MRP Net Requirements calculation in External procurement Vs STO

Hi gurus,
Lets say I have a FG 1234 which has raw component 9999.
Case1:
Setting for 9999 is externally procured.
I have a stock of 50 pc for 9999.
I got order for 60 pc for FG 1234.
so system will only create purchase reks for 10 pc of 9999 as it already sees 50 pc in stock.
Case 2:
Setting for 9999 is externally procured but from one of our own plant (Using SPK 40)
I have a stock of 50 pc for 9999.
I got order for 60 pc for FG 1234.
will system create STR for 10 pc of 9999 as it already sees 50 pc in stock? or will it create STR for 60 pc without checking stock in the ordering plant?

>
dorian661 wrote:
SPK 70 will not create an STR. Stock of 9999 will be checked in supplying plant. In case there is a shortage, a procurement proposal will be created against the dependent requirement here. Stock is not checked in ordering plant. You will notice that dependent requirements for 9999 will be seen in the supplying plant.
Dorian,
Thanks for the reply. so are you saying that in SPK70
In ordering plant - MRP will not look at the stock situation for that material
In supplying plant - system will check stock requirement and create dependent requirement for the shortage amount
and in spk70 case, against what element is the delivery done to the ordering plant? in spk40 delivery is done against STO.
Thx

Similar Messages

  • MRP Net Requirements Calculation

    Hi Guys:
    I defined a Planning Horizon of 40 days, for Example if  today is the start date Since Planning horizon is 40 days (01/30/2012).
    Vendor Lead time = 2months
    Purchase order to vendor with Delivery Date (12/20/2011)  : 5000 Pc
    Purchase order to vendor with Delivery date ( 03/04/2012): 6000Pc
    Onhand Inventory = Zero
    So i have Sales order for 10000 with Delivery Date ( 12/28/12) with in the Planning horizon.So when I run MRP using MD02 ,
    Does the system consider Purchase orders with delivery dates  that are outside planning horizon into the net requirements calculation?
    thanks for the help.
    Kodali

    dear friend,
    as far as i know the available stock is calculated as follows:
    plant stock
    safety stock
    +
    receipts (pur.orders, prod. ordersfirmed proc. proposals)
    requirements quantity (say, PIRs, mat. reservations,...)
    =
    available stock
    shortage occurs if available stock is negative, that is, the requirement quantities are greater than expected receipts and stock quantity.
    so, system specifies the date of the issue (for example, customer requirement, planned independent requirement, reservation, forecast requirement) as the requirements date.
    regards,

  • Net requirement calculation in MRP

    Hi Gurus,
    Is there any way we can exclude Created Purchase order ( Not yet released ) in MRP run for the Net req calcualtion . ( pl suggest other than exit )
    Regards,
    Prasanna

    Hi prasana
    Net requirement calculation in MPR will include firmed receipts. ( P.O.). You can only block what are all given in plant parameter.
    We can exclude in Availability Check, in scope of Availability check setting.
    Regards
    J. Saravan

  • Rescheduling horizon impact on net requirement calculation

    Dear MRP experts ,
    What is the impact of Recrudescing horizon on net requirement calculation .
    Regards
    Sasikanth

    Dear Sashikant,
    The rescheduling check is used to change the dates of already existing firmed receipts not planned on the same day as the requirement to suit the requirement date.
    If you look at MD04, the rescheduling date is based on the Stocks Requirement date. 
    In the net requirements calculation, the system checks whether warehouse stock or firmed receipts are available to cover requirements. If a material shortage exists, the system usually creates a new procurement proposal.
    Within this rescheduling horizon, the net requirements calculation checks whether, after a requirement, a firmed receipt exists, which can be used to cover this requirement. Then the system displays a rescheduling date as well as the exception message Bring process forward for this receipt. The net requirements calculation then uses this receipt and the system will only create another procurement proposal if the receipt quantity is not sufficient to cover the complete requirement. Several firmed receipts can be used to cover one requirement.
    hope it helps. please revert back.
    Regards,
    Alok Tiwari

  • Net requirement calculation

    Dear Gurus
    In Net requirements calculation, Safety Stock, Recipts (Purchase Orders, Production Orders, Firmed Procurement Proposals), Requirement qty(Pir, Customer requirements, Material reservations) are considerd
    In My Situvation, I want to exclude considering Safety stock while doing net requirements calculation
    Kindly tell me the setting i have to do
    regards
    palaniappan

    Dear Planiappan,
      In IMG Production + Material Requirements Planning + Planning + MRP Calculation + Stocks + Define Safety Stock Availability maintain 100% in AvSafetySt field. So in planning your 100 % safety stock will be considered.
    Regards
    Sunil Kumar

  • Net requirement calculation for Sales Order

    Dear Experts,
    I have configured a strategy comprising both( KE,040) and (LSF and 100), say the strategy is Z0.But the system is not doing net requirement calculation for the dependent requirement(always proposing Pr Req though there is stock).Checking group and checking rule, I have created like the standard PP order.Will anybody Pl. guide me regarding this?
    Regards
    Reshmi

    Hi,
    1. The MRP group or the strategy group in the MRP view of the material master record determines what requirements type is used.
    If you have not specified this information, the requirements type will be selected through the item category of the sales order item and the MRP type in the MRP view of the material master record.
    If you have maintained both an MRP group and a strategy group, the system uses the strategy group (precedence to strategy group).
    You can enter the strategy group directly in the MRP view. If you have specified a strategy group, you do not need to enter an MRP group.
    The configured Strategy group need to be copied from a standard Strategy and even if you group many Strategies(Max 7) you ned to check the req Type assigned to it .
    2. The item category is derived from the item category group in the Sales view of the material master record and from the order type of the sales document. Together with the MRP type in the MRP view of the material master record, the item category determines what requirements type is selected. The MRP group in the material master record is irrelevant here.
    The advantage of this method is that the selection of the requirements type depends on the business process (such as quotation, sales order, or repair).
    All the above Points need to checked in your case
    Pavan

  • Exclude Stock Transfer from MRP Net Requirements

    Hi,
    Is it possible to exclude the Stock Transfer Orders from the Net Requirements generated by MRP? I want to base the requirements only from historical consumption. In my Stock/requirements list (MD04) for example, the Requisition generated by MRP increases in quantity since there are open Stock Transfers which are to be served by that plant to other plants.
    Regards,
    Lee

    Nazrin,
    Availability check configuration (OVZ9) has no impact on MRP.  MRP relies on its internal rules when it is performing its net requirements calculation.  You have very little control over which elements are included/excluded.
    You can exclude selected storage locations from MRP planning.  Stock and reservations against these storage locations will therefore also be excluded. 
    You can exclude a material from planning, change the material master MRP type to ND.
    Your best bet, though, would be to set your PM planning process up such that these materials never create the reservation in the first place.
    Regards,
    DB49

  • Parallel MRP run for Internally and Externally procured materials

    Hello all,
    we want to run MRP with different settings for externally procured materials (create purchase Requisition) and internally produced materials. The choices provided my MRP run is either create planed order or Requisitions when run background. Is the activation of user exit M61X0001 the solution to this issue?  I can recall that we had done this is some project in the past, not 100% sure to be sincere. Can anyone help on this?
    Thank you for any help.
    Edited by: Ioannis Salichos on Aug 11, 2010 11:51 PM
    Edited by: Ioannis Salichos on Aug 11, 2010 11:57 PM

    you are right, this is the user exit that can be used to control this.
    see an excellent "how to use"  from R Brahmankar
    in this thread:
    Re: mass MRP run

  • MD02 - Capacity Requirement Plan for External Procurement Material

    Hi, I have the following requirements.
    MRP Scheduling is getting executed material level (material no, plant) with scheduling type 2 which means lead time scheduling using MD02 Transaction Code. This is works fine for the Inhouse Product. In order to achieve lead time the functional team has maintained the necessary routing/workcenter configs.
    The business needs the same functionality "Capacity requirements calculation" for the external procurement material. Business is willing to maintain routing/workcenter config.
    Currently standard program (MD02) is not considering the Capacity planning for the external Procurement material.
    Could you please suggest is it can be controlled through programming.
    Kindly suggest the function modules for Capacity Planning - materialwise, plantwise.
    Please suggest.
    Thanks
    Giri

    Hi Giri
        I think the requirement is not mentioned clearly. Capacity is required only if the material is assembled/produced in house.
    Anyway try this. Set the Procurement type to X in the MRP views in material master. You might have to define your custom material type so that it does not force the procurement type to F. Try the feature called "Quota arrangement". The idea is to define the material in such a way that it can be procured externally or produced in house. With quota arrangement you can say what % has to be bought and what % to be produced in house. If it is produced in house then you can have capacity requirements.
    Regards
    Pragnesh

  • Excluding Stock From Net Requirement Calculation in PPDS

    Dear All,
    We can exclude stock on hand from Net Reuirement Calculation in ECC MRP by selecting Strategy 11 ( Gross requirement Plannung). Is there any Functionality like this in APO PPDS or SNP to exclude the Stock.
    Regards
    Sunil Kumar

    Hi,
              Its possible in SNP, try modifying stock on hand macro in planning book and overwrite initial column value to zero. hope this helps.
    Regds,
    Prasad

  • MRP Net Required/Available  Qty

    Hello Gurus ,
    I am carrying out MRP at plant level .After that MD04 We are analysing the result .We are developing Z report where we need to show Net Required Quanity(-) or Avaialable Quanity .We are using MDKP/MDTB table .
    1.Material Requirement Planning No xxxxxxx is not getting updated in MDTB table .I am getting MRP Table no from MDKP using Plant /Material Combination .
    2.What is the SAP Table -Filed name   to retrive Net Required/Available Quatity  (Planned quantity on the time axis that results from comparing receipts, issues, and current warehouse stock)
    Thanks and regards
    JH

    Hi,
    You can try with below function module, goto SE37 and test it
    MD_STOCK_REQUIREMENTS_LIST_API
    Regards,
    Sankaran

  • MRP net requirement calcualtion for Lot sizes

    Hi all ,
    Can some one help me on this ..
    I want to set up the MRP for the Raw materials Procurement .
    for this i want use MRP type as PD and lot size as WB Weekly lot size .
    but as per the requirement the MRP is run daily , i need clarification on certain things such as how does the system calculates the weekly lot size ?  say if the requirement is converted into PR on the first day of the MRP run ,followed by that if the requirement varies does the system creates a new PR or it changes the Qty in the existing PR if its was not converted to PO .
    what are the stock types considered during PR creation and how are the delivery dates determined during the PR creation ?
    thanks ,
    ksr

    Hi Chris
    You can try to set up a maximum lot size and a takt time on the material master.
    Take a look on the F1 help of this field on the material master:
    Takt time
    If a requirement quantity (for example, for capacity reasons) cannot be procured in a single lot, you have to schedule several receipts. In conjunction with the overlap indicator in the lot size (set in Customizing for the lot size), you can use the takt time to specify that these receipts are offset, that is, that they are delayed by the takt time.
    You enter the takt time in workdays.
    Use
    The system uses the takt time if a requirement is covered by several receipt elements due to restrictions on lot size such as maximum lot size (with all lot-sizing procedures) or rounding value (with fixed lot size with splitting).
    BR
    Caetano

  • Net requirement calculation considering stock ( Strategy 52 )

    Hi All,
    we are using the planning strategy 52 for process industry and according to the standard functionality the stock of finished product will NOT be considered when MRP run and consumption.
    For various reason like customer return we might have the stock of FG. when forecast is finalized and PIR is build in demand management MRP will generate the planned order (type VP) based on the consumption logic. but if stock exist system will not consider it and continue to generate the dependent requirements for the raw material. this is really not acceptable by my client. we want the MRP run considering the stock of FG whensystem generates planned order for PIR.
    Is there any other way to fix this issue?
    we try to use user exit and set consumption indicator 4 for requirement type of VSE.but we failed. the answer is PIR ONLY consumes the requirement elements. Stock somehow a receipt element.
    any pointer is highly appreciateed.
    Reagrds,
    Mao Ye
    Edited by: Mao Ye on Apr 7, 2008 5:38 PM
    Edited by: Mao Ye on Apr 7, 2008 5:41 PM
    Edited by: Mao Ye on Apr 7, 2008 5:43 PM

    Dear,
    Stg 52, will create planned order equivant to the PIR created. and when sales order is created, the planned order is created.
    Hence the wayout is use stg 40. this will suit your requirement, create PIR and run MRP. Planned order is created.
    Do not convert the planned order to production order and give this autjorization to one who can take decision in shopfloor and coordinate.
    You can also use stg 74 ...just see the help link
    http://help.sap.com/saphelp_47x200/helpdata/en/cb/7f9b7043b711d189410000e829fbbd/frameset.htm

  • Regarding mrp pr requirement

    Dear Gurus,
    we are working on MRP
    Through MRP purchase requisitions are raising on date basis.
    i.e.  suppose in aweek  raw material is required  @ 100 KG.
          with referance to BOM  & Qty of header level it raises  5 purchase requisitions.
    I require the system should raise one PR consolidating the qty of 5 PR.
    so that i can assign one PR to the delivery schedule
    is it possible. ?
    confirm the custmising  & process.
    thanks in advance.
    suhas inamdar.

    Suhas,
    What you are describing is 'Periodic Lot Sizing", which means basing the procurement proposals on a time period.
    This is effected by making the appropriate changes in the Material Master of the materials you are planning.  I believe that the Lot Size (MRP1 tab of Matmaster)  you want is the standard SAP lot size WB, 'weekly lot size'.  If you select this SAP standard lot size, no other configuration is needed.
    In this case, when MRP is performing its net requirements calculation, it finds the first instance of a shortage.  It then looks forward in time for all additional uncovered requirements, for one week, and then it proposes a single proposal (purchase req) that will satisfy the entire set of requirements, regardless of parent part.
    Rgds,
    DB49

  • Best Method to calculate Net requirement

    Hi Expers,
    can you suggest the best methods to calculate net requirement for FMCG products in APO Production and distribution planning.
    Best Regards,
    Anandharaj

    Hi Anandharaj,
    There are multiple threads, SAP Notes and documentation in the web about this.
    Please read this note that explains everything about Net Requirements:
    448960
    - Net requirements calculation (documentation)
    You can also check this article:
    Net Requirements Versus Pegging in SAP ERP and SAP APO - SAP Planning
    Hope this helps.
    Kind Regards,
    Mariano