Dear Gurus,
Requirement is to close all open schedule lines beyond one month.
In detailed. User Enters Manual Schedule Lines as per the requirement of the customer say for 6 months.
for Eg . Sale order entered on 1st of august to Dec with 500 qty, schedule 100 qty/Month, manually in sale order.
Now if business delivers only 90 out of 100. they need to short close that particular schedule line only not the entire sale order or line item. I tried with Delivery block at schedule lines level. but it is not working.
If any one has come across this scenario please share with me.
Regards
Praveen

If we apply a delivery block the pending qty will automatically add to the last schedule date. Ex. if there is 3 dates in the schedule lines, and there is some 50 qty pending in second date, and if u apply delivery block it will carry forward that pending 50 qty to the third schedule line and adds up with it.
But in my case i just want to close that pending 50 qty in second line item.
Regards
Praveen
Edited by: Praveen_PG on Sep 15, 2011 1:28 PM

Similar Messages

  • Open Sales Order  table with multiple schedule line....

    YUSUF BHORI wrote:
    Hi Experts,
    In Sales Order there are multiple schedule line for single item.
    Where and in which table i can find open qty for order ,material, item and schedule line items.
    I Want open items for each schedule line. For One vbeln, posnr there multiple etenr.
    Urgent,
    Yusuf.

    Hai,
    Join VBAK & VBAP and store data in an internal table GT_VBAP to get Sales order numbers, items, materials.
    Get Open Sales order items from VBUP into GT_VBUP  where VBUP-GBSTA  NE  'C'.
    LOOP at GT_VBAP.
    Read table GT_VBUP with key vbeln & posnr.
    If sy-subrc <> 0.
      delete GT_VBAP.
    endif.
    ****Fill your Final Report Internal table with required field values **Append into that internal table
    ENDLOOP.
    Now Select WMENG BMENG from VBEP into GT_VBEP for all entries in GT_VBAP.
    LOOP AT  GT_VBEP.
    *******Again Modify your Final Report internal table with these values
    ***VBEP-WMENG is Ordered Qty
    ***VBEP-BMENG is Confirmed Qty
    ************Open Qty     = Ordered Qty      = Confirmed Qty***
    ************Open Qty     = VBEP-WMENG = VBEP-BMENG.***
    ENDLOOP.
    Edited by: Eswara Rao Aakula on Dec 24, 2007 9:56 AM
    Edited by: Eswara Rao Aakula on Dec 24, 2007 9:57 AM

  • My sales order is having two schedule lines

    Hi sap gurus,
    my sales order quantity is 36 pcs.
    the same sales order has two schedule lines in that the material availability date is 05/02/2010 for quantity 22 and for second is 15/02/2010 quantity is for remaining 14 quantities.
    so here delivery can be created for quantity 22 becasue the MAD is on 05/02/2010.  upto here no issues.
    here in my production server user is able to create only one delivery document for total 36 quantity which includes the 14 quantity also for which the MAD is at a far date that is 15/02/2010.
    (2).  i opened the delivery there two picking requests has been generated one on 04/02/2010 & for 07/02/2010.  how it is possible by the system.
    how is it possible for a material which is available in the future date that is 15/02/2010.
    can any help on this.
    regards,
    balaja

    Hi,
    Though the MAD is different, same delivery is possible for the two Schedule lines.
    But for the picking request creation for the future MAD (15/02/2009), please check your sales order. That is, go to VA02, and in to the schedule line level and then to the Shipping button and look for the various dates...
    Regards

  • Sales order we have made schedule line category catCN but still reqt coming

    Dear Sir,
    Sub : For sales order 5000060 line 10 we have made schedule line category as CN but still system is giving requirement against this order (while running MRP T code MD50)
    Details:
    One user has made one FG material delivery with PGI without putting the picking quantity. He had put zero picking qty. When we click PGI button System does not allow to do PGI without putting the picking qty but how he could do it we do not know. Now there is no goods issue material document instead one confirmation of service document is there in doc flow .we can not open this document. if we click display by selecting this document in document flow system gives error - NO document created for confirm service/cancel transaction
    All the delivery fields are gray out. Delivery qty is there in this delivery hence at sale order schedule line tab against the schedule line system is showing delivered qty -2.
    Goods movements status is B- partially completed.
    Also system is not allowing to reverse the delivery- it is saying-no data available for this selection criteria. Hence we are not able to do delivery against this item. Hence we have created sale order line item 20 & transferred this stock to line item 20 & did subsequent transactions.
    Now system giving requirement for line item 10 .We have made schedule line category CN still system is giving requirement against delivery number  in T code -MD 50 against sale order line item- there is customer order ,delivery, production order .delivery number never comes in MD50 .it is giving requirement against delivery.
    Kindly let us know how to stop the requirement to generate from this sale order line item
    Also kindly let us know how user could make this & how this might have happened & how to restrict this in future.
    Regards

    Dear Sir,
    When we create a sale order default sch line category is CN after few days (there is a specific reason) we change it to CP & run MRP
    In this case we made the product by doing this but while doing delivery .user did some mistake & did PGI without picking qty in delivery.Now this qty is in delivery but there is no material document that stock has not yet moved .Since there was a problem in the delivery we have trasfered this stock to sale order line item 20.& did further transactions.
    Afte this we did schedule line cat from CP to CN
    But in MD50 system is giving the requirment against sale order ,delivery
    Regards

  • Sales Order Stock - Problem with Schedule line

    Hi guru,
    I have a problem with my schedules line.
    We use the Sales order stock ( using MB1B with good movement  412/E) for some specific customers.
    Even if the sales order reservation works well, there is an issue with the schedule line in the order.
    Indeed when i enter the material in the order the schedule line display an availibily in 8 days even if the material is out of stock or available now....
    When i enter the same materila in a standard order(with item category without special stock E) the schedules line are good...
    What is it the most weird is that i have done the customizing by copying the standard item and i have just added the special stock E in the item category.
    If anyone can help me!!
    Thanks a lot

    hello Lakshmipathi,
    Thanks a lot for your reply.
    I tried to change the requierement class in order to put one with special stock E as you explained, but i still have my weird schedule line. When i put the item in the order it is 0 stock for today, but stock find in 12 days either if there is stock or no(unrestricted stock i mean).
    If i change the RDD in more than 12 days the stock is available for the date requested.
    If you have an idea of what could be wrong because on my case i want the schedule line to be at 0 while the sales order reservation has not been processed (via MB1B/412/E) and once the stock movement is done the schedule line has to be find.
    I dont know if im clear enought..
    To be more clear,  i want the schedule line based on the "sales order stock" and not on the "unrestricted stock".
    thanks for your help!
    Guillaume

  • Delivery block with confirm. block on schedule line level in sales order

    We customized a new delivery block with confirmation block.
    When using it in sales order header, it is working correctly: the availability check in APO gATP is executed; but as soon as I save the sales order, the confirmation quantity is set to zero.
    We now need to use this on schedule line level, not on header level. It is not working. Even after saving the confirmed quantity stays as filled by gATP availability check.
    What is wrong? SAP help / documentation officially describe that delivery block with confirmation block either works on header level or on schedule line level.
    Thanks in advance.
    Edited by: Schmidt on Aug 13, 2008 4:47 PM

    Please see if OSS notes 21584 and/or 19488 might help.
    Regards,
    Anisha.

  • Sales order delete and rejecting the line items

    Hi,
    1 )What is the difference between deleting a sales order and rejecting all the line items of a sales order.
    2) Are there any pre-conditions for deleting a sales order.
    3) why there is a need to reject line items of a sales order
    regards

    What is the difference between deleting a sales order and rejecting
    If you delete a sale order, you cannot retrieve it or view it.  On the other hand, if you reject any sale order, at any point of time, you can retrieve that sale order and analyse as to why it has been rejected.
    Are there any pre-conditions for deleting a sales order.
    Certainly not.  Its all depends on the discretion of the user.  Of course, you cannot delete a sale order if any subsequent document exists.
    why there is a need to reject line items of a sales order
    Customer has placed an order and at a later date, due to some reason, they have asked the client not to proceed with production against that sale order.  Now if the Management decides to track such of those sale orders, you can assign reason for rejection and have it in system for record purpose.
    thanks
    G. Lakshmipathi

  • Customer purchase order number at schedule line level in scheduling agreeme

    Hi,
    We have one typical requirement from scheduling agreement functionality. The scenario is we receive the schedule lines from Idocs from customer with purchase order number for each schedule line. We need to print that PO number on packing slip and ASN. How do we capture the schedule line po number in SAP SA?
    Please share your ideas on this.
    Regards, Lakshmikanth

    Hi Chandrasekhar,
    Thanks for your reply, here we create one delivery for each schedule line quantity, we need to copy the respective purchase order number into delivery. There is no Corelation between schedule line number and additional data field, so we can not use very freely.  Do we have any other option?
    Regards, Lakshmikanth

  • Change the  sales order reason for rejection for line item

    Hi,
    i want to change the  sales order reason for rejection for line item.
    iam using bapi_salesorder_change.but i unable to change the sales order.
    if possible please provide me what are the fields necessary  for changing
    sales order reason for rejection for line item.
    Regards,
    Suresh

    This is the standard config to supress printing on the rejected item. Are you using standard programs or customised ?

  • Changing delivey dates on schedule line level in Purchase order in IS AFS

    Hi,
    I want to know if there is any standard transaction or enhancements to change the delivery dates in purchase order on schedule line level in IS AFS scenario on mass.
    Thanks,
    Kumar

    Hi Antony,
    Thanks for the reply.But the transaction MASS is not enhanced for changing delivery dates in schedule line level in IS AFS.
    Thanks,
    Kumar

  • Availability check box at schedule line level and requirement class level

    Hi All
    What is the significance of availability check field at schedule line level and requirement type level.
    If I remove the check box at schedule line level, then there won't be any availability check carried out in the sales order, even though in requirement class it is checked. Is it for doing availability once the requirement is passed to MRP...
    In make to stock scenario, no availability check is active at schedule line level.
    scenario 1. stock is 0 in plant, when i place an order for 10 quantity, does system give any confirmed quantity on so and so date...or the confirmed quantity will be zero or as there is no availability check carried out, it confirms 10 quantity on customer requested delivery date and the time of creation of delivery, it gives an error message stating zero quantity is available. which one is correct in all the above.
    In make to order scenario, no availability check is active at schedule line level.
    order was created for 10 qty, as there is no availability check active, does the system give some date based on the lead times maintained in the material master or not?
    Regards
    Sree

    Hi sreekar
    The significance of availability check at schedule line level  is to determine weather availability check and TOR should be carried out for sales orders  or not. 
    If you remove check box at schedule line level , availability check and TOR wont be  carried out at sales order level.
    Coming to the scenario you said , make to stock , i think the availability check you are using is 01 make it 02. which is planned requirements. and stratergy group as 10. in MRP3 view in MMR. .
    as the availability check u have put 01 & stratergy group as 10 availability check doesnt carry
    coming to the scenario 2  , if the stock is 0 in plant and if you create a sales order, then the confirmed quantity should be 0 and that particular order will go to backorder processing.
    sometimes it  confirms the ordered quantity as the  confirmed qunatity, and it gives a confiremed delivery date on which the stock is confirmed , but that date is a tentative date.
    all these unconfirmed orders will go to backorders. once the qunatity is confirmed automatically , delivery date also will be done
    Coming to scenario 3 , when you create MTO order there will be availability check checked at the schedule line level. can you tell wat is the schedule line you are getting is it CP or ND?
    for schedule lines , ND - no availability check will be there , PD - availability check will be there
    Note: plz check 1st the availability check you have entered in MMR , if it  is 01 make it as 02. and then run these cycles.
    Reward points if useful and if Any queries let me know
    Regards
    Srinath
    Edited by: sri nath on Mar 21, 2008 7:53 PM

  • Force ATP-check at schedule line level

    Hello All,
    I want to trigger the ATP check when I change some specific values at schedule line level ( Change the value-> press enter and In the enter event the ATP should get triggered, so that I could see the Value changes online).
    I tried calling FM SD_BACKORDER_CHECK_AND_SAVE in user exit "userexit_check_vbep USING us_dialog" , But this is not the correct place to call this FM.
    Could anyone let me know if we can acheive this using any other FM.
    Thanks
    Bhavana
    Edited by: Bhavana Sati on Aug 11, 2010 10:43 AM

    Hi Victor,
    To do ATP check at Storage location level during sales order create/change, you need to make changes on the following areas.
    1. Scope of Check "Availability Check Control" for Checking rules pertaining to orders (TCode OVZ9)
        Storage location inspection checkbox should be blank.
    2. Enhance program MV45AFZB user-exit USEREXIT_SOURCE_DETERMINATION to determine storage location as it is not normally proposed in sales order.
    Let me know if this helps.
    Arnel Adordionicio

  • Is there a way to track the delivered qty at the schedule line level in R3

    Hello Gurus,
    Is there a way to track the delivered qty at the schedule line level in R3.  I spoke to al ot of functional guys on this and the answer is NO. If NO,then, how does the 2LIS_11_V_SSL extractor extract the delivered qty at schedule line level. Help is really appreciated.
    Thanks
    Simmi

    Hi Simmi,
    I have used this extractor for the purpose you describe at more than one customer without problem. My understanding is that it links the order schedule line with the delivery, but I haven't tried to work out the mechanism.
    Regards,
    Ken

  • Tolerance limits at Schedule line level in PO

    Hi
    How to make tolerance limits at schedule line level in PO, (not at item level)
    Thanks
    Raju

    HI Raju,
    In PO Delivery schedule qty tolerance is not possible.
    PO delivery line itemwise tolerance only possible and also we have freezed tolerance in the line items.
    Based on line item qty, We have delivery schedule given and not exceed line item qty.
    Hope, you are clear.
    K.Rajendran

  • Schedule line level data

    Hi,
    I understant that SRM could not handle schedule line level data, Can any one explain me what is schedule line level data exactly and if the current vesrion of SRM does support it?

    Hi,
    Schedule line data is handled in SUS(Supplier Self Service) one of the module of SRM since June 2002 version SRM 2.0
    You have to use Process " Plan driven Procurement with R/3 - SUS scenario.
    Schedule line data in MM R/3 is published to SUS - supplier system as Scheduling Agreement releases automatically.
    Supplier can either accept or reject a schedule line.
    In current version of SRM 5.0 many useful functions are available like automatic E mail to buyer on acknowledgment of Sc. line data by Supplier.
    Write me if you need more detailed info.