Settlement of Partial deliveries of process orders

Is it possible to do a monthly settlement on a process order that spans multiple months? (Without calculating Work in Process)

Hi,
If the process order is a cost collector then it will calculate the WIP if qty is not exausted or TECO status is not updated.
When you settle the process order it will transfer the variances  and stock to Accounts.
If you want to settle the process order without WIP then you need to update that with Tech completed and then settle on monthly basis. This can be a work arround but not recommended.
This may help
Regards
Shantanu

Similar Messages

  • Report on settlement profile/rule for the Process Orders ?

    Is there any report which will display settlement profile for process order or settlement rule for process order.

    Hi,
    Did you try this one: KOSRLIST_OR - Settlement Rules?
    Regards,
    Eli

  • Settlement of the month end process order KKS1 & C088

    Hello all ,
    we are trying to settle the variance & upadte WIP for the month end but facing some  problems.
    When try to Run KKS1 getting the errors for some ordera as
    Only remaining var. in version 0 - no target costs for 000001003928.
    Should we just ignore these errors & proceed with the settlement which is using Txn CO88.
    Also if I run the CO88,I  hope it just updates the WIP account so whether there is any high risk of running this transaction.
    Any documentaion on CO88 will be helpful  & also if you can explain what is reasons for  the errors on KKS1 then it will be quite helpful .
    Thanks,
    AG

    Hello All ,
    One more question . I have done the variance calculation for my process order via KKS2 but when I run CO88 it does not settle this order . Not sure what is the criteria for order not considered for the settlement.
    Order already has the delivered & Techoed status.
    Thanks,
    AG

  • Partially conversion of process order

    hi all
    i am implementing PP-PI scenario.
    just like production order i want to know how plann orders can convert to process orders with partial quantity.
    please mention setting advise.
    thanks in advance.

    Hii,
    For Process order , maintian master Recipe instead of Routing, create Process order type with PS profile.
    After MRP run, check planned order and carry below transaction,
    Run Cor7 - coversion of planned to process order
    COR8 - Collective conversion of process order
    with regards,
    K.Lokesh.

  • BAPI to retrieve partial deliveries in purchase order item level

    We have implemented an invoice scanning solution for all our purchasing documents, we seem to have an issue picking up partial deliveries in our scanning interface, in the delivery schedule at item level, if the delivery is not complete, you will see this information in this tab, is there any FM available that can display this information??
    Will 'BAPI_PO_GETDETAIL' have this information??
    Regards
    mark

    Hi Mark
    If you simply put a PO number and execute you will see you have this information available in POSCHEDULE
    Nabheet

  • Partial Deliveries against Sales Order

    Dear Team,
    Query1: How to see the salesorders list for whose more than one delivery happened in the system?.
    Query2: How to see the list of invoices that were created with reference to sales Order?
    Regards,
    Varma

    Hi,
    Please check this criteria also
    delivery will be split if the below fields are different
    Shipping point
    ship to party.
    Route.
    confirmed qty dates
    Also if you have any custom splitting rules, please check your copy control setting in T code VTLA from order to delivery.
    if you manually break the schedule lines, and if stock is available for the order quantity , then delivery split will not happend and whole ord quantity will be delivered, even if there are varying schedule lines for the line item.
    Hope this helps
    Br,
    Tushar

  • Confirmation Error in process order

    Hi
    During partial confirmation of process order,i find that for a Phase/counter the goods moment for 101 has taken place but no entry is posted for 261.But the material document shows one 101 movement and two 261 movements and for the reversal of the confirmations of the same counter the material document shows only one 102 movements.Can u kindly help me in the root cause of this error in posting.
    1.Why 261 Movement is not dspalyed but two entries on the material document are found
    2.The reversal process has only one 101 Movement
    Thanks
    Praveenkumar

    Hi Prasobh
    We have three activates happened on this order.
    Partial confirmation for counter 10.
    Reversal of posting for counter 10.
    Partial confirmation of counter 12.
    During partial confirmation there is one 101 movement and two 261 movement happened through material document xxxxxxxxxxxx. The second 261 should not have happened.
    During the reversal only had one 102 movement and there was no reversal happened for 262 in material document xxxxxxx. But we have 2 COGI errors for counter 11, this is not cleared the reversal though the COGI error was cleared. The CORT will not show counter 11 since it’s a reversal of counter for 10.
    In above all we should not have two movements for 261. Also after clearing from COGI we have no posting for 262 movement. But the document for 102 is posted when it’s cleared from COGI.

  • Incomplete Process order settlement at Month end.

    We have issue with order settlement during the month end. We have process orders that run over the week (thus will run over the month-end), with REL, PCNF, and PDLV status at the month end. Production does not want to close/ TECO those orders, as we are not yet done. But FI wants to settle them for the month end.
    1) Can FI settle those REL work orders, as mentioned before?
    This is what I found:
    2) The standard practice is TECO, is to set before closing the order.
    3) You can only perform (business) closing for a process order if (CLSD):
    The order has status Released (REL), Control recipe created (CRCR) or Control recipe discarded (CRAB), or Technically completed (TECO). To have status Technically completed, the order must have already reached status Released.
    The order balance is 0.
    There are no more open purchase requisitions, orders, or commitments for it.
    All data related to the process order is available and correct (For example, the inspection lots for the order must be completed).
    There are no future change records from the confirmation processes
    2) So, if statement 1) is correct, is this correct lifeycle:
    A.     Settlement at month end for all orders with REL status.
    B.      TECO after settlement, and also after DLV and CNF status.
    C.      Close after TECO.
    Upload in your comments, if there is any link.
    Thanks, points will be rewarded.

    Hi Abi,
    Since the Process order is in uncompleted stage and partially delivered to stock, still it has WIP to be delivered to stock.
    Calculate the WIP value & settle the order in Month end.
    Prerequisite for WIP calculation is order should has REL status.
    In month end for Uncompleted order , calculate WIP value & settle the Order.
    General steps for month end practice:
    Over head calculation
    WIP calculation
    Variance calculation -  Once the Order receives  -  DLV /TECO  status.
    Order settlement.
    Order closing
    Regards
    Pradeep

  • Settlement of partially delivered order

    Dear all,
    I have one question.
    Can we settle the process order which is partially delivered?
    Need your valuable suggestion.
    Regards
    Nilesh Joshi.

    Hi
    You can calculate the wip for partial delivered orders and the same may be settled  to FI  WIP ac debit and Change in invetory account will be credited and once complete the order you can reverse the wip and calculate the variances on the process order.
    Regards
    Madhav

  • Target Cost in the settled process order become zero after cost deletion

    Dear all,
    User has standard cost estimates created in Jan 2010 that valid until the end of 2010 for every material in the system.  user created a process order in April 2010. Target cost of the order was created based on the standard cost estimate and recipes as well as order qty.    The order was also confirmed and settled in April 2010 without problem. 
    However, after I deleted all old costing estimates before I did a costing run for all materials in May 2010, the old order was resettled and all Target cost is removed from the order.  I guess system try to look at April costing estimate but it is not there since it was deleted before I created the new costing estimate in May.  Therefore, all varainces are throwed into remaining variances since the target cost become zero.
    Other than mark the settled order for deletion or keep all old costing estimates,  I am just wondering is anyway in the configuration to prevent the system to recaculate the target cost again for the settlement so I can avoid the problem happens?
    Thanks.

    Hi,
    Target costs are only calculated after goods movements have occured on the order, the Target Costs are then calculated during the Variance calculation.
    Target costs will only be calculated after the first goods receipt has been posted to the order. Also you have to ensure that the information to calculate target costs exists on the system in particular in OKV6.
    This estimation is based on the customizing for the Target cost version in transaction OKV6 as in turn will the "real" calculation of the Target costs via the variance calculation.
    So in OKV6 the Target cost will be based on preliminary costing on the order, an alternative cost estimate or the current standard cost estimate. Importantly if the choosen option is not fulfilled e.g. no current standard cost estimate, the target costs will not be predicted or calculated.
    regards
    Waman

  • Open Order Quantity by partial deliveries in 2LIS_02_SGR/CGR/SCN/ITM

    members,
    One of our customers uses now in BW the following Datasources for Purchase Orders:
    2LIS_02_SGR
    2LIS_02_CGR
    2LIS_02_SCN
    2LIS_02_ITM
    This seems to be done via the standard way of working,
    These 4 Datasources go to the DSO 0PUR_O01
    The data of this DSO goes via another DSO (ZPUR_O01) to the purchase cube ZPUR_C07
    In the DSO all values are overwritten, so you have the latest values.
    I expected the field "Current goods receipt quantity in order unit" (= /BIC/OW_AKTWE_DA) to be the total.
    But it is the latest value
    What I need is the open quantity for an order/position:
    In case of partial deliveries I see that you have the value of the last delivery.
    As I want to have the open order quantity in reports, is it necessary to make an extra field in the DSO (based on Goods receipts), but then with a summation rule?
    Or are there better options to realize this?
    I also see the field OPNQTY(= Open Amount of Schedule Line (after Goods Mvmnt Assignment)) in the Datasources 2LIS_02_SGR
    2LIS_02_CGR which is not used currently.
    I might oversee something trivial as the open order quantity is an important keyfigure report about.
    If you have any idea, let me know.
    Thx in advance,
    Ben J.

    Dear Anand
    This might be happen, when your data sources is not active in LBWE .
    Ex: You have maintained your setup initialization, at the time all the DS might not be active. Hence those DS only have the data in RSA3. In Future if you want to go with some other DS, you delete the setup table once and once again you need to fill the setup.
    Hence i request you to delete & reload the setup table, and try in RSA3
    Regards
    Raju Saravanan

  • Partial GR and GI for Process Orders

    Hello,
    I have a scenario where user want to do Partial GR and GI posting against process order using PI sheet and he can very well do this.
    I want to know which SAP table will store this data. I want to prepare report which will run everyday evening and get GR and GI postings done against process done.
    regards,
    Parshuram

    >
    parshuram manjrekar wrote:
    > Hello,
    >
    > I have a scenario where user want to do Partial GR and GI posting against process order using PI sheet and he can very well do this.
    >
    > I want to know which SAP table will store this data. I want to prepare report which will run everyday evening and get GR and GI postings done against process done.
    >
    > regards,
    > Parshuram
    Parshuram,
    You can use standard transaction MB51 for this purpose, which would give you all the material movements for an Order/orders.
    If you still need to develop a report then you need to use MSEG table to extract the data. Order details can be from AUFK/AFKO/ AFPO , planned GI quantities from RESB table
    Regards,
    Prasobh

  • Partial reversal of a goods receipt from process order

    Dear All
    Could anyone please help me with explaining how to do a partial reversal of a goods receipt from process order? If Iu2019m using trans CORS I have to cancel the entire operation, which I donu2019t want to do. If Iu2019m using MIGO and MT 102 I only reverse the goods receipts of the produced material, the corresponding components from the BoM is not reversed with MT 262 as they are if I cancel with CORS, and I donu2019t want to do a second MIGO transaction in which I cancel the components with MT 261. I have also tried to create an operation with a negative quantity, but without any success.
    Itu2019s not an option for the business to reverse the entire quantity and then perform a new goods receipt with the right quantity.

    Hi again,
    I have been trying to do the reversal with CORR but Iu2019m getting the error message u201CMixed confirmation types (time ticket/time event) are not allowedu201D, message number RU179.
    Anyone who can help me on the way?
    /WM consultant on unknown territory

  • Process order settlement

    Hi,
    when i do process order settlement , system gives error message that "maintain the settlement rule of the sender".
    Process order contains two co-product and i have given details in "joint production" in MRP II tab.
    When i checked order settlement rule in COR2 i couldn't find anything and when i try to insert new settlement rule system gives error message .
    Sunoj

    error message when executing KKS2
    KV     206     1     OIT 20000095/1     No suitable settlement rule found for object OP0000200000950001          Checking and processing orders

  • How to get the all process orders and outbound deliveries based on material

    Hi Team ,
    I need one help from you regarding the MB 56 transaction.
    My doubt is : How to get the all process orders and outbound deliveries based on material, plant and batch?
    Please help me regarding this.
    Thanks & Regards,
    Srikanth.

    Hi,
    You can use ST05,to trace the program and find out,
    hope it will help you...
    thanks and regards,
    veera.