Hi,
My client is using REM. They create planned orders in their distribution centre and through special procurement manufacture the orders in a seperate manufacturing site. There is no stock transport orders the goods are manufactured in the production facility and recieved into stock in the distribution centre during backflushing.
The cost collector is set up for the planning site so that once the planned orders are settled the moving average price of the finished product is updated in the distribution centre.
My client wishes to add a 'transfer price' at order settlement so that the moving average price in the distribution centre is updated with the new moving average price + the transfer price during settlement.
Is this possible using transfer pricing functionality??? How is it implemented?
R'ds
Nick

Hi,
If this indicator is turned on, the costs are collected on a product cost collector. In this case you use the functionality of Product Cost by Period. In this case you calculate the work in process and variances by period
If this indicator is not turned on, the costs are collected directly on the manufacturing order. In this case you use the functionality of Product Cost by Order.In this case you calculate the work in process and variances by lot.
Cost Collector will be used in conjunction with the distribution rule - PP2 periodic settlement.
In discrete , if you split the order you have to use the cost collector indicator and the PP2 periodic settlement rule.
Regards,
Sheik

Similar Messages

  • ISO UoM vs USA UoM for SO and Transfer Order

    Hi to All,
    I've an issue  that I must resolve urgently!!!  So, I hope in your precious advices.
    Case: Customer Model: Holding with european company codes and americans ones.
    The corporate is an Italian Company. So, Materials Master Data are created centrally at Italian Company; consequently the Base Unit of Measure in which stocks of the material are managed (Master Data: view Basic data 1) is expressed in ISO UoMs( Kg, dm3....).
    I have the necessity to use also american UoMs so I've created in Additional Data -> Unit of Measure  alternative TU and CU using USA  UoMs for the dimensions (lb, "3....) in corrispondence to europeanTU and CU.
    I can use them on Sales Order, and Transfer Order with type ZT02 STO Cross Company but I can't use them for ZT01 STO from APS: Transfer order intra- company becouse as default the Base Unit of Measure is used.
    Does it exist a way to convert the Base Unit of Measure expressed in ISO UoMs to USA UoMs for dimensions without modyfing the Base Unit of Measure set in Master Data: view Basic data 1?
    Thanks in advance
    Roberta

    Hi,
    If you want to create any transaction with only alternative unit of measure  you don't active variable active unit of measure in purchasing view of material master. In this field take not active.
    Variable Active unit:
    When you required to create any transaction with both unit of measure  base unit and alternetive unit of measure you active it and if you want to create transaction with only alternative unit you don't active it.
    NOTE: - In case of Purchase order system take order unit of measure(In Purchasing view) and for stock transfer order take unit of issue(Plant Data1) - If variable active unit is off.
    Regards,
    Mahessh

  • Costing for Maintenance- and Service Orders

    hi
    Can any one tell me the Configuration steps for Costing for Maintenance- and Service Orders.
    Kindly please guide me.
    regards,
    R.Ramakrishnaraj

    Hi,
    Please go through below mentioned threads.
    Re: Activity Costing
    Re: PM order costing.
    Re: Planned cost not getting displayed in Maintenance Order
    Re: Costs not appearing in service order
    There are many threads available for Costing. Please search in the threads.
    Regards,
    Maheswaran.

  • Product cost collector settlement

    Hi
    I have done the prdouct cost collector settlement. 
    What would be accountry document entry for this settlement ?
    Please comment.

    any comments, pl.

  • Standar cost and product cost collector not updating the new price

    Hi,
    Created Standard cost estimate for one FG product and runned the product cost collector. Based on that consumption delivery everthing is made. Later on the work center and activity type changed in routing. Now i am trying to run the standard cost with new activity price (due to work center change) for the current period, system is showing only the previous rate(previous period) and it is not updating the new price becuase of already we have created the product cost collector.
    Can any one give the suggestion for how to update the new price in standard cost as well as new price updation in product cost collector.
    govind.

    Hi
    1. If the original cost estimate was run in the current month - Then you cant re-release cost estimate unless you reverse it from CKR1
    If the cost estimate was of previous months - then you can definetely release it again
    2. In cost collector, you need to manually cost it again using the Preliminary costing feature... Your cost coll will then show 2 cost estimates i.e. One from Original date to current date-1, and 2nd from Current date to 31.12.9999
    br, Ajay M

  • Cost collector settlement

    We are having huge amt in settlement at every month end. We use cost collector as the cost object and backflush process. The huge settlement amt is because of some raw materials not being backflushed to finished goods and some times it is because of the missing activities costs. All these contribute to the difference in cost collector and shows up in settlement. I want to know if there is a way to know if  the amt difference in a cost collector is because of material being missed or activites missed during backflush? As there are lot of materials it is hard for me to research on each material. so i am looking for a easy way.
    Thanks in advance

    Hi,
    Ur raw material are converted in to finished good but because of some missing in contribution of
    cost activities u are not converting the material in to FInished goods right
    so u can create some text message for the missing Materials in document header
    are in the text where ever u mention the text so when u executing the  material list
    u can sort it out by the text and identify the missing ones.
    Regards,
    Padma

  • KKAX shows WIP costs after settling the production order

    Dear experts,
    We have production order and we did the following actions in March (end of the year),
    1-     Create the order
    2-     TECO the order
    Then in May we did the following actions:
    1.     Revoke TECO
    2.     Give DLV
    3.     TECO again
    4.     Calculating the variances
    5.     Settle the order
    The problem that in KKAX we can see the WIP costs in the column (WIP (Cumul.))
    So, although the order is settled but the WIP costs not cleared,
    And as I know the settlement will clear the costs, how this happen.
    Thanks in advance

    Hi
    First u see whether u have any incomplete Production order .
    That is in any oder have u not comfirmed quantity if  in this casse please clear than now  try to run the KKAX
    Regards
    Ramanujam

  • User exits for delivery picking confirmation and transfer order creation

    Hi
    We have a scenario for which we need help.
    This is to do with replenishment from plant to plant.
    We have sales sets.
    The sales sets needs to be replenished from one plant to another. We want the componenets of the sales sets to picked from the issuing plant. For this we need a transfer order. this needs tobe confirmed and then the goods issue should take place from the issuing plant. Its a two step process.
    we are doing Sales sets in STO. The explosion takes place in STO. However when we create deliveries for this. Only the sales set header item without its components are flowing into the delivery.
    The Tranfer order does not contain the components either.
    However post  the goods issue we  can create a TO with reference to the TR. This is is not acceptable because we want the picking and confirmation to occur before PGI from the issuing plant.
    Could anybody help: We want the TO to be created with the components even though in the delivery only the Sales set header appears. Can u suggest a user exit in which when we create the TR from the delivery the components of the set.
    After confirmation of the TO then we want the picking status to be put as C.
    Supreeth

    Hi,
    Check the following users exits.
    MWMRFSSG            user exit for sorting TOs in RF system-guided transaction
    MWMRFUP             Customer defined general purpose pushbutton called from scr.
    MWMRP001            Cust. Exit for Fixed Bin Replenish.: Delivery Item Selection
    MWMRP002            Cust. Exit for Fixed Bin Replenishment: TR Quantity Distr.
    MWMRP003            Customer Exit for Replenishment using RLLNACH1
    MWMRP004            User Exit for Replenishment using RLLNACH4
    MWMTO001            Enhancements for end of transfer order generation
    MWMTO010            Exit: Calculation of Total Planned TO Processing Time
    MWMTO011            Correction of Planned Processing Time for TO Item
    MWMTO012            Correction of Sorting and Split Transfer Order
    MWMTO013            Stock Removal for Sev. Storage Types as in Stringent FIFO
    MWMTOAU3            Separate selection of posting changes for autom.TO creation
    MWMTR001            Exits at the end of transfer rqmnt creation (IM,PP interf.)
    MWMD0001            Transfer order print via RLVSDR40
    MWMD0002            Transfer order print as multiple process with RLKOMM40
    MWMIDI07            Enhancement for Output WMPIHU (Create Pick-HU) Inbound
    MWMIDO11            Enhancement for message WMTORD: TO with several items
    MWMIDO12            Enhancement for Output WMPIHU (Pick-HUs) Outbound
    MWMIDO13            Extension for WMMBXY (subsequent tasks after goods movement)
    MWMPP001            Enhancement WM/PP Interface (automatic TR generation)
    Regards,
    Murali

  • Purchase requsition and Purchase order Price Changes

    Hi All,
    When purchase requsition(XXXXXXXX) is converted in to a purchase order through ME 59N(YYYYYYYYYY),after converting in to a purchase order i will change the purchase order price to a new value.
    How can i track the price changes for a purchase order that is converted from a purchase requsition.(i know i can see the changes to a PO,under item changes for PO)
    Is this data is stored in any table?
    with regards,
    Amogh

    Hi,
    this change is not captured, because the price is being changed at the point of the PO creation and so there will be no record in the header or item changes option (the system does not see anything as being changed because this is a creation of a new PO).
    The price from the requisition is merely a suggestion and it is not meant to be a purchase price anyway (it is designed to be used to value the requisition for the  release strategy).
    I know that you can configure the system to pass this req "price" to the PO, but it is not the same price and so you will not find the type of controls that you would expect.
    In many cases a simple ABAP is written that reads POs that have a reference requisition and the ABAP compares the prices and reports on those that exceed a tolerance (either hard coded in the program or held on a new table in SAP).
    None of this is standard SAP but it is something that many people create to handle the situation where the user enters the requisition at a deliberately low value to get it through the release strategy.
    Steve B

  • HU and Transfer Orders

    Hi All,
    I have a scenario where system is creating as many Transfer Orders as many HU's that i create.
    I have HU managed Storage Location. I am creating an inbound delivery for the standard purchase order and in the inbound delivery i need to create a HU for each unit (ex: if i am receiving material A, Qty 10 units; then i have to create 10 HU's) and further when i create a transfer order for the delivery, system creates 10 transfer orders (one for each HU). How to fix this issue, i want the system to create one transfer order for each inbound delivery. All your inputs will be appreciated.
    Regards,
    Samuel

    Hi Nagesh,
    Thank you for the response. I have the standard profiles given by SAP for my warehouse in Verification Control-Assign Verification Profiles to Goods Movements (PCKEAC, PICK, PUTWY)
    W05     ***     916     0     PICK
    W05     902     ***     0     PUTWY
    W05     902     ***     501     PUTWY
    and i do not have TO Split activated in Transfers-Processing Performance Data / TO Split-Define Profiles.
    Regards,
    Samuel

  • Need help on Picking due list and Transfer order.

    Hi Folks,
    In our current process, the deliveries are taken from picking duelist (VL06O)and the transfer order is created manually. Now we want to automate this process. I know that it can be done by a batch job.
    Could some one tell me the program that should be used in the batch job which takes the delivery numbers from picking duelist and creates transfer orders?
    Points rewarded.
    Regards,
    Krishna

    Hi
    you can use this program WS_MONITOR_OUTB_DEL_PICK
    or
    In transaction VL06P you can give the selection criteria & click on Create TO in background. You can schedule this job as per your requirement.
    Thanks & Regards
    Kishore

  • How to create wave pick document and transfer order from that document

    Hi All,
    I want to create wave pick document based on delivery and correspondingly want to create transfer order for that. My requirement is that if in 3 delivery i have to pick material M1 as 100, 50, 100 qty then when i create wave pick for these deliveries and create Transfer order by this wave pick doc it should pick from single bin of warehouse , currently it is picking from 3 different bins though qty in each bin is more than 250 in each bin. Also suggest me the configuration requred for this.
    Thanks in advance:

    Hello Gordon, tha is working perfect now I finaly get the forecasted items in my MRP window If I click on show recommendations I see he recommends he wants to order some pcs, and Indd what I split in to Buy or Make is separated in an Production order. But how do I change the recommendations into orders?

  • Sales order stock on delivery document and transfer order

    Hi all,
    At my current client I have a requirement where we need to put stock against sales order (sales order stock E). So, being a MTO process we create production order and perform goods reciept to unrestricted stock. To avoid getting picked up by a different sales order, we move the stock to sales order stock using 412 E (tcode: MB1B). Here are the issues I am facing currently:
    1. Is there a direct way of receiving production order directly to sales order stock?
    2. I couldn't find a way to do the first, so I am currently receiving production order against unrestricted inventory and then move it using MB1B. So, the stock can be seen to assigned to sales order.
       2a. When I create delivery it is not consuming same stock, it is consuming inventory out of unrestricted stock (if any, in case no inventory is available it throws error of 0 available quantity). Once I have assigned sales order stock why is it still looking into unrestricted? Is it due to the requirement type which is assigned. Do I need to change the item category so availability will check sales order stock (similar to item category TAB)?
      2b. This probably will be resolved if I get the delivery fixed but we have SAP WM and during TO creation I don't see the special stock reference filled in? I tested this process with item category ZTAB (copy of TAB) which creates purchase requisition and it seems to be working but I don't need the purchase req for my case.
    3. This is more of an accounting issue: when I attempt to move stock from unrestricted to sales order stock using 412 E, I was getting "Account XXXXX is not assigned to cost center". So, I went in an assigned a cost center to this cost element. IS THIS REQUIRED & WHAT IS THE RELEVANCE as it takes stock out of inventory.
    I understand it crosses other functional areas but even if you can clarify 1 part of it, will be very helpful.
    Thanks.
    Naren

    Dear Friend
    You are telling that it is MTO scenario and you are posting stocks into unrestricted stocks
    This is entirely wrong
    This is happening because of a simple thing missing in your sales order item category configuration in VOV7 that is special stock indicator E is missing which should be there
    This is the cause of whole problem
    MTO item categories will have special stock indicator E in standards
    In MTO based on the sales order production order is triggered and stocks are receipted against sales order and not into unrestricted use by defaut in standard
    You will receive MTO stocks as sales order stocks in your plant  only in standard
    But it is not happening for you because of  stock indicator E in VOV7 of your sales order item category is missing
    Posting MTO stock in to unrestricted use is meaningless  and the same is happening because of a slight miss out in setting in VOV7
    This is the solution for issue no 1
    For issue no 2
    You have created the sales order( MTO order) without special stock indicator E and now you are doing a transfer posting in MB1B with 412 E  referencing the order no sales order stocks  that is Fine
    You are getting an error that only zero qty is available either at delivery or at pgi eventhough in MMBE you will find sales order stocks in your order name
    This is happening because
    Reservation in MB1B is done with special stock indicator E for sales order
    But the  same sales order is not created with special stock indicator E in VA01 during creation
    There is a mismatch
    Hence the system is not able to sense while the order comes for delivery there are already stocks are reserved
    By inputting  special stock indicator E for sales order item category the whole issues will get solved
    By doing that there is no need to do MB1B itself
    The first step itself will get corrected  as the stocks will be posted to sales order stocks no need for MB1B
    No need to touch TAB make it ZTAB as it is meant for a different purpose it is for individual purchase order not to be used for MTO
    *By marking the special stock indicator as E in your sales order item category your entire issue will be resolved*
    Issue no 3
    MTO is based on costing for which you have take the help of FI person
    Note Very important
    If U make the settings now in item category it will not work for the existing or already created order
    With existing orders it will have the same error as the order is created without special stock indicator E
    Only for new orders it will work and from Now on it will work
    Test it with new order cycle starting from VA01
    Please let me know this issue has got solved or not?
    I am 200 % sure it will get solved
    Regards
    Raja

  • Full Settlement and transfer AUC to Completed Asset

    I'm trying to do full settlement on my project and it doesn't transfer cost to my Asset Shell.
    When i try to test partial settlement i could see a transaction created.  Am i missing a step or did wrong on my configuration or settlement rules in my project.

    HI,
    Please check the settlement profile  and check settlement rule
    Regards
    srikanth

  • Costing with Standard and Moving Average Price

    Hello All,
    I understand that SAP recommends Std Price for Semi Finished /Finished goods and MAP for trading goods and raw materials.
    How does costing takeplace when it includes both the materials - semi finished and trading goods.
    Is it possible at all?
    Any suggestions will be helpful.
    Thank You,
    Andy

    Hiya,
    You may want to frame your question differently.
    When what(?) contains SF and Trading Goods? BOM? Costing Run?
    The Std Price and MAP you mentioned are the Price Control Indicators. These dictate the price to use and the treatment required for the material (realtime stock value updation during the month with GR/GI for MAP and no value updates for SP).
    By itself, it does not affect the costing of (say) a BOM containing both these materials together... the system determines what price to use and costs the product accordingly.
    Cheers.