
    Thanks!

    Hi,
    Thanks for the reply. Where is the config you have mentioned?
    In response to other advise to enter the material-SLOC in MMSC, we do know this setup but would like to avoid it since once you move inventory in a specific location, the SLOC view would automatically be created thus no need for MMSC initially for new materials. We would like to have the previous warning message only so that user can proceed manual assignment in Process order instead of getting error.

  • Process order CLOSE:Message no. BS013

    Hi Gurus,
    I am trying to CLOSE some Process orders which are TECO status,(All are TECO status, and Settled) but when I execute those it gives error messages, and the Log says,
    System status CRTD is active (ACT 112033 0011 )
    Message no. BS013
    Diagnosis
    Object ACT 112033 0011 has system status CRTD (Created).  According to this status, transaction 'Complete' is not allowed.
    Procedure
    You can only carry out the requested function if this is allowed according to the status of the object.
    your time greatly appreciated,
    Paartha

    Hi Partha,
    Our internal systems behave the same. The reason is that the activity
    cannot be set to TECO unless it has been Released. You can see for any
    activity that setting TECO is not allowed via Edit -> Status -> Complete
    Technically unless the activity is at least at status REL. Therefore,
    when you try to set TECO for the project you get BS013 because status
    CRTD is active for the network activity.
    The system shows TECO as an allowed option for the project as it is
    allowed but only as long as all pre-requisites are met. The alternative
    would be for the system to do the pre-requisite checks before deciding
    whether TECO should be shown as allowed or not. This would not be good
    from a performance viewpoint.
    Regards,
    Abhisek

  • Batch Number field in IDoc for Process Orders (message type LOIPRO01)

    Hello PP experts,
    Just wanted to ask if anyone of you have worked with message type LOIPRO01 (IDoc for process orders)
    There is a segment-field in this IDoc  E1RESBL-CHARG which has description of "Batch Number"
    We tried to assign a Bath Number for an Order (using t-code COR2 --> "Goods Recpt" tab under "Receipt" section), generated an IDoc for this order, but upon checking the E1RESBL-CHARG field of the IDoc it is not populated with the Batch Number.
    The material in the process order is FERT, so technically we're trying to assign a Batch Number in one of the process orders for a Finished Goods material type,  so not on the component level.
    Can anyone here verify:
    1. is the E1RESBL-CHARG field of IDoc LOIPRO01 intended for the Product Batch Number?  If Yes, how do we populate that for in the IDoc?  --> Do I need to have a Reservation/Dependent Requirement for the Product for the Batch Number to be populated in the IDoc?
    2. If E1RESBL-CHARG can not be populated for a Product that has no Reservation/Dependent Requirements, Do I have any option of populating this field with just the Batch Number assigned to the Process Order of that product?

    Solved - LOIPRO01 IDoc does not pick up the Batch Number from AFPO table, instead from table RESB.    We need batch from AFPO and just created a lookup using the Process Order Number as import param

  • Error while creating a process order

    Dear Guru's
    While creating a process order ,i am facing an error.
    "Unable to create batch. Storage location BPSS is invalid for material 112100050
    Message no. 40116".
    How to assign specific storage loaction to that particular material.I have assigned in material master "work scheduling tab",But it was throwing an error while doing process order.Pls help me to solve this problem.
    Thanks in advance,
    Rgds,
    cherukuri

    Hi Cherukuri
    Are u using special procurement key "80"? It seems that storage location is not mentioned for the header material in the production plant.
    Maintain this using T Code MMSC. It will solve ur issue
    Rgds

  • Error for open process order when BOM alternative is not found

    Dear colleagues,
    When I open process order. BOM alternative is selected according to the production version. But when  BOM alternative is not found system gives only information message and I can open process order, I want to prevent open process order when there is no BOM alternative according to the production version. Because the Bom can be deleted after creation production version.
    Thanks for your helping,

    Hi,
    U need to use an enhancement at the creation of order to check the active status of the bom and restricting the order creation when BOM status is inactive.
    see whether following enhancement is useful for your scenario:
    PPCO0006 Enhancement & EXIT_SAPLCOZF_003
    Please confirm.
    Regards
    Suri

  • Process Order accepts Confirmation & GR from BAPI even after Confirmed

    No matter what i try the formatting and CRLF go for a toss in this text.
    Hi PPPI Gurus,
    I am a beginner in this area and request your help.
    We are implementing a project where the process order Confirmation in SAP ECC 5.0 in SAP PPPI module is done using xMII which call the BAPI_PROCORD_CREATE_TT     RFC.
    The customer wants to (certain times) do a final confirmation without actually completing the order e.g if the Order Qty is 100 then, they want to just manufacture 25 and then do a final confirmation, after which SAP GUI screen does not allow any Process order Confirmations against that process order.
    We are using the BAPI_PROCORDCONF_CREATE_TTRFC to do multiple PO Confirmations and GR for particular Process order. Below is a scenario
    Case 1:
    1. Order Qty =100  ( Unlimited Delivery is not checked and tolerance is Zero).
         Which means only 100 is accepted.
    2. 100 Quantities are produced and confirmed using the BAPI_PROCORDCONF_CREATE_TT (with Final confirmation value as 1 , which mean auto confirmation)
    3. Next when the BAPI confirms & GR's against the same order, the Complete qty is not visible in the COR3 status. And is visible only in the COGI transaction.
    That is expected behavior. and i am ok with that.
    Case 2: (The one with the problem)
    1.  Order Qty =100  ( Unlimited Delivery is not checked and tolerance is Zero).
         Which means only the 100 is accepted.
    2.  25 Quantities are produced and confirmed using BAPI_PROCORDCONF_CREATE_TT (with Final Confirmation value as X , which mean Final confirmation)
    3. The Confirmation and GR go through and the status of the process order now changed is CNF and the Deliverd qty is 25.
    At this point , if you logon to SAP GUI and try to make a process order confirmation you get an error messages which says the Process Order is already confirmed and no more confirmations or GR can be done against this Process order.
    4. But when you Again Run the BAPI_PROCORDCONF_CREATE_TT, it goes ahead and confirms and makes the GR for that Process order.
    The Expected Behavior should have been that this quantity is now in the COGI transaction.
    5. The Process order  allows any number of Further confirmations till the Ordered Qty and Delivered quantity are  same .
    so dear gurus I know i have written a very long doubt but would be very happy to get a response from you. I would ideally not like to enhance or change the BAPI and want to understand if I have missed some setting or parameter that I have to pass in the BAPI for the final confirmation so that once the Status of the Process order is CNF , no more Confirmations are allowed even from the BAPI.
    Thanks in Advance.
    Regards
    Suraj
    Edited by: surajprabhu on Aug 17, 2009 6:37 AM

    Hi,
    The standard SAP will allow the GR even after the Final Confirmation. The Final Confirmation is acting as a agent to change the status of the process order to CNF. thats all.
    If you want to restrict the GR then you have to do Enhancement with  use the USer Exits. Pleas try to use the User Exits PPC00009 or MBCF0001,MBCF0005
    thanks and regards
    murugesan

Maybe you are looking for