Customer's requirement is to plan cost on cost element level (in CJR2 or CJ40) on overall basis. They donot want to plan it on period basis. They want to check variance for a project overall but on cost element basis.
If I check Total Values in planning profile I donot get Cost elements.
Can somebody suggest please if this is possible without development.
thanks you.
regards
maneesh

Hi,
In your case, you can do either Unit costing/Easy cost planning as both are cost element based.
Unit costing is useful, where in you can enter the qty of materials (internal, external).
Easy cost planning is used for preliminary planning.It is possible only in CJ20N
In both the cases, you should have profiles.
Regards
N.Raju

Similar Messages

  • Report Painter Request - Cost Center and WBS Element

    Hi Everyone,
    Currently, my company settles all project related expenses through to a cost center by way of an internal settlement cost element (category 21).  The issue with this is that when the expense gets to the cost center, they lose all visability as to where the expense originated, such as salaries or travel expense (category 1 cost elements).  We can't switch the settlements to the originating cost element from wbs to cost center just because of the additional data/volume that will cause.  My thought was to create a report painter that can run by cost center but also show the wbs's that settle to that cost center and group the expenses by primary cost element (cat 1).  I'm assuming that there is a way to marry a cost center and wbs element by way of the wbs settlement rule but how would that be done for reporting purposes?  I've seen it done before by way of a nightly job that created sets based on the combination of cost center and wbs but I'm not sure how that was done.  Any advise and examples?
    Example:
    Cost Center:  IT
    WBS: A.0017.01.01 (settles to cost center IT)
    Postings made:
    1.  CC IT and CE 552000 "salaries"..............................$20,000
    2.  WBS A.0017.01.01 and CE 552000 "salaries"........... $5,000
    3.  Settlement of WBS to CC (expenses flow through to CC IT by way of CE 985000)
    I want to run CC IT and see that the account 552000 really shows $25,000 and can be broken down by cost object (CC and WBS by the amounts above)
    Thanks,
    Pete

    Hi Peter,
    I had a similar requirement and used report painter report group 1SHK-002 (in library 1VK).
    I took a copy of the standard and ameneded it slightly, I switched the explode so it occured on the cost center not cost element.
    The report runs so that direct costs on the cost center are shown at primary cost level. And values settled to the cost center are shown on the partner object. In your case i guess WBS Elements (Partner ObjType WBS).
    Now in my case I didnt need cost element breakdown on partner level, just on cost center so effectively I have(sorry for text alignment but I hope you get the idea):
    GL1   .............  100
    GL2   .............  250
    + Cost center1 total ....350
    GL3 .............   50
    GL4 ............. 100
    + Cost center2 total.... 150
    Primary Cost Total ..... 500
    X-YZ-1.200 .............   50
    X-YZ-1.400 ............. 100
    + WBS total ............. 150
    IO 1............. 100
    IO 2  ............. 100
    +IO total  ............. 200
    Partner Total............. 350
    Overall total .............  850.
    Its not exactly like your requirement but it might be a good report for you to work with to get what you need.
    Elaine

  • COPA derivation for thecombination of Cost center and Cost element/GL accou

    Hi Gurus,
    In COPA derivation using KEDR i am trying to make a derivation for the
    combination of Cost center and Cost element. Here i got following problems
    • While posting FI document using t.code FB50 system not automatically
    updating the fields Cost center and cost element in Profitability
    segment. Hence system not posting COPA document. How can i make this
    derivation? Is there any note should i apply regarding these.
    • How can i create cost element as characteristic.
    • If i configure derivation for the combination of Cost center and cost
    element will it be posted with copa document for postings or automatic
    postings from MM,HR and FI
    Pls provide me solution at the earliest.
    Thanks and Best regards,
    Dhanumjaya.Ranga
    Mobile: - 919940093579
    Mail : [email protected]

    Hi Murali
    Thanks for update
    I explain my req clearly
    For me segment is Distribution channel field (EXPORT and DOMESTIC)
    If GL account is 1000-2000     always                      Export
    If GL account is 2001-3000    and Cost center is     X then Export.
    If GL account is 2001-3000    and Cost center is     Y then Domestic.
    Based on above REQ i am making derivation using KEDR T.code.
    These postings should work for all modules postings such as MM, HR also.
    Actually this should work automatically and after saving the transaction we should have copa document also.
    But problem is in source fields of derivation we have GL account (HKONT) and Cost element (KSTAR). I am making derivation using either of these.
    But after posting document system not giving COPA document.
    I found the reason is  at GL postings we are giving input to GL account (HKONT) but we took in KEDR source field as GL account (SAKNR). GL account (HKONT) is not updating GL account (SAKNR) field in PSEG screen in Fb50. Even i try with cost element (KSTAR), GL account (HKONT) is not updating this in PSEG screen in fb50.
    If GL account (HKONT) updates either GL account (SAKNR) or cost element (KSTAR) at the time of posting FB50
    Or
    If we have the field GL account (HKONT) as source field in KEDR i hope my problem
    Get solved.
    If you want further info pls give me your mobile number then i ll call you

  • Cost centre and cost element related tables

    Hi,
    Could any help me in knowing whre the cost centre goup and cost element groups are maintained.
    Could you help in proving the link tables between Cost centre, Cost centre Group, Cost element and Cost element group.
    Regards,
    Krishna

    Hi,
    Please refer to Table SETLEAF for cost element group and cost center group. This table is based on set class and 0101 is for Cost Center Group and 0102 is for Cost Element Group.
    Cost Center Master data table is CSKS and Cost element Master data table is CSKB. To the bse of my knowledge you cannot directly join these two tables with SETLEAF table as key figure fields are not common. In case you are getting any ABAP report developed, you can ask the developer to write a code saying Controlling Area is equal to Organizational Unit as Set Subclass.
    Hope this helps.
    Regards,
    Harish

  • Function Module to find Planned Costs and Actual Costs against WBS element

    Dear All,
    We have a requirement where we need to find out the Planned Costs and Actual Costs booked against a WBS element, in a year. The costs can be against all the plan versions or on individual plan version.
    Are there any function modules to retrieve this value?
    Thanks for the help.
    Warm Regards,
    Judith

    Hi,
    The easiest way would be to get the OBJNR for all WBS elements from PRPS and look up RPSCO and summarize for Value type (RPSCO-WRTTP) 1 for planned cost and 4 for Actual cost.
    Please let me know if this helps.
    jibat

  • How to assign cost center to cost element.

    Hello,
    Can any one please guide how to assign cost center to cost element.
    Thanks in Advance..
    Have a nice day...

    Hi ,
    There are 3 ways :
    1. Default the cost center in cost element - Ka02 - account assingment tab enter cost center .
    2. Use OKB9 for diffrent combinations as per your requirement .
    3. Use GGB1 for substituting the cost center based on some conditions .
    Regards ,
    Dewang T.

  • Reports to see cost in statistical WBS elements

    Hi,
    Is there any standard SAP report available to see cost in statistical WBS element?
    Aman

    Closing the thread. Got answer.

  • Cost center and Cost element.

    Hi all,
    I am in an urgent need to understand the relation between cost center and cost element. Please provide me with their individual information as well as the link they share. An existing relationship table between the two, if any, ...then plz mention.
    Thanks & Regards,
    Naresh

    Cost Element: cost element is an individual which carry cost like salaries, wages, power expenses, etc.. These Cost Elements are Two types
    1. Primary Cost Element
    2. Secondary Cost Elements
    Primary Cost Element will carry cost form FI to CO (Cost Centers, Internal Orders, Cost Objects, etc…)
    Seconday Cost Elements carry cost with in CO to different Cost Centers, Internal Orders, Cost Objects, etc…
    Cost Center: Cost Center is an individual which contain collection of costs. For example “Admin is a cost center, it contain costs like Salaries, Power, Rent, Stationary etc,
    With this following report you can retrieve  cost elements given a cost center “controlling – cost center accounting – information systems – reports for cost center accounting – plan/actual comparisons  ”
    Thank you

  • Cost center and cost element in different collumns

    Dear all,
    I developed a report painter where the lead collumn has cost element and cost center. When I run the report it shows at the same collumn the cost centers and in a different line the cost element totalizing the amount of each cost center. So the report shows for each cost element the cost centers posted with this cost element. The report show like below:
    |-------
    Cost center A    | 100
    Coste center B  | 200
    |-------
    Cost element xxx - 300
    The problem is: How can I make the Cost element in a separate column ? Ex:
    Cost element xxx  |  Cost center A  | 100
    Cost element xxx  |  Cost center B  | 200
    Cost element xxx - 300 (In fact I don''t need the total)
    I need cost element and cost centers in different collumns to allow export it for other application..
    Regards

    Hi
    In report painter report we have only one lead column so we cannot have cost centers and cost elements in two different columns.Instead we can use the functionality of variation.Give the cost center in general data selection screen and select the variation functionality.So that cost centers are displayed on the left side of the report as hirearchy and only cost elements are only displayed in lead column.
    Thanks
    Sandesh

  • Cost center and cost element display through report painter/writer

    Hi
    Can any one suggest me how to display both cost center and cost element in the output of a report painter.
    Presently --- I am able to display cost center and its cost elements in the same leading coloumn and its periodical values for 16 consecutive col.s.
    Help Needed --- Suggest how to display cost center and cost element in the output of the report along the periodic values.
    Thanks
    Tangudu

    Can any one share some advice on this above query.
    Thanks
    Tangudu

  • Cost Center Assessment - cost element type 42

    Hi dear All,
    I got issues running KSU5 to allocate planned costs under cost element type 42. we were expecting that all planned costs (primary and secondary(cost element type 42)) could be allocated by credit cost center (actual). only primary costs are being allocated.
    Scenario:
    cost center planning (kp06) 1000 currencies in primary cost element in cost center A
    running planning assessment - KSUB: cycle uses assessment cost element (type 42): sender cost center A, receiver cost center B (all planned values). assessment cyles posts 1000 currencies from CC A to cost center B
    planning in cost center B (primary cost elements through kp06, 500 currencies) total planning 1000 from previous assessment  with CE type 42, and 500 from cc planning in a primari CE.
    by the period end closing, tcode KSU5 (allocation actual) is running. new cycle created, based on planned values (origini not actual, but planned amounts).
    we were expecting to allocate 1500 currencies from cost center B to cost center C (using 100% and through assessment cost element)).
    result: credit actual cost center B = 500 currencies debit actual cost center C = 500 currencies.
    1000 currencies pending on cost center B (planned).
    do you know why SAP is not allocating the 1000? even if those 1000 were planned in cost center B by assessement, a new allocation cycle should be able to post them or not?
    thank you for your outcome.

    Hi dear Ajay, thank you for your answer.
    first, I understand the difference between KSUB and KSU5, in the defined scenario, we have both. planned values, become actual with the MEC activities. business definition.
    regarding the cycle, I have setup assessment cost element so we can get all planned lines posted as 1.
    On sender tab I have only the cost center. no cost element defined.
    receiver its cost center.
    furthermore, i've not setup allocation structure, so all cost elements should be allow, there is no restriction on this.
    the only difference is: planned costs which their origin is already an assessment are not being assessed again.
    I can show you the print screens with cycles setup if it helps
    best regards
    MF

  • Cost Center Budget-Cost element wise

    Dear SAP Gurus,
    My client needs to create cost center budgets cost element wise. For e.g. Salary paid (code 430000) in Development Cost center (code 9901).
    We now use KPZ2 to create cost center budgets and KP06 for cost element planning. Kindly guide.
    Regards,
    Siva

    Hi Ramesh,
    Thank you for the reply. I did suggest them to use KP06 but they require some sort of validation when posting an expense (cost element) to and cost center.
    For e.g. If the travel budget for Marketing cost center is $1000, they need the system to prevent posting once that amount is exceeded.
    Any help in this regard would be appreciated.
    Regards,
    Siva

  • Cost Center and Cost Element Hierarchy and Actual Cost Center

    In Bex - Right now I am displaying Cost Center and Cost Element hierarchy with 12 months of data. I want to display the actual Cost center number next to cost element hierarchy - Can I display in Bex?
    Tried to with Structure creating formula variable for Cost Center using replacement path - didn't work. Can you please suggest me how i can achieve this?
    The format should be
    CostCenter H1   CostElement H1   CostCenter   Jan  Feb ...
    Thanks in advance and appreciate for any help...

    Let me explain it clearly and hope it is clear now...
    Designed the report as like this - Cost Center Hierarchy by Cost Element Hierarchy for 12 months of data. But Business agian search in R/3 for actual cost center numbers based on above two hierarchy nodes.
    I am trying to achieve this Bex instead of going back to R/3 - so that they can understand how the dollar amount is summed up on which major cost centers.
    If I remove the hierarchy on Cost Center - it will display all the cost centers. They want to see the Cost center numbers based on CC and CE hierarchy node so that you are displaying only those cost centers. That's the reason I am trying to design the  report with CC Hier, CE hier, Cost Center number and 12 months of data.
    In my data model - have only one Cost Center, if i can create another ZCOSTCENTER same as 0COSTCENTER - May be I can achieve this. still looking for options with out changing the design.

  • Cost center Vs cost elements

    can any body give examples for Cost center groups, cost centers and cost elements..
    Assigned poits..

    hi
    Cost Center Group
    Definition
    You can collect cost centers according to various criteria into groups. This enables you to use cost centers to depict the structure of the organization in the SAP System.
    Use
    You can use the groups to build cost center hierarchies, which summarize the decision-making, responsibility, and control areas according to the particular requirements of the organization. The individual cost centers form the lowest hierarchical level.
    There must be at least one group that contains all cost centers and represents the entire business organization. This cost center group is described as the standard hierarchy. You can assign more cost center groups to the standard hierarchy.
    You can also create any number of alternative groups. You can structure these, for example, according to organizational and/or functional viewpoints. Cost center groups enable you to perform evaluations for each decision-making, responsibility, or control area. They also support the processes during planning and internal allocations.
    You can assign each cost center to only one group in the standard hierarchy, but to as many alternative groups as you require.
    cost element  
    Classification of the organization's valuated consumption of production factors within a controlling area.
    Each cost element corresponds to a cost-relevant item in the chart of accounts.
    Cost centre:
    You receive an overview of the actual and plan values, or the actual and target values with the corresponding absolute and percentage variances. The reports also display the fixed and variable portions of the actual, target, and plan costs as well as the actual and planned.
    The Cost centers: Actual/Target/Variance report is structured by cost centers. The posted cost elements are listed for the selected cost center group or cost center.
    The Area: Cost Elements report is structured by cost elements. For each cost element selected, the system displays the corresponding cost centers.
    nagesh

  • Repot cost center groups,cost element groups and quantities

    Hi
    Is there any report displays only costcenter groups, costelement groups and quantities. No line items are required this is for management purpose.
    thanks in advance
    prasad

    Hi Sunitha,
    Thanks for your immd. reply
    But my requirement is not that
    I need cost center groups, cost element groups and quantities in the same report
    regards
    hariprasad reddy
    accenture - 9963411136