Rescheduling planned order

Hi All
I have material A and B is child of A
Also C is child of B
I have customer requirement for material A on 17/02/2010
When MRP is created then it has created planned order for B with requirement date as 27/01/2010
And for C with requirement date as 8/01/2010
When I changed requirement date of B manually in planned order as 07/01/2010 then it has given order start date as 15/12 /09.
This will be requirement date of C.
When i do MRP planned order requirement date of planned order of C does not get changed to 15/ 12/ 09 but remains as 08/01/10

Hi,
2 things:
1. Can you let us know if the planned order for C is firmed ?
2. What is the need date coming from B for material in C in MD04?
Regards,
Vivek

Similar Messages

  • Can't dispatch planned order (LA), but can dispatch production order

    Hello,
       I'm new to capacity planning and all of the related configuration screens.  I'm probably missing something simple.  We've configured our work centers and routings.  We've configured our production order types (tcode OPU3, type US01) and planned order types (tcode OPU5, type LA) so that all create capacity requirements and are relevant to 'detailed scheduling'.  Requirements are being generated for production orders and planned orders.  We can see correct setup and production times in the graphical planning table CM21.
       Here's the problem: When we try to dispatch a planned order, nothing happens.  There is no error, but the order is not dispatched.  If we convert the planned order into a production order, accepting all SAP proposed defaults, and then try to dispatch the production order, it works fine.
       What configuration are we missing?  My first thought was to look in OPU5 for order type LA.  In the detailed scheduling section, scheduling horizon is zero (is this Ok?), SelID: Detailed is 01, 'scheduled' and 'generate capacity reqs' are checked.
    Thanks,
    Randy

    Randy ,
    Please analyse the below note related to your issue.Hope this will help you to sort out the problem.I have cheked the configuration area.I hope u are correct .In fact , it may related to your production version if you do automatic dipatch.Please reade the note and come back.
    If an error arises when automatically dispatching planned orders (for example, a capacity overload at a work center) then the system schedules the affected planned orders to another production line.This function is available in both types of planning table. It is of interest for all areas that use planned orders, for example in repetitive manufacturing or in MRP/MPS. It can also be used in production control when later converting planned orders to production orders.
    this function the following conditions must be met:
    The dispatching function Change production version on error must be set in the strategy profile.
    The original work center
    must be entered in the production version of the material as the production line (not necessarily in the current production version).
    can only be assigned to one operation in the routing for this production version
    The alternative work center can only be assigned to one operation in the routing for the alternative production version
    If an error arises the system copies the production version with the version key that is next alphanumerically into the planned order. The planned order is rescheduled with this production version. However, it is not dispatched to the new production line but remains in the pool. In this way you can dispatch the rescheduled planned orders together with other planned orders in the pool to the new production line.
    To give you a better overview and to improve handling you should choose a sort key with which the planned orders in the pool are sorted according to work center and, for example, latest start date. All orders that are to be dispatched to a production line are then placed next to one another in the pool. If an error arises during automatic dispatching to the new line every planned order affected is rescheduled with the next production version
    . If the conditions are not met then the following occurs depending on your settings in the strategy profile:
    Dispatching is terminated
    Dispatching to the same work center is continued and error messages are written to the planning log
    You can only dispatch main operations with this function, but not sub-operations. Operations are always dispatched with the full quantity to the new work center
    Reward point if useful
    Regards
    Jia

  • What is equivalent ASCP report for Planned Order&Order Reschedule Report

    What is equivalent report for Supply Chain Planned Order Report & Supply Chain Order Reschedule Report
    We are currently on MRP and running Supply Chain Planned Order Report successfully. We are planning to go to ASCP(Decentralized) next month ,what is the equivalent reports in ASCP?
    Edited by: SanDan on Jan 9, 2013 1:57 PM

    Hi ,
    You can explore the Planning Detail Report which you can run against your ascp plan. However there are few standard reports available in ascp. I suggest you can explore option of building custom report which will be best suited to your business needs (i.e. using Discoverer or if you are also implementing obiee you can build a custom report based on standard views or noitex views (- for ascp)
    Regards
    narendra

  • MRP not rescheduling the planned order by itself

    Hi,
    After MRP i could see that the planned order is not present as per the date of the requriement whereas the planned order at a future date is given a Exception message 30 : Plan accordingly to schedule and proposed the date of the requirement. The requirement is beyound the replenishement lead time and hence MRP should reschedule by itself the planned order as per the date of the requirement rather than giving a exception message as above for a future dated planned order.
    I am not sure what is it i am missing. Could you explain.
    Thank you

    Dear ,
    MRP will re schedule the planned order based couple of inputs and checks during MRP run .Basically , it depends on following
    In MRP exectuion you should  keep : Procesisng Indicator : NETPL: The system only plans materials that have undergone a change that is relevant to the planning run within the period which you defined as the planning horizon. The system sets the net change planning horizon indicator automatically for these materials 
    Planning Mode : 3-Delete and Re-create Planning
    It also depend on following set up  and you need to analysie that :
    1.Planning Time Fence : based on the PTF , there will not be any automatic changes relevent for MRP
    2.MRP Type : PD , it will adoped normal planning and it will not re-schedule order proposal automatically  .In you case  can use P1-Automatic Firming and Re-schedule Out Of Order Proposal based planning time Fence
    3.Keep your Planning Horzon more than the Highest Material Lead Time in Material Master MRP2 View
    Please check and revert
    Regards
    JH

  • How to reschedule multiple planned orders ?

    Hello guys..
    The rescheduling can be done manually via transaction MDAC/ report SAPMM61P.
    MDAC gathers all parameters necessary for function module MD_SET_ACTION_PLAF. In MDAC only one planned order can be schedule.
    I want to create the report in which, the planned order number should be replaced with selection criteria for multiple planned orders. The other fields should be the same as in transaction MDAC.

    hi,
    there are two ways of doing it but both needs technical person's help:
    1. switch off back ward scheduling - find out the program which is triggering back ward scheduling and make it inactive.
    2. write a code in MV45AFZZ, SDTRM001 stating that when ever system is proposing back date at that point of time it should trigger todays date as Material Availbility Date.
    then no need to change manually to todays date.
    hope this should help you.
    please check the same with ABAPER and update the forum
    regards,
    balajia

  • Planned order Vs.Purchase order

    Hi,
    can you tell me major differences between a planned order and  a purchse order.

    Hi,
    Planned Order : Planned Order is generated by the planning logic, or arithmetical procedures, of the system itself with MRP set. When MRP is re-run after the closed-loop transactions are fed back into the system, all existing planned orders are deleted and a new set is generated. However, the newly generated planned orders may be identical to the previous set in timing and quantity, so that it will appear to the system user as if the old plans have simply been somewhat revised. The use always of planned orders in closed-loop MRP ensures that plans are always in synchronisation and that the planner does not need to concern himself with rescheduling messages.
    Purchase Order: The purchase order is a formal company document which conveys the instructions or detail of a required supply. The legal role of the purchase order in forming the contract of supply will vary with circumstances: most usually, it will be an offer, such that the supplier's acceptance of it at the price mentioned seals the contract, but it might alternatively be the acceptance of an offer (say, an order placed immediately against the supplier's tender.) The document itself may also be used by the company simply to convey detail, perhaps being a call-off for material against a yearly contract already in existence. The purchase order might convey a summary of substantial material to be delivered at various times in the future by special order forms.
    For more follow the link:
    http://www.xtuple.com/docs/userguide/ch03s09s03.php
    Regards,
    Biju K

  • Collective Planned orders Scheduling for lower level orders with reference to the Superior order

    Hi All,
    Collective planned order scheduling.
    I have been trying to reschedule the superior planned order and i was expecting the lower level planned orders to reschedule based on the superior planned order.
    My problem is
    when i try to reschedule the superior planned order the system is not rescheduling the lower level planned orders.
    For example if i change the basic finish date of superior planned order as 30/09/2014 and reschedule the planned order it is only scheduling the header planned order and the lower level planned order is not scheduling.
    Could some one tell me why this is not happenning at planned order level.
    As the rescheduling of collective order will work at production order level but for some reason it is not happening at planned order level(as there is no option available to do so).
    Please give your thoughts on this asap.
    Mahee.

    Hello Mahee
    Please observe that your system is working as designed. Planned orders are scheduled independently, even when they are part of a network/collective order. Note 152319 explains the planned order scheduling in detail and it provides the following information:
    * No scheduling of overall networks is executed although a directly manufactured component is assigned.
    Note that no scheduling of the overall network is executed for planned orders. For the components requirements dates are determined. In order to cover them, planned orders are created in the next MRP run. Since the requirements are not managed using the exact time, the results of the planned order scheduling and of a scheduling of the overall network of the converted collective order can differ.
    BR
    Caetano

  • Duplicate planned order is generated with  one sales order item.

    dear :
    when the production order is confirmed with sales order item.the other new planned order is generated.
    the   requiremet quantity of sales order item  is  1,but the custstock  is 2 .display exception:26. in md04.
    please help me analyze it .
    best regards.

    Hi
    Please check rescheduling horizon in OPPQ(by default it would be 100).
    May be you would have shifted the dates of production order after converting from planned order which had crossed rescheduled horizon. This would generate additional planned order to maintain initial dates.
    If this is the case, increase Rescheduling horizon.
    Regards,
    Krishna Mohan

  • Exception message during planned order creation

    I am coming across a situation wherein am creating a planned order for Semi-fininsh good, but the problem is that am getting an exception msg "15" against the planned order created whihc states that "Reschedule out". Can somebody tell me the significance of this message, when am reviewing the overview tree for that order am not  seeing any message for the downlevel components. Expecting a positive response.
    Regards,
    J K Tharwani

    Hi Jitendra
    Logic behin EM 15
    It means to postpone the operation i.e. reschedule out the process if the receipts lies before my requirement.
    Rescheduling horizon is also linked to it. Check in OPPQ
    It defines the period for bringing the reciepts inwards i.e. prepone the receipts which are required to be considered for rescheduling.
    If your receipts come before your requirements system will give this EM 15.
    Opposite to above is EM 10 i.e. if receipts lie after your requirements
    Go the dates of your planned orders and compare it with your receipt date. U will get idea
    Rgds
    Edited by: Vicky Khabrani on Mar 5, 2008 7:38 AM

  • Planned order splitting during capacity planning

    Hello,
    anybody plese help me during the capacity planning in T.code.CM31 i want to split a planned order and want to assign alternative sequence. how can i do this and the capacity should be reschedule automatically to my requirement date. i am using backward scheduling.
    plese suggest immediately
    Thanks and reagards
    Bhakta

    Dear Bhakta
    MRP does not perfom any Capacity Requirement Planning .While  you are executing MRP with Lead Time Scheduling , MRP proposes Planned Order Dates based on the Routing Operation Timing not based on the Work Centre available Capacity because in SAP Std R/3 we did not have scope to check the finite scheduling and capacity requirement chek .MRP assume that Work Centre has infinite available capacity .
    In MRP run , it will give you Detail scheduling of the Operation in Planned Order -Detail Scheduling tab  and copied the routing , BOM as master data .When you convert that Planned order to Production order , it will copy the Routing details based on the Order Type denpendt Parameters -OPL8-Routing -Alternative sequnce  and Automatic selection -3 option
    Thats why we have Capacity Requirement Planning  for Detail Capcity check and production order scheduling  .
    Note : Earlier to my first  reply , please note that you have option in CM21  enter sequence number  at order level which may applicable to you .CM21-Work Centre -exectute -Select the Order from order pool -Goto Order -Sequence number maintainence
    This number( sequence number operation /order )  that can be assigned to production orders or planned orders at the level of the task list header and is therefore valid for all the operations in an order.
    Hope this is clear .Revert if you nees farther help
    Regards
    JH
    Edited by: Jiaul Haque on Jul 5, 2010 3:32 PM
    Edited by: Jiaul Haque on Jul 5, 2010 4:01 PM

  • Planned order scheduling in mrp

    hi
    iam trying to run MRP at my client place
    facing problem in planned order dates
    i choosen  tequirement type BSF and strategy group as 11
      in md 61 pir was given in a month of june2008(monthly)
    after mrp run at modo4 iam getting planned order with
    execption message 64 called order date in past
    means iam getting planned order START DATE AND END DATE IN THE MONTH OF JUNE
    where as i need to  my planned order satar date in MAY MONTH and
    end date must be 1st of june
    means i given PIR which is my start of my june month
    checked scheduling parameters which  says backword scheduling, and i choosed planning mode 3 and leddtime scheduling
    plz suggest which setting effects the planned order start and end dates??
    regards
    sasikanth

    hi
    i selected schedule margine key with 0 flots (key000)
    and chossed *LEED TIME SCHEDULING (in mrp controll parameters :-scheduling 2 at MD02 )
    how the reduction strategy helps in this case ,casue i am doing lead time scheduling system has to consider only routing time ??? right ??
    plz suggest how to  arrest message 64
    regards
    sasikanth 
    message 64 diagnosis enclosed
    64: Production finish after order finish                                                                  (P4)
    Message no. MD427
    Diagnosis
    The production finish date calculated using the routing lies after the order finish date that was calculated using the in-house processing time in the material master record.
    As the system uses the order finish date in the planning run, this situation may lead to material shortages if production is not finished until the production finish date calculated by the system.
    System Response
    This exception is displayed in the MRP list and in the current stock/requirements list.
    Procedure
    Check the times in the material master record and in the routing.
    Check whether the order has to be rescheduled in.

  • Release Rejected - Message no. C2039 during Planned Order Conversion

    Dear Experts,
    I was trying to convert a Planned order to Process Order via COR7, and it prompted the following message,
    Release rejected (check log) - message no C2039.
    But when I create Process Order manually via COR1 for the same material master and release, it works.
    Does anyone got any idea?
    regards,
    Abraham

    Hi,
    1. Check the Storage Location for the components in BOM & Check the availability of stock for the Missing Parts in Header.
    2. Check the reservation for the "Missing Component's".
    3. Reschedule the Planned order in MD12 before conversion.
    4. Also check whether "Serial no.Profile" is activated in Material Master , if yes please go to CO02- Header->Serail Nos-> Create Serial No (Either Manually or Automatically). Then release the Order.
    Hope it helps.
    Regards,
    Sundhu

  • Firmed planned order creates a type of firmed horizon

    Hi Gurus,
    we had following system behavior the other day (actually a few months ago) that we weren't able to explain.
    It was beginning of November and a colleague of mine was creating his production schedule for the week before x-mas (i.e. another 7 weeks in the future). He was working at it and was called away for something and postponed the planning to another day in the week. The next morning he noticed that the MRP considered everything between today (must have been around the 5th of November) up until the 18th of December (the day he had firmed the planned order to) as a firmed horizon and didn't want to put any planned order inside.
    Even worse... all planned orders created by the MRP - now scheduled for after the 18th - had an exception message to schedule them in, as they came too late.
    Did anybody ever experience this behavior? If yes, please let me know, where I can manipulate this!
    Any help greatly appreciated!
    Thanks & regards,
    Bobby

    Hi Rupesh,
    first of all: thanks for joining!
    here are the answers to your questions:
    1.) lot-size = EX (i.e. not periodic)
    2.) no overlaps defined for EX in OMI4
    3.) no time fence and the rescheduling horizon is set to 100 days
    Looking at the rescheduling horizon and what is described in the OSS-note, I think I found it. The system actually works as designed. What we failed to do was to update the factory calendar with the downtime over x-mas back then. If we had done so, the demand would have been pulled forward, which means that the firmed order would have been consumed, instead the demand was distributed over the following for weeks.
    With the rescheduling horizon being so long, the system used the firmed order to cover all up-coming demands first using the firmed order before the MRP created other planned orders. It just happened that this one order was so big that it covered everything until then and that it looked like a "firm period".
    Thx for your help!
    Points will be awarded for pointing in the right direction...
    Regards,
    Bobby

  • MD02 generates another planned order

    Hi everybody, plese help me.
    Why if I have in the system a firmed planned order covering all clients requirements, the transaction MD02 generates another?
    For example (The MD04 transaction before run MD02 looks like):
    15.01.10  Stock                                            0
    15.01.10  CusOrd                47-                 47-
    15.01.10  CusOrd              100-                147-
    15.01.10  Planned Ord*      147                    0
    The MD04 transaction after running MD02 looks like:
    15.01.10  Stock                                            0
    15.01.10  CusOrd                47-                 47-
    15.01.10  CusOrd              100-                147-
    15.01.10  Planned Ord*      147                    0
    15.01.10  Planned Ord        147                 147
    I'm not sure why if the first planned order cover all clients requirements, the system make another proposal.
    Thank you
    Edited by: Donald Tatún on Jan 15, 2010 11:41 PM

    Hi Donald,
    1) Please check OSS note 25388 and connecting notes. Isn't it possible that your firmed PldOrd is after the requirement and rescheduling horizon?
    2) Isn't there any modification (user exit, BADI) in use in your system?
    (what are your settings in config, master data, etc?)
    Regards,
    Csaba
    Edited by: Csaba Szommer on Jan 16, 2010 9:49 PM

  • What parameters determine Planned order production start and end dates?

    Greetings
    We are using the graphical planning table @ MF50 to firm Planned Orders (Basically checking off "Firm Order" field within the Planned Order). We are on ECC 6.0
    Whenever I backflush, the production start and end dates get overwritten (The Basic dates do not change).
    I would like to prevent this. Can someone advise me on what parameter controls how the production start and end dates getting changed?
    Thank you
    Hanarin

    Hi,
    Calculating production dates ( Lead time scheduling) are explained in detail in the SAP help URL as below:
    If "Automatci Scheduling indicator" is set in the customizing for scheduling parameters then after every change relevant to scheduling, the production order is also automatically rescheduled before saving.
    You need to check these settings.
    regards
    Datta

Maybe you are looking for