I am defining the project status values in transaction 'solar_project_admin' under 'project standards' tab as follows.
Z25 - 25% complete
Z50 - 50% complete
Z75 - 75% complete
Z100 - 100% complete
There are columns called valuation and sort sequence next to status and name .
What is the usage and where in IMG do we configure these.
Thanks.
Mike
Edited by: Mike Sikorsky on Jul 17, 2008 7:54 PM

Hi Mike,
it's not maintainded in IMG but in SOLAR_PROJECT_ADMIN on tab "Project Standards". There click on the button "Project Template" at the bottom.
Regards
Andreas

Similar Messages

  • How to change status value in component system (maintenance project)?

    Hy Experts,
    we are facing a problem while stting up CHARM in a three system landscape:
    The error occurs wile attempting to create an IMG project:
    Longtext:
    Status values are different in source and target systems. See long text
    Message no. SOLAR_SPROJECT022
    Diagnosis
    When you create a customzing project in the component system, the Solution Manager project status values are copied. If these values do not yet exist in the component system, they are created. If they already exist, they are not changed.
    In this case, the copied  status values exist in the component system, but they may have a different meaning: their descriptions differ.
    Procedure
    Check the meaning of the status values and make them match. If this is not possible, create and use new status values to avoid inconsistencies.
    How can I check and change this settings in component systems?
    kind regards
    T. Uhl

    Hy Valdecir,
    thanks for urgent reply!
    Do you know where the status values in (each client) or centrally (SolMan?) could be modified?
    I think there are some changes to be done, cause there are all identically configured but none of them has a specific status description.
    thanks in advance
    kind regards
    Tom

  • Status Definition in Project Administration

    Hi@ll
    i want to know, if you define Status in the PROJECT_ADMIN then this statuses will be available at diffrent locations, e.g. Business Blueprint Documents, Configurations Documents etc.
    For example, i define 5 status: open, closed, in work, paused, reopened
    All them will be shown everywhere i can set a status!
    So, if i want e.g. at a business process description dcument only two status: open and in work; can i define this? or will i always be able to choose of all status at e.g. business process description dcument???
    i hope you understand this.
    thx
    Marco

    Hi Marco,
    The status values you define at SOLAR_PROJECT_ADMIN aren't meant to be available for Documents you upload, they are for other tabs/reasons, including the following:
    (1) As a possible Status value in SOLAR_PROJECT_ADMIN itself, in General Data tab
    (2) Admin Tab of SOLAR01/ 02
    For Status Values for Documents, you have to make settings in Configuration as follows:
    SPRO
    SAP Solution Manager  -> Configuration -> Scenario-specific settings -> Cross-scenario settings -> Document Management -> Status for Documents
    You may also like to read other nodes and what they stand for. They are very useful indeed - provided the project is ready to let the SolMan Consultant gather requiremetns and do a proper job. Many of them cannot be (should not be) done in a hurry
    Trust this answers; please feel free to pose any other question on this.
    Best regards,
    Srini

  • Document status values

    Hello!
    I am on solar02 transaction and pulling out IMG objects for configuration. After configuring I am documenting the config in the  by pulling object-document . The default status values for this in "processing status"column are - open, in process, finished and not relevant". How do I add more status values to this drop down menu?
    Thanks.
    Mark

    Hi Mark,
    you need to create 2 status schemes.
    Goto SPRO > SAP Solution Manager Implementation Guide > SAP Solution Manager > Advanced Configuration > Scenario-Specific Settings > Implementation > Document Management > Status for Documents > Define Document Status Schemes
    Do these steps for a blueprint schema and config schema
    1. Click yes to the Cross-Client popup
    2. Click the New Entries button
    3. Name you status Schema
    4. Click Save
    5. Highlight the new schema
    6. Click the status value folder on the left
    7. Click the New Entries button
    8. Add you values in the order you wish, initial status, min, max, ect..
    9. Click save
    Go to SOLAR_PROJECT_ADMIN
    Open your project
    Click the Project Standards tab
    Click the Documentation Types tab
    Click the Project Template button (bottom right)
    Find you documentation types for Blueprint and Configuration in the right hand box
    Go to the last column for those documentation types (you'll need to scroll)
    Select the newly created schema
    Click the save button
    Dont forget to assign point
    Regards
    Kenny

  • Status Values for Test Management

    Has anyone else encountered odd behaviour when maintaining test status values?
    For example, in the IMG (STWB_SET Transaction) the table that holds the status values has 10 entries, however the drop down that the end user accesses only has 6.
    Another thing I noticed is that when you add / change / delete test status values, a drop down entry TEST_ERROR appears when selecting the status.
    Has anyone else noticed this? Do you have a solution?

    It's all here, it just needs to be put together.
    SP10 IMG path
    1. Go to SAP Solution Manager > Scenario specific settings >Implementation > Optional activities > Document Management > Status for Documents > <b>Define Document Status Schemes</b>
    2. Click New Entries and add a new schema
    3. Highlight the new schemas and click on the Status Values folder
    4. Add the new values
    5. Go to Project Administation > Project Standards tab > Documentation Types Tab > Click Project Template button.
    6. In the last column of each Document Type select the proper status schema that you created.
    regards,
    Jason

  • Earned Value with Project Web App 2013?

    Hi folks,
    Earned Value in Project Client is quite fine, the choice of calculate against actual or status date is a nice feature. But using Project Web App I lack the option of setting the status date - is EVA in Project Web App 2013 really restricted to the actual
    date? Or is the status date set automatically by approved task updates?
    Thanks
    Olaf

    Hi Olaf,
    Unfortunately the status date cannot be set from PWA, and there is no automatic update behind. The intent is that the PM updates the status date and the tasks in MS Project Pro and the team members and executives can consult EVA from PWA.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Retrieve all values from project type when project type combo box is null

    Hi,
    We are facing a tight situation here. We have a scenario where we have 2 filter options.
    1) Department ID
    2) Project type
    When department ID is selected all the department IDs should be populated in the combo box and the project type combo box should be empty.
    Similarly, when project type is selected all the project types should be populated in the combo box and the department ID combo box should be empty.
    Then, when more than one value is selected from department ID box and all the values from project type must be retrieved from query level (as per business logic).
    How do we do this? Kindly help us with this situation.

    Basically my situation slightly different.
    I am trying to do a bulk insert on SQL Server table using prepared statement, during that time i am getting the exception. I am using JDBC-ODBC driver. However, if i do individual record insertion, it is working.
    Any idea about this type of problem ?
    Regards
    Ramesh

  • Unable to change the status of a project to approved

    Dear Members,
    I am using the Oracle Vision Instance version 12.1.3 and Database 11.2.0.3.0
    I have created a project. I am unable to change the status of the project to APPROVED. I am getting the below error:-
    Please enter an active project manager for this project in order to change or update this information._
    Can any one please help me in resolving this issue.
    Many thanks in advance.
    Regards.

    R4S wrote:
    Dear Members,
    I am using the Oracle Vision Instance version 12.1.3 and Database 11.2.0.3.0
    I have created a project. I am unable to change the status of the project to APPROVED. I am getting the below error:-
    Please enter an active project manager for this project in order to change or update this information._
    Can any one please help me in resolving this issue.
    Many thanks in advance.
    Regards.Please see these docs.
    CMRO Partially Implemented Visit Errors with "Please enter an active project manager for this project in order to change or update this information" [ID 864812.1]
    Update_Project Erroring With PA_PR_INSUF_PROJ_MGR While Creating Task For Templates [ID 1085068.1
    Thanks,
    Hussein                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

  • Mass change Tcode for  status of multiple projects

    Dear All,
    Any SAP Standard t code for mass Status change for multiple Projects
    (like TECO,AALK).
    Thanks.
    Arun

    Hi
    You dont have this option in any STD SAP t.codes, where you can change the status of the projects/WBSE collectively.
    So use this BAPI to Read  the status of Project/WBSE
    BAPI_BUS2001_GET_STATUS   To get both the active system statuses and the user statuses for a project definition
    use this BAPI to Change  the status of Project/WBSE
    BAPI_BUS2001_SET_STATUS
    one system status and one user status  can be revoked each time, and one system status  and one user status  can be set each time for a project definition 
    For Network order status change
    BAPI_BUS2002_SET_STATUS
    Set/Reset Network Status. At the same time, you can revoke one system status and one user status, or set one system status and one user status in a list of activities for the network.
    Thanks
    S.Murali
    Edited by: S. Murali on Jul 24, 2009 3:43 PM

  • Set value of project code to Reciept from production matrix.

    Hello Friends,
    I want to set value of project code to Reciept from production matrix after selecting Production order number.I have taken project code field in Production order header.That project code value i have to set  in Reciept from production. I got the Project code no by query but I cant set it to Reciept from production  Matrix project column.
    RS.DoQuery("Select U_PrjCode from OWOR where DocEntry='1')
    str = RS.Fields.Item("U_PrjCode").Value
    oMatrix.Columns.Item("21").Cells.Item(1).Specific.value = str
    this code give me an error
    "Item-Cant set value on item because the item cant get focus"
    Plz give me solution for this..
    Thanks & Regards,
       Swati

    Hello Swati,
    The cell should be foucsed before setting value for it. try this:
    RS.DoQuery("Select U_PrjCode from OWOR where DocEntry='1')
    str = RS.Fields.Item("U_PrjCode").Value
    oMatrix.Columns.Item("21").Cells.Item(1).Click()
    oMatrix.Columns.Item("21").Cells.Item(1).Specific.value = str
    Kind Regards
    -Yatsea

  • What is Value added project stock and how can we track it.

    Hi all,
    There is one query in PS.
    Please guide me about Value added project stock and how can we track it.
    any information regarding this will be highly appreciated
    Thanks & Regards
    Shiv

    Thanks Thorsten for reply.
    Can you please provide the liink or any document you have.It wil be usefull to me
    shiv

  • How can I retrieve the document line status value from UI

    Hi,
    Right now I need to do some check with the each document line status in UI, but it seems it doesn't exist in the the matrix. When I try to use code like this:
    oEditText = (SAPbouiCOM.EditText)oMatrix.Columns.Item("LineStatus").Cells.Item(i).Specific;
    It gives me Invalit Column error, I guess the line status field does not exist in the matrix. Do I have to use DI or SQL query to retrieve the like status value?
    Thanks,
    Lan

    If the document is open on the screen, you can of course get line status from the UI.
    It is column 40:
    oEditText = (SAPbouiCOM.EditText)oMatrix.Columns.Item("40").Cells.Item(i).Specific;

  • In service order Search page,In Service Order Search criteria, In Status value drop down i have to show only user status?

    Hi Team,
    My requirement is In service order Search page,In Service Order Search criteria, In Status value drop down i have to show only user status values only? how to do it..now in my status drop down values system status values also displayed ,i want only user status values only i have to show...how to do it?
    Thanks
    Kalpana

    Hi Kalpana
    As Standard there are 2 separate search fields for Status.
    One for User Status
    One for System Status
    Are you sure that the other Status value you require are not for other Service Transactions different to the one you are wanting to search on?
    If you need to make a only the User Status for  a given selected Transaction Type, then you would need to make an enhancement to that Component
    Regards
    Arden

  • How to get Invoice status value in oracle payable

    Hi guys,
    I am new in oracle apps plz tell me how to get invoice status value of prepayment invoice type in payable.
    Navigation ->Payables->Oracle Payables ->Invoices->Inquiry->Invoices ->go to Invoice status block and open to Status LOV
    plz provide me sql query to find those status lov values and accounted values for any supplier & invoice num.
    it's urgent plz .......................
    Thanks guys.......

    The invoice approval status does not come from any table / lookup.
    Instead, Oracle builds it by calling the ap_invoices_pkg.get_approval_status function.
    You can also call it by passing invoice_id, payment_status_flag and invoice_type_lookup_code.
    All these 4 columns are present on the ap_invoices_all record.
    Hope this helps
    Sandeep Gandhi
    Independent Consultant

  • Display Char Status Values

    Hi BW Wizards,
    I have a query which I run by calendar month/year via a variable. The query runs off a multi-provider and is restricted to two info-providers.  I would like to show the Status values for each info-provider by month per ID.
    The problem is that Status is a Char and so are all the other info-objects used in the query.  I would like to show the status values which are alphabetic- they are not numeric.  The query is defined as follows:
    Rows
    1. Calendar
    2. ID Number
    Columns
    Info-Provider
    Status
    I get blanks in the white result value cells as I am not using a Key Figure.  I know I can set a counter by using a formula selection but I actually need to see the values for status per cal date and ID....this could be a status value of A, C, D etc which all represent a meaning in business.
    How can I achieve this?
    Thanks
    DV

    HI Venkat,
    This is a good suggestion and a correct one, but actually I did this but the users would like the status in the columns, I tried this but the ID must then also go in the columns and causes a scrolling problem.  This is due to the fact that we have 40000 IDs in a monthly report and if they go in the columns its difficult to easy look through the report as opposed to if they were going down the rows.
    Do you know how I could provide them with what they need.
    Thanks
    DV

Maybe you are looking for

  • Unable to connect to a remote db using Sql Developer

    hi, I have 2 systems (A and B) both running on RHEL 6. A has Oracle 10G installed while B has Oracle 11G, and on both I have SQL Developer. A and B are cable networked with static IPs as below. A 192.168.1.1 B 192.168.1.2 I am trying to connect to da

  • Problem inserting value in CLOB column from an XML file using XSU

    Hi, When I try to insert CLOB value into Oracle9i database from an XML document using XSU, I get an exception as below. 09:37:32,392 ERROR [STDERR] oracle.xml.sql.OracleXMLSQLException: 'java.sql.SQLException: ORA-03237: Initial Extent of specified s

  • Wired PC losing network connection to AE

    I have an Airport Extreme, a Power Book (wireless), and a destop top PC. I hook up the AE to my ethernet jack, and the PB connects just fine. I hook up my PC through wired network connection on the AE, and I get a "network cable unplugged" error on t

  • Business area not defaulted for tax line item

    Hello Friends, I am posting Customer invoice, when I simulate the invoice that time Output tax is automatically calculating the tax. My problem is, in the Output tax line item business area is required field which is appearing in display mode. T code

  • Start Up Problems with too full Mac Air

    I cant restart my Mac Air after the batterie whent flat after i got message about Start Up Memory Too Full. What do i do now.