Rescheduling of order based on operation confirmation dates
Hi All,
Our production process to complete a product has got long lead times.
In production order, for example, there are four operations OP10, OP20, OP30 and OP40.
During production order creation, system will perform lead time scheduling based on standard value time mentioned in the routing for every operation. Due to long lead times and production delay, there will be delay in actual execution of these operations with scheduled dates. After confirming OP10 with actual execution dates in CO11n, if we go to production order and click on scheduling button, then system reschedules remaining operations dates in the production order based on actual execution times entered for OP10.
Our requirement is by using Enhancements/BADI/IDOCs is it possible to automatically reschedule the order after confirmation of OP10 in order to reflect nearest actual production execution dates.
Please suggest your valuable findings.
Thanks & regards,
Satya.
Hi,
1. For calibration orders .. once usage decision is selected as OK , we can trigger follow up actions via which u can do TECO of Calibration orders , for this u have to do settings in QS41 for Catalogue 3- Usage decision , QS51 - For a catalogue 3, Plant , Selected set as * , here for a selected set , u can define for a combination of code group and code u can give valuation code & follow up action .. , this follow up action is defined via SPRO -->QM -->Quality Inspection -->Inspection Lot completion -->Define Follow up actions -->Here u can define Follow up actions and use FM QFOA_ORDER_TECHNICAL_COMPLETE :- Follow-Up Action: Technically Complete PM Order ,Select After posting & sync update tick mark.
2. For other orders , In IW42 - U have the option for TECO but need to do manually , but for automatic case i believe u have to use User exit :- CONFPM05 PM/SM order conf.: Cust. specific enhancements when saving , you have to use a suitable FM , which
regrds
pushpa
Similar Messages
-
Conversion of Sales Orders with Original ATP Confirmation Dates/ Quantities
Hi
Please suggest best practice to maintain ATP confirmation dates/ quantities during sales order conversion. We have committed schedule lines in a legacy SAP system. Now we want to maintain the exact same dates/ quantities when loading these dates into the new SAP system.
We will not have supply (inventory/ orders) loaded at the time sales orders are loaded.
Thanks
Rishi MenonHi
I will suggest to turn-offthe Transfer of Requirement & Availability Check from the Schedule Line (VOV6). And then make your BDC to upload the Sales Order of Legacy System in SAP.
While creating the BDC recdord the consider the Schedule line date and quantity.
Regards,
Amitesh Anand -
Purchase order list display with confirmed date
Hi,
I know the ME2* transactions, but how can I get a list from SAP where I see for a list of purchase orders the initial requested delivery date next to the confirmed delivery date?
Thanks,
Peter
Helpfull feedback will be rewarded.Hi,
you need to customize on this requirement, use below purchase order tables
EKKO Purchase document
EKPO Purchase document (item level)
EKPV Shipping-Specific Data on Stock Tfr. for P Doc. Item
EKET Delivery schedule
VETVG Delivery Due Index for Stock Transfer
EKES Order Acceptance/Fulfillment Confirmations
EKKN Account assignment in purchasing
EKAN Vendor address purchasing
EKPA Partner functions
EIPO Item export / import data
EINA Purchase info record (main data)
EINE Purchase info record (organisational data)
EORD Source list
EBAN Purchase requisition
EBKN Purchase Requisition Account Assignment
Regards,
Sankaran -
Production order release based on operation
Hi friends
How to release production order based on operations ?
pl help meHi
The real time scenario is to select release operation wise is:
If you are expecting any change in the subsequent operations after starting of production say first opration, you will opt for this .
I do not find any advantage if you release all operations at a time in mass processing. It is as goods as releasing at header level.
Normally in such cases one can opt for trigger points in which system will release successive oprations automatically when preceding operation is confirmed.
If you want manually release the operations you can select the operation which you want release & press release button in operation overview screen.
Hope it is clear now.
Regards
YMREDDY -
BAPI to create SNP planned order based on start date
Hi,
I am looking for a BAPI to create SNP planned order based on the order start date. There is BAPI BAPI_MOSRVAPS_CREATESNPORDER which can be used to create SNP planned order based on the end date but not based on the start date.
Also would be great if some one can share how do they create SNP Planned orders using BAPI BAPI_MOSRVAPS_CREATESNPORDER in case if GR processing time is defined in the product master and workdays for GR to be respected according to the calendar.
Regards,
VenkatHello Mr.Venkat,
Hope you recognize me.
Please check out the BAdi below.
BAdi - APO_BAPI_BUS10503 (this is the BAdi for ManufactOrderAPS BAPI which contains the SNPorder BAPI)
Method - CHANGE_SAVEMULTIPLE2
In this method parameter IT_ORDER_HEAD contains Order start date input option.
For GR time please check this (not sure if it will help).
Same BAdi/ same method
Parameter IV_PLANNING_MODE_USAGE contains field PLANNING_MODE.
Value 1 for PLANNING_MODE corresponds to "Observance of parameters from the product master".
This may make it respect the GR time in product master
Good luck with the above
Regards,
Ashok -
Facing Schedule lines Material Confirmation date inconsisteny in order
Hi Experts,
We have created Material 100 (FERT) in Plant 1000 (in both Storage location - 0001 & 0002) as well as maintained in production time: 14days in MRP2 tab.
When I attempt the material 100 in standard sales order Iu2019m receiving schedule confirmation date: next day (01.12.2011) for Plant 1000 and storage location 0002 combination (using Field user exit for automatic storage location determination).
However when I change the storage location from 0002 to 0001 in the sales order item level manually u2026Iu2019m getting schedule Material Confirmation Date: 15.12.2011 Pop up...
Expertsu2026 please guide me where I did the mistake for 0001 Storage location and right me.
Thanking you !!!
Vijaykumar Kdear friend,
in this case you would open 2 sessions in MM03:
this material on Plant Data / stor.1
and same material for same tab for the second Sloc
and compare data
say, for example, the difference might be in Container reqs field or someone else...
compare Plantdata/stor. 2 for your SLocs as well
good luck! -
TECO of Main Order based on UD or Operation Confirmation
Dear,
In my existing system, we have to do TECO manually. But I want system to perform TECO of maintenance order once I am doing result recording (calibration main order) or Operation confirmation.
Rgds,
DipenHi,
1. For calibration orders .. once usage decision is selected as OK , we can trigger follow up actions via which u can do TECO of Calibration orders , for this u have to do settings in QS41 for Catalogue 3- Usage decision , QS51 - For a catalogue 3, Plant , Selected set as * , here for a selected set , u can define for a combination of code group and code u can give valuation code & follow up action .. , this follow up action is defined via SPRO -->QM -->Quality Inspection -->Inspection Lot completion -->Define Follow up actions -->Here u can define Follow up actions and use FM QFOA_ORDER_TECHNICAL_COMPLETE :- Follow-Up Action: Technically Complete PM Order ,Select After posting & sync update tick mark.
2. For other orders , In IW42 - U have the option for TECO but need to do manually , but for automatic case i believe u have to use User exit :- CONFPM05 PM/SM order conf.: Cust. specific enhancements when saving , you have to use a suitable FM , which
regrds
pushpa -
ATP check with RLT - rescheduling keeps pushing confirmed date out???
In order entry, our availability check is looking only at inventory and RLT... so that if stock is unavailable, the line item gets confirmed for a future date based on the material's RLT. We have noticed, however, that every night when backorder rescheduling runs, the confirmed date is pushed out one day later (assuming that no inventory exists still). So it appears that BO rescheduling is recalulating the confirmed date based on the current date + RLT.
Does this make sense? Is there any way we can make the original confirmed date stick? We don't want to use the Fixed Date & Qty flag on the schedule line screen, because we want to be able to pull the confirmation (and delivery) in earlier if the inventory is available earlier... we just don't want it to keep getting pushed later.This boils down to a business question.
Say you have a material with a 30 day RLT.
On Day 1, an order is placed - and due to no stock or planned receipt of stock with the 30 days - the delivery date is moved out 30 days based on the RLT.
Now it's day 29, you run the backorder report and there is still insufficient stock / replensihment plan within the next 30 days.
==> Do you want to keep the promised delivery date of day 30 - or is day 59 more realistic?
More to the point, why hasn't stock been acquired or a replenishment plan / order been created in the previos 29 days?
The RLT shouldbe set so that there is a very high likelyhood that the order can be fulfullled ini that time line.
To me, it makes sense to keep pushing out the date. When stock actually shows up in sufficient quantity, the date will be moved back up. -
Generating Inbound delivery based on Vendor Confirmation for Purchase order
Is there a way to create Inbound deliveries based on Vendor confirmation for a purchase order.
Here is the complete scenario.
Buyer Creates the PO for qty 100 and Date August 29
Vendor Confirms that he can supply a qty of 50 for August 29 and remaining 50 for Sep15th
Based on vendor confirmation, Buyer creates 2 vendor confirmations (AB) to match with the data received from Buyer, without modifing the PO.
Requirement:
Inbound deliveries should get created based on the vendor confirmation.
As MRP looks at Inbound delivery for Planning purposes once they are available, Inbound delivery should match with vendor confirmation data.
Is it possible to get this requirement met with standard config available in SAP.could you eventually get the answer from the docu Set Up Confirmation Control
-
Availability Check : Confirmed Date in Sales Order.
Hello Gurus,
I have an issue with the availability check.
Scenario :
Customer has created an order for quantity 800 on 26th of Feb and accordingly when created the order go confirmed for 17th of March.
The specific quanity(batch) of 800 was released from Quality to unrestricted on 27th of Feb.
And Now that the stock is in unrestrictd the customer wants to deliver this material before 29th of Feb as against the 17th of March confirmed date.
When we try to re run the availability check, since there are other open orders and deliveries against the material system proposes a new confirmed date alltogether which is still further ahead of 17th.
Can some body advice me as to how do i ensure that the particular quantity can be sold before 29th.
I have also tried running Backorder processing and Rescheduling which failed, It might also be because i might have not run them properly as i am new to the concept of backorder processing and rescheduling.
Please guide me to correct this step wise.
Thanks.please try as below:
Back order processing is a functionality in SAP where you can change the committments and over-ride the blockage of stocks marked against sales documents/deliveries. For e.g. you receive an order from a very important customer for material "A" but the entire quantity of A is committed to another customer "B" via earlier sales orders and this is where BACK ORDER processing helps you to change the committment and shift stock due for B to A. This is the benefit of this funtionality.
OMIH - Checking rule for updating backorders
OPJL - Define new checking rule
OPJJ - Define scope of check
V_RA - Backorder Processing
Data selection:-
Sold-to-party Customer code Mandatory
Sales Organization Mandatory
Distribution Channel Mandatory
Division Mandatory
Changed confirmed quantity :-
Tick the material you want to changed and click the Back order button Confirmed quantity that still can be changed are highlighted.
V.15 - Backorder List
Sales Organization Mandatory
Distribution Channel Mandatory
Division Mandatory -
Consumption of sales orders based on Sales order Doc Date
Hi Guys
I am using 40 Strategy currently. The consumption of sales orders now happens based on requirement delivery date. But my customer want to serve his customers based on first come first serve as the production is always getting delayed. Now irrespective of req. del date, the stock should be consumed based on the sales order document creation date to fulfill first come first serve concept.
I am not finding suitable requirement class in SAP. Please help
Regards
KPHi Krishna,
The scenario is quite not clear...Could you please brief it out further.
Because, in strategy 40, if a sales order comes in then sytem checks for any avaliable stock is there or not. If not then it looks for any open proposals available for PIR's, if so then it consumes the PIR based on consumption mode and period defined in material master or MRP group. If no open proposals, then system creates the new one.
So always the first come sales order will be consuming the stock or PIR, until the next MRP run.
Today a sales order has been coming in for 100 qty on 07.09.2014 delivery date and consumes the available stock of 100.
Tomorrow, another sales order has een coming in for same qty but delivery on 05.09.2014, then in next MRP run system will consume the 100 qty for 05.09.2014 and a proposal will be generated for
07.09.2014
If the business scenario is something like above, then to avoid this, a PGI job can be scheduled always as next step to MRP run so, that PGI will be done for all the sales order which has stock and rest will be in error log. By this way one production plant can ensure that always the first incoming sales order is delivered.
Also an another option would be is to run the transaction V_V2 to reschedule the sales order before delivery, this will work out if the sales order line items are not account assigned. In this reschedule transaction, priorities can be given for item date of creation as 1 and followed by delivery priority and rest....
Please check out and let us know even if you have diffrent solution as well.
Regards,
Chinna -
Tables for Confirmed Prouction orders to first operation only in routing
Hi QM/PP Gurus,
My client has this requirement, they want a list of production orders as well as their confirmation dates for their first operation in their routings. Can u provide me any tables for this one. Thanks.
Regards,
Matildo, Edsel F.
QM ConsultantHi,
Table is AFRU,
while field for Operation is VORNR
Regards,
Dhaval -
Regarding Order based confirmation
Hello friends,
Let me ask one simple question, which answer i know but confused.
In Order based confirmation for process order , what is yield? Is it the OK qty or the total produced qty (ok qty plus scrap qty).According to me its the ok qty.Now if its the ok qty than while doing the confirmation by CORK (Order based confirmation) where to give the scrap qty and rework qty?In operation based confirmation ( Enter time tickect) there is separate field for yield, scrap and rework but in order based confirmation (CORK) there is a field for yield but not for scrap and rework.
Scrap qty we can manage by considering it byproduct and in goods movement we can put (mention) the scrap qty but what abt rework qty?Where to mention the rework qty while doing the order based confirmation?
Thanking you guys in advance.i am closing the thread.
-
Sales Order confirmed date in work days
Is there a way to change configuration so a Saler Order will confirm based on the Factory Calendar??
I created a new Order Type (VOV8) but see no option to change from calendar days to work days.
Bascially, I need the sales order confirmation date to be based on work days and not calendar days.
Is this possible???Hi,
Sales Order is created for particular Sales Area i.e. SO + DC + Div. And Sales Org. is the highest org unit in SD.
At Sales Organizational level you maintain Sales Org calendar and not factory calendar.
Factory Calendar is basically used at plant level which comes under MM module.
So, by SAP std practice i dont think it will be possible..............
Or you can do one thing that is,........maintain the same sales org calendar as factory calendar..........so i think it will help you....
But can you elaborate you point so that we can understand properly.............
regards,
Sagar -
Table name& field name for production order & operation confirmation
Hi All,
I would like to know the table name and field name for the production order "confirmation" (CNF) and the operation confirmation (CNF).
Thanks and Regards,
PSSHi there,
CORU(R/3 Application development: PP Confirmations )
AFFW Goods movements with errors from confirmatio
AFRC Table of planned changes to conf.: Automatic
AFRD Default values for collective confirmation
AFRH Header information for confirmation pool
AFRP1 Table of planned changes to conf.: Automatic
AFRP2 Table of planned changes for confirmation: B
AFRP3 Table of planned changes for confirmation: C
AFRP4 Table of planned changes to confirmatn: Data
AFRU Order completion confirmations
AFWI Subsequently posted goods movements for conf
TAFWD CORU: Messages that are not interpreted as e
TCORD Table for field-dependent check routines
TCORU Parameters for order confirmations
TCORV Table with Routines for structureing variabl
TCORW Confirmation: Window Control
TPARU Control parallelized confirmation processes
TPRRU Control table for process chain for confirma
TPRRUT Text table for process control of confirmati
TRUGS User status caused by deviation
CO(R/3 Application development: PP Production orders )
AFBP CIM order: Batch print requests
AFFL Work order sequence
AFKO Order header data PP orders
AFPO Order item
AFVC Operation within an order
AFVU DB structure of the user fields of the opera
AFVV DB structure of the quantities/dates/values
FAPW Index of production-/issuing plant for produ
FTIND Missing parts index
ORDCOM Communication control Operation download
T024F Production scheduler
T399X Parameters dependent on order type
T441C Profile - availability check
T441CT Texts for Profile "Display Availability Chec
T490 Transactions PP - orders - order category
T496B CIM order: Assigning document types to refer
T496D CIM: Destination/lists/spool parameters per
T496F CIM order: Form description of the list
T496K CIM order: Entity table of possible table id
T496N CIM order: List descriptions
T496P Print PP documents: Determination of output
T496R Print PP shop papers: Report control
T496T Print PP shop papers: Transaction control
T496V PP Print: Default Value for Printing Online
T496Z CIM order: Table-controlled table access
TC32 Assigning subscreen to processing location
TC34 Allocating operation to object type for the
TC62 Sequence of detail screens when processing h
TCO01 Sequence/operations control in logicstics or
TCO03 CIM order: Texts for TCO01, Description of o
TCO04 Table for controlling the screen sequence gr
TCO05 CUA status depending on panel, trans. type,
TCO06 Exclusive functions for PP orders
TCO09 CIM order: Text IDs of objects in orders
TCO10 Valuation variant for order costing
TCO11 Control table for production orders - availa
TCO12 Control table production orders - stock dete
TCO36 PP orders: Control table for calling up pop-
TCO41 CIM order: Default values for generating ope
TCO43 PP-SFC order profile
TCO43T Description of production scheduler profile
TCO60 Sequence keys for input facility and verific
TCO61 Sequence key for PP orders
TCO62 Defining screen sequences for input facility
TCO63 Sequence of detail screens when maintaining
TCODB Database fields development class CO per ord
TCOF Profile for missing parts info system
TCOFF Profile for Missing Parts Info System: Displ
TCOFFT Texts for Missing Parts Info System: Display
TCOFG Profile for missing parts info system: crite
TCOFGT Texts for Missing Parts Info System: Criteri
TCOFK Texts for functions in milestones/trigger po
TCOFS Profile for Missing Parts Info System: Sort
TCOFST Texts for Missing Parts Info System: Sort Cr
TCOFT Texts for Missing Parts Info System
TCOKO Constants for PP orders
TCOKT Account assignment categories for order
TCOP Field selection profile
TCOPS Field selection profile
TCOPT Description of Profile for Field Selection
TDUMMY Dummy structure of a table for READ with VER
TRUG Reason for variances in completion confirmat
TRUGT Text describing the reason for a variance in
TXPR1 XPRA control - missing parts info system
Regards
Hemant G
Maybe you are looking for
-
Just bought a macbook, how do I install Lion on my old iMac?
Macbook doesn't come with any OS CDs, and I want to upgrade my iMac. I don't want to have to buy Lion again, since I already have it on my macbook. How do I get Lion on my iMac (along with iLife '11)?
-
How to set up attachments on mac mail
When i attach a document in my email the whole document appears in the body of the email not as an icon at the bottom
-
How to control two different processes with one DAQ output board
Hi! I posted this in the Signal Generators forum, but I'm reposting here in case someone on this board has suggestions for a way to get around my problem programmatically (ie. within LabVIEW). Thank you for any help you can provide. Patrick I have a
-
I used to access the on line docs frequently, but recently I can not and message given the "Sorry, this page was not found. (ErrorDocument 404)". How can I read the docs ? Thank you in advance.
-
Beep sound at the start of G570 laptop
From last 2\3 day my laptop start making a constant beep sound during booting. At the start up there is no problem with Bios and I am able to change the options, but when I save&exit and system starting booting it make beep sound. I have both ubuntu&