Return delivery while using a service entry sheet

Hi all,
We have created a purchase order related to a service entry sheet. This purchase order is completely confirmed (MIGO, movement type 101).
When we try to create a return delivery (MIGO, movement type 102) we get the following message: Purchase order had no items.
Does anybody know how's it's possible we can't create an GR for PO reversal?
We are on SAP ECC 6.0.
Best regards,
Tim van Thiel

Hi,
Thanks for your fast reply.
We created this PO with item catagory D (services). Then we confirmed the goods (MIGO - movement type 101)
Afther this confirmation we got an extra line under Purchase Order History (ME23N) with the service entry.
Best regards,
Tim

Similar Messages

  • What is the use of service entry sheet in plant maintenance module.

    Hi Expert,
    I want know about, What is the use of service entry sheet in plant maintenance?
    Regards,
    Ram Rathode

    Hi dear,
    Service entry sheet concept is used in all the modules.
    Service entry sheet is created to do the service confirmation and to pay the vendor for the services which he has performed.
    Based on the service entry sheet invoice is booked by Finance.

  • Settings for 101 movement while accepting the service entry sheet

    Hi All,
             Please let me know the settings required to do a 101 movement in the background when a service entry sheet is getting accepted using ML81N.
    Regards,
    Ashwin

    Hi
    The PO is always account assigned for service PO.
    Hence when you accept service entery sheet the system do GR for account assigned PO i.e.
    Debit - KBX for account assignment
    Credit _ WRX GR/IR account
    You can check it in OMJJ under update control from left pan for movement type 101 and GR for account assigned

  • ERROR WHILE DOING THE SERVICE ENTRY SHEET

    Hi All,
    I have budget INR 3000 & i created PR INR 2500 ,PO for the same amount INR 2500.Against the same i made INR 2000 down payment and it would as statistical in SAP. But while doing the service entry for same PO ,budget exceeded error coming.
    I seen Program RFFMS009 program also all DP figures updated as statistical ,but while clearing the DP through F-54 system getting budget exceeded error message.
    Kindly help me .we are in 4.7
    Former budgeting
    Rgds
    Manisuma

    Hi All,
    There is problem in Field status varaint
    Rgds
    Suma

  • Error while creating the service entry sheet in PRD

    Hi All,
    We are in SAP R/3 4.7 Version. OF39 settings are 58 & 61 Statistical update only ! Now my case is i assigned Rs.100 Budget agaisnt one FC & Comitmetn item & created one service Purchase order Rs.80 & Make down payment against same PO Rs.80.
    Now as per above mentioned scenario ,system should allow new Purchase order creation for Rs. 20. But my system is allowing to create up to Rs.100. I am very much sure system not allowed the same and also allow for service entry creation for first PO. But system given error message while doing the Service sheet.
    Kindly advice. OF39 settings are OK .Both are statistical only
    Rgds
    ManiSuma

    Hi Manisuma, statistical update is recommended to be used only at the begining of a document chain (i.e.purchase requisition or funds reservation) cause if you set it in intermediate documents as you did the budget is set as available, in your example the downpayment reduces the purchase order commitment, and as the downpayment is statistical it does not affect the Availability Control, so the amount (80 in your example) becomes available again so new commitments/actual can be created.
    Regards
    Cesar

  • Duplication of Inv. while miro for service entry sheet

    I hve made the setting at duplicate check inv. for incoming excise inv.......... irrespective of date........
    so....... while inv. verification it will give the error for duplicate inv. if entered the same inv. twice...... if we give any date of any financial error for the same invoice it will show error..........
    And our client requirement is dat if the same inv. no. occurs in different financial year......it should not throw the error..........
    So,
    Plz. guide me so how can we can make the above settings for check of duplicate inv. for the particular financial year......
    Rgds,
    navin

    Hi,
    Go to  XK02 and enter the vendor  no.
    In the accounting data tick the duplicate inv check
    and do the MIRO. It will not accept.
    Duplicate invoice check is done at vendor level only  and not
    at PLANT LEVEL
    G.Ganesh Kumar

  • Exit while releaseing Service Entry Sheet ML81N or event

    Hi,
    Any exits/ events while releasing a Service Entry sheet?
    Thanks,
    Krishna.

    hi,
    Check the User Exits for ML81N
    Exit Name           Description
    INTERFAC            Interface for data transfer
    SRVDET              User screen on tab strip of service detail screen
    SRVEDIT             Service list control (maintenance/display)
    SRVENTRY            Unplanned part of entry sheet (obsolete since Rel. 3.1G)
    SRVESI              Data conversion entry sheet interface
    SRVESKN             Set account assignment in service line
    SRVESLL             Service line checks
    SRVESSR             Set entry sheet header data
    SRVEUSCR            User screen on entry sheet tabstrip
    SRVKNTTP            Setting the account assgnmt category when reading in, if "U"
    SRVLIMIT            Limit check
    SRVMAIL1            Processing of mail before generation of sheet
    SRVMSTLV            Conversion of data during importing of standard service cat.
    SRVPOWEB            Purchase order for service entry in Web
    SRVQUOT             Service export/import for inquiry/quotations
    SRVREL              Changes to comm. structure for release of entry sheet
    SRVSEL              Service selection from non-SAP systems
    SRV_FRM             SRV: Formula calculation (obsolete since 4.0A!)

  • Service entry sheet (urgent)

    dear all,
    i made an PO for service PO with unit of measure AU qty. 1 but in the service tab i added one service with quantity of 1000 with price 1 usd and unit of measure is TO.
    10 K D     HANDLING & TRANSPORT OF IRON ORE FINES 1 AU D 02.12.2008 1000 USD 1 AU TR04 2100
    then while doing the service entry sheet system throwing me the following error.
    PU Ordered quantity exceeded by 1 AU : 2100
    Message no. M7022
    Diagnosis
    The specified stock level or quantity is exceeded by 1 AU.
    System Response
    If the message is an error message (E), the above is not allowed.
    If the message is a warning message (W), the system will allow your input, but the warning is intended to prevent you entering a wrong quantity.
    Procedure
    In the case of a warning message, check the quantity entered.
    In the case of an error message, change the quantity or terminate processing.
    Note:
    The abbreviations in the short text of this message can have the following values:
    BA = batch
    OR = order
    PL = plant
    PR = previous period
    PU = purchasing document
    RE = reservation
    SL = storage location
    VC = consignment stock from vendor in storage location
    but when i check unlimited in over delivery tolerance then system is allowing me to do SES. and completing the process fully but i dont want to give check of unlimited tolerance.
    can any body help me for this issue.
    regards,
    qsm sap
    Edited by: qsm sap on Dec 3, 2008 6:04 AM
    Edited by: qsm sap on Dec 3, 2008 7:59 AM
    Edited by: qsm sap on Dec 3, 2008 8:23 AM
    Edited by: qsm sap on Dec 3, 2008 11:58 AM

    i think You would get this error when there are multiple Service entries, but you have not flagged the Unlimited Flag under the Limits Tab in ITem Details.
    plz check the delivery tolerance
    http://www.helpinfo.com/index.jsp?k2dockey=1021028680438086807&formwassubmitted=true
    plz dont use words like U rgent as it block us to post
    regards
    kunal

  • To make service entry sheet for multiple line items of the service PO.

    Hello MM Gurus,
    Please help me for the following
    I create a service PO with say 10 line items. Then while doing the service entry sheet the system automatically picks the line item 10 by default. When I try to enter the other items it throws an error" unplanned services cannot be entered"
    So how to make a service entry sheet which shall include all the line items of the service PO at the same time.
    So if I have 100 items in the PO do we make the service entry sheet 100 times against each item? Is there any seeting/solution on this?
    Please help.
    Regards,
    Prasanna.

    Dear,
    I have two solution for u.
    1) Create different service entry sheet -ML81N for each line item and create single invoice verification for all service entry sheet - MIRO
    2) Create service purchase order - ME21N for only one line item.
    And include all services in service tab available at item detail level of service purchase order. Enter it's quantity and rate.
    Than create one service entry sheet for purchase order.
    So you can create one service entry sheet for all line item of services.
    Note: - Use option 2 for easy process.
    Regards,
    Mahesh Wagh.

  • Service Entry Sheet Deletion

    Hello Friends,
    My client is facing a problem while creating a service entry sheet for a PO. In the PO history it is showing a service entry sheet(SES) is created for a line item. But that SES has been revoked and deleted also. But the concern is although the SES is deleted, total values (Amt in LC) is still showing in the PO history. The value is not being changing to zero in PO history.
    When user is attempting to make another SES for that line item, as the PO is open now, an error messege displaying which says the entered quantity exceeds the PO quantity. Messege No - SE363.
    When i am trying to do the same scenario in development, system is working fine, i am not getting that error. I am able to make futher Service Entry Sheet.
    It will be great help if anyone can give me some feedback on this at the earliest.

    Dear Frnd,..
    This is a std system bug. Which is not reproducable.
    Please use SAP note - 126285.
    Whice will provide you with Report RMBESTK2.
    with following coding. create a report with this coding and assign a T-Code to it. And use it when you face such an issue in future.
    Amit P hiran
    Njoy SAP...
    Njjoy Lyf...
    Edited by: Amit P Hiran on Jun 21, 2010 4:59 PM

  • Service PO and Service Entry Sheet / MIRO

    *Dear SAP Gurus
    We have created Service PO - Repairing of  AC Machine.    and Service Tab we maintained 10 line items of Parts Qty with Rate.
    and we maintained Local Frieght  Charges in Header Condition.     upto This stage ALL OKey.
    while making MIRO / Service Entry Sheet.   the Local Fridht charges calulating on no of Line Items.
    Example ;  Local Frieght   :  10000/-     no of line item  10   then showing  10000 x 10 = 10,0000/-   
    how it will be solved.  please  guide me...      
    NOTE :  NOT ONLY LOCAL FRIEGHT   IF I PUT  OCTORI   IT ALSO SAME HAPPENING.
    PLEASE  AWAITING FOR YOUR HELP
    REGARDS,
    *RAJESH **

    Hi Rajesh,
    Your question is not clear, if you can explain the requirement little more clearly.
    Delivery costs are generally not supported in external services
    management and in case of blanket purchase orders, item category D or B.
    Instead of representing delivery costs via conditions, in case of
    service documents, freight costs and other, SAP recommends to add in
    additional service lines. Check the OSS Note: 381030 and Note 499575
    There is no problem to post
    invoice for different vendor for particular SES created for service
    line that constitutes delivery costs.
    Cheers
    Kris

  • Service Entry Sheet Create Creation

    HI all,
    While creating & accepting Service entry sheet using ML81N T- Code we are getting the below error massage.
    <u>Account Assignment 01,ErrorM7 Message 022
    "Error message M7022PU quantity exceded by 1AU "
    Higly appreciate your solution at the earliest.
    Thanks in advance.
    KC pani

    Hi,
    Please ensure the field for overdelivery tolerance ( EKPO-UEBTK ) in the item detail is not set to ' unlimited '.
    This field must always be set to 'unlimited ' for purchase orders for external services.
    The reason for this is that services are always managed with the unit of measure 1 SU on item level, that is, if this 'unlimited' flag is not set on item level, only one service entry sheet can be created. For the second, the above message is then displayed as the quantity 1 SU is now exceeded.
    Please check and confirm.
    Regards,
    DilL

  • Service entry sheet pick price from Scales based contract

    Dear SAP Team,
    We are doing the service entry sheet using Transaction Ml81N & facing the pricing issue.
    Before doing the service entry sheet a SAP contact which has prices based on the scales as distance is created .We pay the vendor based on the depth where the drilling operation are performed.
    Purchase order is created using as limit order as at the time of PO the exact depth & time consumed for the service is not clear.
    While creating a Service entry sheet against the PO, when I click on the pushbutton u2018Service selectionu2019 the system prompts me to choose the Service from different sources.
    I select the option of service to be selected from the purchasing document (which is my contract number with scale pricing).
    After this step, I could see my contract service as below but I do not have the option to select the scale prices based on the depth where the services are performed.
    I do not know when SAP has provided the scale pricing in contract & it allows you to select the contract during the service entry sheet then but it does not allow you to select the prices maintained in the contract for the scales. I would highly appreciate any solution provided on it or any other alternative possible.

    Hi,
    You have two options, just check for to carry out....
    OPTION--1:
    You can create three service master/activity number namely Pumping depth 0-500 M , Pumping depth 501 -1000 M & Pumping depth 1001-Above and keep  base unit of measure for service master/activity number  is Hour.
    Now create value or quantity contract as per your requirement with  three service master/activity number  & you can maintain
    the cost per unit as Pumping depth 0-500 M is 400$/ Hr , Pumping depth 501 -1000 M is 500$/ Hr, Pumping depth 1001-Above is 600$/ Hr
    Then you can create Release Order/Purchase Order WRT contract.
    Now during SES creation in ML81N, you can select which activity number performed and accordingly the cost and service number copied to SES & you can save SES and release SES.
    OPTION--2:
    You can have source list(ME01) & Info record (ME11). In the info record , you can maintain all scales as your requirement
    and then create contract & then release order and finally SES.
    Regards,
    Biju K

  • URGENT VERY URGENT---------Error in Service Entry Sheet-ML81N

    Dear Experts,
    I am getting a Error msg while creating a Service Entry Sheet by ML81N. It says that " You cannot enter an Unplanned Order". wht to do pls help
    Its urgent
    Thnx
    Sankha.

    yes u have to make the serv entry sheet with rspt to Serv. P.O just go to ML81N here click on create icon, a small box opens here give the p.o no & click on continue.here give all necessary details like desc, valid dates , serv, location, etc then click on serv. sel tab which is at below then all line item which r in Serv. p.o will be picked up.
    Hope this can help
    Reward if useful,
    KM

  • Vendor Evaluation TAb in Service Entry Sheet (ML81N)

    Hi,
    While creating a service entry sheet, we have a tab named 'Vendor Evaluation".
    In that tab there are two fields.
    We want  to add more fields there.
    Is it possible?
    Regards,

    Hi,
    Please review the note 79166 which explains that you can setup 2                
    sub criteria one with 'C' and one with 'D' using the standard criteria          
    04 'service'.                                                                               
    Now, if you need more than 2 sub-criteria, you will have to use a user          
    exit to use your own sub-criteria and calculation.                              
    Please have a look to note 45748 for more detail of the user exit for           
    vendor evaluation.                                                                               
    Run transaction SMOD , enter enhancement MM06L001 . Then you can see            
    three functional modules:                                                                               
    - ATTRIBUTES                                                                    
      Extension          MM06L001                                                   
      Short text         Exits to determine ratings in vendor evaluation                                                                               
    - COMPONENTS                                                                    
      Function module                ShortTxt                                       
      EXIT_RM06LBAT_001 used for the quality criteria if the vendor                 
                        evaluation is carried out in the background                                                                               
    EXIT_RM06LBEW_001 used for the quality criteria when the scores for           
                        semi-automatic and automatic subcriteria are                
                        determined                                                                               
    EXIT_SAPLMEL0_001 used for the general criteria                               
    The following data is passed on to the function modules:                                                                               
    XLIFNR  (Vendor number)                                                               
    XEKORG  (Purchasing organization)                                                     
    XHKRIT  (Main criterion)                                                              
    XTKRIT  (Subcriterion)                                                                
    XKRTYP  (Scoring method)                                                                               
    The function modules then supply the scores in the parameter XBEURT.                                                                               
    Regards,  