Promotion planning and lowest level KF

Hai,
        The promotion key figure has to be the lowest level of detail, which means the KF has to be the lowest in the hierarchy. This means, I can only assign promotions at the lowest level?
For example, a product called DOW white color soaps and a group level called DOW soaps. So as per the promotion planning, I can only set promotions at the DOW white color soaps and not at the group level of DOW soaps? is that true? What if I have a case that I have to specify a promotion at group.
Thank you.

Hi Vishu ,
Firstly let me clear you that Promotion Key figure is the key figure in which the data for the promotion is to be stored and the Promotion level is the characteristic at which level the promotion is maintained ,this may be the Locaion or the Product .Yes you need to assign promotion to the lowest level but this does not mean that you can not add promotions at higher level like product grp or Brand .
In promotion base you can define Characteristics (Grp/Brand etc) on which you want to plan promotion.
For more clarification go thro.
<a href="http://help.sap.com/saphelp_scm40/helpdata/en/0d/429ba838ee11d3982b0000e8a49608/frameset.htm">Creating a Promotion</a>[url
Regds //Digs...

Similar Messages

  • Why do we need to plan promotions at the lowest level of aggregation

    Hi,
         The documentation says that we need to plan the promotions at the lowest level of aggregation i.e., the material level. Why? Is there a specific reason for this? Can we plan at other levels of aggregation as well? What happens if we plan at higher level;s of aggregation?
    Thanks.

    I think it is possible to do it in an aggregated level however you need to define your distribution rules in order to get the desired result, you need also to consider that if distribution rules changes and the value after promotional planning returns the same value, it is possible that detailed level are not realigned to the new distribution rule (e.g. regarding another ratio).
    Maybe this is one of several causes.
    Regards,
    Carlos

  • How to confine various level of planning in to limited and lowest level of planning in DP by the users

    Hi Gurus,
    May I know the various methods to confine planning level at the lowest level and re-define the Primitive methods where  business currently uses in excel sheet and plans at all level into demand planning with a minimum and lowest level by which the business reduces manual work and increases visibility and planning.
    Example: Business currently plans at customer Hierarchies  which has about 6 levels, product has Hierarchies at 5 levels, location hierarchies at 3 level in excel sheet and on monthly level for an year and then quarterly for 2 years and yearly basis  for one year. This we need to confine to lowest level of customer, product and location.
    HEIRARCHY LEVEL
    PRODUCT
    CUSTOMER
    LOCATION
    LEVEL
    P0
    C0
    L0
    HIGHEST
    1
    P1
    C1
    L1
    2
    P2
    C2
    L2
    3
    P3
    C3
    L3
    4
    P4
    C4
    SOLD-TO
    5
    P5
    C5
    6
    P6
    CUSTOMER
    LOWEST
    SKU
    PLANNING LEVEL
    PRODUCT
    CUSTOMER
    LOCATION(DISTRIBUTION CHANNEL)
    HEIRARCHY LEVEL
    P6
    C5
    L3
    LOWEST LEVEL
    WHERE
    P6
    SKU
    C5
    CUSTOMER
    L3
    SOLD-TO- PARTY
    CVC
    P6_C5_L3
    So in this case, the cvc are created at lowest level of planning, at P6_C5_L3.
    Now how to convenience the business that they need to do the planning at this level for planning, as the rest levels will be aggregated automatically in demand planning.
    Is the grouping level place a major role? if so how to do that as the business says for some products they do at p4_c2_L1 level for some they do at P5_C4_L2 level.
    Could someone guide us in giving some solution which ease the business need of planning at any level. Hope you have understood my requirement by the above example. If not do let me know, so that I may try to inform by further details. Thanks in advance.
    Praveen

    Praveen,
    Not really sure what the question is.  You say you want to 'confine' planning to the most detailed level, but you also want to support planning at an intermediate level.
    No matter.  DP transparently supports planning at any/all levels simultaneously.  Data in DP is always stored at the detail level, no matter which level (or combination of levels) the forecast is entered at.
    Creation of the Demand Forecast - SAP Library
    Best Regards,
    DB49

  • Transferring Open Items, Instalment Plans and Dunning Level

    Hi all,
    We are implementing SAP IS-U for a water suplly company and we have a process in which an Installation is transferred from a Business Partner to another. For this we are using the Move-in / Move-Out functionality (trx EC60).
    So far, so good. The problem is that we also should transfer also the Open Items, Instalment Plans and Dunning level to the new Business Partner and new Contract Account.
    The questions is: can we transfer these automatically?
    We thought in different scenarios in case this is not possible, so I would appreciate if you can give us an opinion:
    1 - Use FP40 transaction and transfer FICA elements manually
    2  - Create a FOP process to perform step by step the process from CIC0. The only problem I have found is that there is not any object that allows me to transfer the open items. Does it exist? If not, this option is not valid
    3 - Use the "Change CUstomer" Functionality. Did you have any experience using this funcionalidty? The main issue I have with this is that the system generates a dummy invoice, the Move in Date is in the future, and the Account must be closed.
    Please any information will be very helpful. Thank you very much in advance!
    Best Regards,
    Lucas

    Hi Lucas,
    You can transfer the open items and the dunning level manually to the new BP and CA through transaction code FP40.
    You need to maintain the following configuration settings in the posting area 1055-
    Curr-Currency of the Cocd
    Clearing Reason-Clearing reason used for transfer
    Document Type-Document Type used for Transfer
    Only all items- blank
    Credit-X
    Transfer DL-X
    Moreover, you cannot transfer Instalment Plans through FP40, as instalment plan items are statistical in nature.
    Hope it clarifies.....
    Thanks,
    Amlan

  • Promotion planning and SD, CO-PA

    Can anybody send me info about promotion planing and its relation with CO-PA? I also want to get further information about "promotion planing and its customizations on SD.
    Thanks in advance.

    Hi,
    Are you refering to promotion planning in APO? Promotion planning is usually done by APO but the orders are generated by SD component. For example in promotion planning you plan in advance regarding the free offers to be made to customers. But the real promotional orders are generated by SD. As per CO-PA free of charge orders or samples will not flow into CO-PA at the time of billing but you will have to transfer it through settlement.
    Regards,
    Abhisek.

  • DP Local Key Figure Discrepancy between Aggregated level and lowest level

    Dear,
    Here is my issue.
    Forecast (key figure)
    Life Cycle Factor (key figure)
    Final Forecast (Local Key figure)
    Final forecast = Forecast * (1- LCF (%) )
    Example :
    Product 1 = 100
    Product 2 = 200
    Product 3 = 300
    TOTAL FORECAST = 600
    If I assign a life cyle factor to Product 1 = 60
    Total LCF appears  = 20 (60 + 0 + 0) => OK
    Final Forecast Product 1 = 40        => OK
    Final Forecast Product 2 = 200      => OK
    Final Forecast Product 3 = 300      => OK  
    Total Final Forecast =  480  (600 * (1-20%)        => NOK 
    I have a very strange situation because  at the product level, the formula is OK   => Final Forecast = Forecast * (1 - LCF(%) )
    BUT Total Final Forecast should be the sum of the each product Final forecast = 40 + 200 +300 = 540.
    Can you help me to understand what I have to correct for  this aggregation ?
    Thanks a lot for your help
    PE

    Hi Arnaud,
    My macro is running "interactively" because it is placed into the Default basket of my planning book.
    (macro executed  for each save / change)
    I agree, calculation is done at each level.
    Here is the parameters of the macro... should I change something ?
    Thanks for your help
    Pierre

  • Store rep signed me up under the wrong plan and no one in customer service has fixed it in over a month

    I was bait and switched. I signed up under the pretense that I was getting the promotional rate of 40gb/$150 that was scheduled to end on November 5 2014.
    I walked  into a Verizon wireless store on November 4th with the intent to trade in my iPhone 5s which I was offered $350 trade in value and port over 2 of my lines with T-Mobile under the Verizon promotion. Once I was approved and offered my trade in I was told that the phones I was seeking to purchase from Verizon was not in stock and needed to be ordered, and delivered separately with the iPhone 6 being shipped out November 14 and the iPhone 6+ shipped November 21. Thomas, the Verizon wireless sales representative, also informed me that for me to get the promotional rate I would have to open the account with an active line before the 5th or I wouldn't be able to get the promotional rate since the phones would be delivered past the promotional date period. The sales representative insisted I should add an iPad that  was in stock at the store and I could leave the store with an active account and once my phones were delivered I would be all set to go with my promotional plan and devices. I had no need for an iPad but decided it was worth getting for the sake of the promotion.
    ON November 14 I recieved via FedEx a package containing not a iPhone 6 as promised, but a iPhone 6+. I called Verizon to activate the phone that was ported to my personal phone number, and didn't have my iPhone 6 that was set to port my out of state business line and cancel service with T-Mobile on the 14th of November. To say the least I was extremely upset for which I had no means of recieving business calls from North Carolina while I live in Florida. At that point I asked the Verizon customer care representative I had on the phone to see if they could see if there was a store that had the iphone 6 I ordered in stock so that I an could have a business phone the same day. He found a store that had it in stock and it happened to be the store I originally signed up at. I was told that it was in the color and storage capacity I had originally ordered and that I could pick it up at the store to complete my purchase with Verizon. Again, for the sake of having a business line I ran to the store and spoke with Thomas and explained the mix up. upon moving forward I was informed that they had an iPhone 6 in stock with the capacity I had requested but not the same color I had ordered. At that point I didn't care I just needed a phone and proceeded to activate the phone he had in stock And ported over my business line.
    After recieving a text from Verizon that I had consumed all of my data just days after I recieved my phones I called Verizon 611 from my phone and spoke to a customer care representative named Fallon, which informed me I was set up on the wrong plan and that she see's the notes that Thomas notated that I was subscribing for a 40gb plan and that she was going to send a  request I D # [removed] form to make the corrections and that there was no need for me to cancel service as I was within my cancelation period, again she insisted that there was no need to cancel and that the request would be granted and she would be calling me once my billing cycle reset and the corrections were made and she would credit my account based on the promotional rate. I NEVER RECIEVED A CALL FROM FALLON! Not even to be notified that the request was denied! I came to realize later in December when I recieved a $1200 bill that this wasn't resolved. I called customer service again and spoke with a gentleman that explained the request was denied and that this will be resolved after I explained what transpired. He assured me that he was going to expedite another request and he would be in contact with me within a few hours....... I'm still waiting for his call as well!
    I called again several times in the past few days and have spoken to several supervisors that promised to resolve this matter and call me back promptly........ Again, no one has called me back!
    December the 8th I spoke with a supervisor named Victoria which assured me she would get this resolved within the next 24 hours and gave me her direct number to reach her if I didn't hear from her [removed], again I haven't heard from her yet and I've made several attempts to reach her at her direct line to no avail.
    December the 9th I spoke with supervisor named Mike employee #[removed] in the Seattle call center, he appoligized for the mix up and that no one has called me back and that he would handle this matter and get back to me today December 10th....... Again no call..... I have spoken to 3 people today all which have made promises to call me back today within a few hours and none that have. I just got off the phone with a supervisor named Vanessa Jentfield at the Chicago call center and saw all the notations and assured me that there is no reason why this shouldn't be corrected and that she would be calling me back tonight or tomorrow. I will be sitting by the phone unless Verizon wireless decides to disconnect my service for non payment of $1200+.........
    I have filed a complaint giving a detailed explanation of what has transpired with the FCC as well as the FTC, my next step is to file a small claims lawsuit tomorrow morning with the state of Florida and see if Verizon finds a way to contact me then,I guess I will just have to wait and see.
    Personal information removed as required by the Verizon Wireless Terms of Service
    Message was edited by: Admin Moderator

    It was a good idea to file a complaint with the FCC, someone from Verizon will contact you by phone in an effort to  resolve your issue. I wouldn't suggest small claims court as they have not done anything illegal, (just bad customer service) and their contract with you is usually upheld, which in this case is not for the plan you want. The person contacting you likely has a little more pull, as the call centers can only uphold the written customer agreement made.

  • Called to Cancel, was talked into a discount plan and now I'm being told the discount isn't applicable to the plan I just signed up for??

    On August 22nd I called to cancel my service being that my contract was over. My logic was simple. I really didn't use the phone enough to justify a $87/month payment.  The young lady on the phone was very nice and presented to me the $60 plan that is unlimited talk and text with standard data package. After I told her where I work now since my old employee discount had expired she pulled up the data and said "good news, your new company also has a 22% discount with Verizon".  After we did the math together she said that with the discount I'd be saving over $30 a month doing this plan with the employee discount.
    Everything has been great so far. I went out and upgraded my phone to a new Iphone 5C, paid the upgrade fee of $30 and the tax on the free phone. Now this month I go to pay my bill at its at $63.  I call and the rep tells me I was misinformed and that the $60 plan is a promotional plan and the employee discounts do not apply.
    I'm stuck now since its been over 30 days since I signed up for the plan.  The rep on the phone I spoke to today is very pleasant (his name was Kelley)  and has tried all options to help but no option helps me pay an extra 22% out of pocket for the next 2 years!
    I'm demanding that the 22% be honored in monthly or lump sum discounts. OR let me walk away like I wanted to do before without a any cancelation fees!  I've been with Verizon 9 years now and have always been loyal. Not sure this event will keep me around a minute longer than I have to be!
    Please help! Review the phone call from August 22nd and stand behind what your employee told the customer.....

        We certainly don't want you to leave, O. I apologize that you were given inaccurate information. Unfortunately, we are unable to honor the 22% requested because the plan selected is a promotional plan. I apologize for the inconvenience.
    ChaunceyM_VZW
    Follow us on twitter @VZWSupport

  • APO Demand Planning - promotion planning

    I am using APO V5.
    I am interested in promotion planning, and have these two questions:
    1. Is it possible to create 'template promotions', which specify parameters such as number of periods, and use such 'template promotions' when creating an actual promotion?
    2. When I see promotion quantities in cells of an interactive DP planning book view, how can I see reference to the promotion to which the quantities refer?
    Thanks, Bob Austin

    Hi group APO,
    Answer to Q1: I think the standard SAP promotion components doesn't the "template" functionality that you are looking for. However, you can create a custom program to do this. 
    I am thinking of the following:
    1) You will create your "promotion templates" in the standard SAP promotion planning screen.
    2) A custom ABAP program will be created which will copy a certain "promotion template" to a new promotion. The new promotion can later be edited in the promotion planning screen.  The program can use the promotion BAPIs to accomplish this (BAPI_PRMSRVAPS_GETLIST, BAPI_PRMSRVAPS_SAVEMULTI)
    Answer to Q2: I am not sure I understand your question correctly. If you go the promotion planning screen, you will be able to see the promotion's "total" values and also the CVCs that has been assigned to this promotion. Alternatively, you can use program /SAPAPO/PROMOTION_REPORTING which comes handy when displaying CVCs and it's promotion or vice versa.
    Hope this helps

  • Promotion planning level change from product to product  category.

    Hi
    About the promotion planning level, currently we use product level which means we adds individual products and assign money to there.
    But we are thinkin of changing this to product category level planning.
    Could anyone please teach me some good references or links or how to do it in step by step?
    It seems we need to do a lot of work to change the level of planning, but hopefully it might be not too difficult?
    If you know the solution, could you point me some directions?
    Thanks.

    Looking at all that code, I can suggest one way of debugging the issue(Its a bit hard to guess what went in this case,particularly when the problem could be at so many places).
    1. Run your PLSQL as an anonymous block and check if the generated XML structure is what you expect.
    2. Check Firebug Console (if you have it) if an ajax request is send when the item is changed.
    3. Print out the return XML as a string on the screen so that you can make sure it what you wanted(use alert function or append to some page element)
    4. Now try your XML parser JS section starting with the obtained XML as a static variable, trying printing out the parsed out values at different stages
    5. Setting the page items shouldn't be much of a trouble if everything else worked fine.
    Some Observations: If you are on Apex 4.0 wouldn't a Dynamic Action save you all this trouble (Two SetValue processes). Even otherwise you seem to be fetching two id's from the Ondemand process..Can't you just concatenate them with some separator and send that as the result stream(htp.p), handling them in JS would be simple using the split function. If the data is more complex you could return it as a JSON string and parse it with fewer lines of code.
    Found a problem with the code :
    get.add('PRODUCT_ID',pValue)Do you have a page item by that name(PRODUCT_ID) ? else change it to
    get.add('P4_PRODUCT_ID',pValue)and change the following in ur PLSQL process code
    PRODUCT_ID = TO_NUMBER (v ('PRODUCT_ID'));to
    PRODUCT_ID = TO_NUMBER (v ('P4_PRODUCT_ID'));But as I said earlier, Debugging it step by step might be easier.

  • My battery life at a full 100% charge is about 2 hours 22 minutes (backlight and key lights at lowest level). Should I go complaining to Apple or do I just need different software?

    My battery life at a full 100% charge is about 2 hours 22 minutes (backlight and key lights at lowest level). Should I go complaining to Apple or do I just need different software? I've only had my mac book since August 2011. The battery dies in 2 to 3 hours with some web surfing (little video play) and photo editing etc. I really don't feel like taking my computer all the way to the apple store to wait there for 5 hours to hear that I need to call someone blah blah blah. Any advice? (BTW Safari hasn't been working since I last updated my mac, WHYYYY?)

    emsavage1127 wrote:
    Should I go complaining to Apple or do I just need different software?
    emsavage1127 wrote:
    I really don't feel like taking my computer all the way to the apple store to wait there for 5 hours to hear that I need to call someone blah blah blah.
    Make an appointment at the genius bar, that way, you wont have to wait. http://www.apple.com/retail/geniusbar/

  • Is it Possible to do easy cost planning in network and acitivity level

    Hi,
    Is it possible to do easy cost planning in network and acitivity level
    Rgds
    Purna.M

    Dear Sanjeev,
    ECP not possible at Network or activities but it is not like that as you saying " any of cost planning not possible at activity level as per sap standard."
    It is possible to do Network Cost Planning, for that you have to make the settings required for to determining the plan costs in networks.
    In networks/activities the plan costs are:
    Calculated automatically on the basis of the defined price and quantity structures
    Planned using unit costings for general costs activities or material components
    for this make the setting in config of PS node Project System -> Cost -> Planned Costs -> Automatic Costing in Networks/Activities.
    Rgds
    Rajesh

  • Planned and Actual costs at the Activity level

    Hi all,
          Can you tell me if there is a R/3 report which lists out the planned and actual costs for a project and displays it for each network and activity? I want these values at the activity level.
          I found a report which lists out these values for each network, but I cannot drilldown to the activity level. Please help.
    Thanks,
    Satyajit.

    Hi,
    There is setting in network type. Please go through transaction OPUV  i.e.
    Change view- Network type paramaeters : overview " Overview.
    Uner Network type parameters there is one radio button in front of ActvtyAcctAssgn. Just activate it.
    Hope this helps.
    Regards
    Tushar

  • Planning at daily level and weekly reports ?

    Dear Experts,
    Will be advisable to do Planning at daily level and weekly reports in 7.5 NW?
    Any body did these kind of project earlier ? Kindly provide suggestions / recommendations please...
    Thank you,
    Kumar

    Hi Kumar,
    We had done a planning at the daily level. However, the scope was also small for this planning scenario.
    The main point is that in case of daily planning, the volume of the data might get too high. Any complex manipulation of the data might take a longer time due to the huge volume of the data.
    Hope this helps.

  • Lowest level planning ???

    hi sir
    What is the lowest level of planning???
    2.   Smoothing u2013 How do you do time period wise ???

    Hi Dallyanusha,
    1) The Lowest level of planning is planning or forecasting at the product level.
    2) Smoothing:- You need to maintain alpha, beta, gamma values, seasonal
    periods etc.,
    Regards
    R. Senthil Mareeswaran.

Maybe you are looking for

  • How to fix graphic freeze while playing minecraft?

    Hi My computer freezes every time I try playing minecraft. It works for the first 30/40min, but crashes more and more frequently after this (every 2/3 min for longer and longer periods of time!). If I stop playing for an hour or two, for some reason

  • Urgent : Home - Documents - Overiview - Public Documents

    Hi, I want to make some modifications in the Public Documents iview which could be found here in the Portal: Portal Content -> Content Provided by SAP -> End User Content -> Standard Portal USers -> iviews -> com.sap.km.iviews -> Public Documents. No

  • How can i check the unzip file has finished unzip process?

    i am using 7zip to unzip the file. java program can check the unzip file has finished unzip process? Edited by: rayray2008 on Feb 12, 2008 7:14 PM

  • OS X 10.8 Mountain Lion Photoshop CS5 Windows file server save issue

    After Lion to Mountain Lion upgrade. Cannot save or save as to Windows server. Due to "program error." Adobe Photoshop CS5. Can save as fine to local drive. Can also drag and drop in the Finder to this server. This is Photoshop CS5 12.0.4 (current).

  • Losing predictive text and error correction on keyboard

    A strange thing  happened to me and I am wondering if others have experienced this.  I was in the middle.of typing a message and the predictive text/spelling check, suddenly, went away. The keyboard was still there but without these options. Tried re