Problem during Process Order Confirmation - COR6N

Dear All,
We are into process industries
Till now we are creating different BOM for each section and different process orders for each BOM.
For example Pulverize, Acid MIXING, Continuous Rotery, Blending and Packng.
Now we have created new BOM for FG - showing all input/output of  RM, SFGs.  In Recipe, define operation for each section. and assign operation to material.  I have attached screenshot of Recipe Operation.
During process order confirmation, system shows movement type of all material perfectly during each phase. But during confirmation of last phase system does not show 101 movemet of FGs.
I have checked in Recipe, control key is ok i.e. Automatic GR,  in OPK4 setup is also correct.
We have created new BOM and Recipe. There is no change in other configuration parameter.
Thanks and Regards,
Nirav

Hi Nirav
The automatic goods receipt is defined by the operation/phase control key.
Control key PI03 has the automatic goods receipt setting by defaul.
Analyzing the screenshot I could observe that this control key is assigned to all the opration/phases, however, it should only be assigned to the last operation/phase, where the goods receipt will actually take place.
For all the previous operations/phases you should use a different control key, without automatic goods receipt, such as PI01.
BR
Caetano

Similar Messages

  • Restriction during process order confirmation

    Hi,
    I want one validation during process order confirmation (mile stone) through t code COR6N  if resource capacity & shift intervals not maintained ( t code CRC2) then process order should not confirmed &  there should be error message. Plz advice how it is possible through customization.
    regards,
    sps.

    Dear shukla,
    Check with this User Exit,
    CONFPI02                                Process order confirmation: Customer spec. input checks 1
    CONFPI03                                Process order conf.: Cust. spec. check after op. selection
    CONFPI04                                Process order conf.: Customer specific input checks 2
    CONFPI05                                Process order conf.: Cust. spec. enhancements when saving
    If the above is not working then check with this BADI
    WORKORDER_CONFIRM at the time of saving,
    Regards
    S Mangalraj

  • Problem in Process order confirmation ( while doing batch splitting)

    Hi All
    In our Industry we have sceneraio
    we create Internal order and assign internal order to sales order
    Once MRP run take place
    Planned order created and converted to process order
    Process order released
    once we try to do confirmation of process order
    example suppose process order header matl qty : 8
    and in final confirmation while Goods receipt(101) of Fert
    we do batch splitting (example 4 batch : each qty : 2)
    but some time system not allows to do Goods receipt (movement type101)
    system gives "Error confirm order not allowed"
    please need urgent help
    Thanks in advance
    Sunil Singh

    Hi Sunil,
    During your first confirmation you must have activated "Final confirmation" Indicator, probably this is blocking from further confirmation.
    Please check whether current system status of the order contains "CNF" if so, please cancel the previous confirmation and then redo confirmation with "partial" button active. Final confirmation should be activated only when it is the last confirmation for the order.
    Hope this will resolve the problem, reward your points....
    Regards,
    Prasobh

  • Process Order Confirmation COR6N - By using Shift Management Functionality

    Hi,
    I want to confirm Operations/Phases by using T.Code COR6N.
    Here i want to identify which Shift i have done confirmation by using shift management functionality.
    It can be done for CORK. While doing Cofirmation for Order by using CORK, we can use this functionality.
    The same i want to use for COR6N.
    I have done as per following link
    https://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/c0fa9a04-376a-2c10-c396-86d32ac80614
    Is there any option to use this functionality for COR6N ?
    Pl suggest
    Regards
    Nag
    Edited by: nag1975 on Mar 29, 2010 3:06 PM

    Hi Srinath,
    Go to T-code CO86 directly or go to SPRO> Production planning for process industries>process order--> operation>>confirmation and then hide the field for scrap by clicking the radio button. I think this should serve your purpose.
    Please let me know if you have any issues.
    Regards,
    Abhijeet

  • Problem during Process Order creation

    Hi,
    I have problem while creating Process Order.
    I have maintained all the basic data required to create the process order.
    When I Release the order, I am able to create the control recipe also, but PI sheet is not generated along with it. System gives the message "No PI maintained in customising for CRD for which control recipe is to be generated "
    If I maintain the same, then system is unable to create the control recipe.
    What may be the problem here? What i can do to rectify this situation?
    Pavan

    Hi Pavan,
    1. Maintain PI in SPRO of process management
    2. Assign this PI to one of phse in master recipe
    3. Plz check wheather ur created Control receipe destination or not.
    4. if not then maitain the same in Spro.
    5.Check the ordre type dependent parameter i.e COR4 from SPRO
    see the Control recipe gerated in REL phse else maintai the asme in production scheduling profile.
    if possible plz send the sctren shot fir the same to
    [email protected]
    Regards
    Siddhesh

  • Loss % in process order confirmation

    Dear all,
    During process order confirmation,loss should not to take above 10%.
    It should be within 10%.
    Kindly let me know hat customization to be done for this scenario
    Regards
    Rajasekaran

    Hi,
    In the confirmation parameters in OPK4 in the checks option in the under delivery maintain error when quantity falls below under delivery tolerance and in the material master in work scheduling view in tolerance data maintain under Underdely tol as percentage and check...
    Thanks
    Kumar

  • Goods Issue- Process Order Confirmation

    Hi,
    During Process order confirmation, in Goods Movement tab the BOM components with qty are displayed. But some components OTHER than BOM items ISSUED for the process order is not displayed in the goods movement tab. Why?
    Is there any additional configuation to be done?
    Thanks....
    JK
    Edited by: J K on Apr 15, 2008 6:04 AM

    Hi
    As said by Mr sateesh,
    If u r doing confirmation phase/operation wise(COR6), then the material assign to phase/operation is only seen according to phase/operation wise.so have to check in which phase u have confirm the component quanity.
                    or
    If u confirm the process order collectively(CORK), then their must missing in OPK4 (confirmation Parameter) of All component tick at Goods Movement.
    Kindly check the same & coem back if their is any other issue
    Parminder

  • No 101 for Co-products in Process order confirmation

    Hi All
    I have a problem in Process Order Confirmation.
    I have a order with Co-products.  When I do confirmation, 101 Mvt type is not happeneing for all the co-products along with the main product.
    The configs looks fine
    1.  Control key has "Automatic GR"
    2.  Confirmation parameters have "GR Co-products"
    What else could be the problem?

    Hi Jack,
    I'm not sure how it works with process orders but in case of production orders is it not possible to do auto GR for co-products - according to my best knowledge.
    Please check:
    http://help.sap.com/saphelp_erp2004/helpdata/en/b1/c04d01439a11d189410000e829fbbd/content.htm
    You can use MB31 + PrdOrd reference to book the co-products by mvt 101.
    (You can also search in this forum to find threads in connection with this.)
    BR
    Csaba

  • Process order confirmation without 101mvt type

    our client is  a process industry.client need during process order confirmation Background 101 not happen.
    Step : 1 Process order create
    Step : 2 Goods issue The material -261
    Step:  3 Process order confirmation   (No 101)
    Step:  4 Goods Receive (MIGO) 101 happen 
    Following Steps Process only,
    cork-only activity confirmation only,after Activity  confirm GR will Happen , how to configure in the system,any user exit or sap note there in the sense tell me?
    Thanks For Advance

    Hi Thiyaharaajan,
    For Goods issue i believe you are using MB1A/MIGO. You also use backflush to automatically issue the material during confirmation.. For this maintain Backflush - 1 in material master MRP 2 view.
    Also during confirmation for doing Auto GR (101 movement type) you need to assign the control key ticked with Auto Goods Receipt for Last operation/phase of Master Recipe.
    Thanks & Regards,
    Ramagiri

  • ABAP Programming Error when saving the Process Order confirmation in COR6N

    Hello,
    We have an issue related to Process Order confirmation using Tcode COR6N. When we enter all the inputs to confirm( Activity, yield and phase) and click on save it gives ABAP Programming Error (Exception condition "SEQ_NOT_FOUND" raised).
    Any inputs in this regard, would be appreciated.

    Hello
    I can observe that you have implemented the report ZOPSECRE and that an inconsistency was found.
    This repor corrects inconsistent orders which do not have an operation or a sequence, or the two of them.
    The report checks whether there is at least one operation or one sequence and creates both including status objects.
    Therefore, you need to have the default valus for the operation generation defined on OPJG for this order type/plant.
    BR
    Caetano

  • Problem with creating Process order confirmation using BAPI

    Hello,
    While creating Process Order confirmation using BAPI_PROCORDCONF_CREATE_TT, material document is getting created. But a line item is inserted in the table AFRU without material document number. When it is created manually using the transaction COR6, the table is getting updated with material doc in the line item. Can anyone let me know what other attributes to be passed in order the update the same?
    Thanks in Advance.
    Regards, Senthil G.

    Hello , I am working with the same Bapi, can you please send me the code to fill the parameters, if I find the same error like you, I will send you the solution if I correct that.
    Thanks for your help.
    [email protected]
    Guatemala, Cempro ADATSA

  • PROCESS ORDER CONFIRM DURING UD

    Hello Experts:
    Here's my question concerning a customization in QM issuing UD.
    Std. results recording has been completed and valuated:
    UD is customized to require user to confirm all operations including QM operations have been Process Order Confirmed. This is o4  inprocess manufacturing.
    When attempting to enter UD, error pops up indicating QM Operation XXXX  has not been confirmed, do so to complete UD.
    Please explain the steps to execute P.Order confirmation via the COR transactions.
    Appreciate.
    Verroz

    Go to CO11N
    Enter process order and Operation xxxx in respected field and save the transaction. Do for all unconfirmed operation or for which you getting error message.
    You will be able to UD.

  • Create process order confirmation

    Hello,
    I use the Bapi 'BAPI_PROCORDCONF_CREATE_TT' to create a confirmation in our Z program to replace 'COR6N'.
    The only problem I meet is that it makes a material document for the good movements but don't write it in the table AFRU (field WABLNR).
    Do I miss something in the BAPI??
    I run the BAPI like that:
      CALL FUNCTION 'BAPI_PROCORDCONF_CREATE_TT'
        IMPORTING
          return                   = lwa_return
        TABLES
          timetickets              = gt_timetickets
          goodsmovements           = gt_goodsmovements
          detail_return            = lt_detail_return
    The tables gt_timetickets & gt_goodsmovements are filled with relevant values.
    Could anyone help me to know what make the doc no. to be written in AFRU?!!!
    Thanks in advance,
    Fariba

    Hi Fariba,
    I am facing the same kind of issue that you faced long back. If you have resolved this issue, can you help me by replying back to the thread Problem with creating Process order confirmation using BAPI
    Thanks in Advance.
    Regards, Senthil G.

  • Change Work Center during production order confirmation

    Dear All,
    I must to modeling this situation:
    I created an production order. In routing I used an work center A.
    After I confirmed a half of quantity, the work center A was damaged and I must to change it, with the work center B.
    The system allow this change, but when I checked the costing, the situation isn't real. The system counted the costs just for the work center A, and no for work center B.
    My question is: it's possible to change the work center, during production order confirmation and the costs updated with new cost?
    Thank you for your answer!
    Regards,
    Marian

    once a Order is released, the Process order detaisl for that order is frozen.
    however if you want to do it, change the order status to CRTD after reversing the Movements done.
    Do READ MAster data , this will copy the new Work center , redo the previously done Moevements.
    if the change is long term.
    or
    Just manually add the new work center and do the processing. if the change is temporary.

  • BAPI For Process Order Confirmation

    Hi,
    For Process Order Confirmation we are using the following tcode. COR6N. in the t-code we are include a new field (Shift Field) with help of CONFPP07. and we made the field as mandatory also. in cor6n it is working fine.
    now we are using the bapi for same Process Order Confirmation. here the new field is not available. we want to include the new  ( Shift ) Field also. we are using the following
    BAPI Fm: BAPI_PROCORDCONF_CREATE_TT .
    Regards
    Sathis

    BAPI_PRODORDCONF_CREATE_TT to confirm a production Order