Hi Gurus,
I am maintaining 2 UOM in the material master .
1) Kg
2 ) Tonne
I am purchasing my material in Tonnes . During Usage decision, I want to post my material in Kg.
I ] Is it possible to make the UOM change during Usage Decision.
II] Is it possible to use same inspection plan for the same UOM, In case of I am recieving the material  by Kg or Tonne
Thanks in Advance.
Srinivasan

You cannot normally change the UOM in the UD.  You can only use the bas UOM.  SAP however does have a note on using alternate UOM in the stock posting. It is not as seamless as you would probably like, but its the best you'll do.
The note is 605861.
I posted part of it below.
Craig
With the import of the assigned Support Package or the implementation of
this note, a Business Add-In is made available with which you can program
an input help for quantities in the usage decision.
For example, this enables you to specify quantities for the stock posting
in an alternative unit of measure in the usage decision. Via a
corresponding BAdI implementation, you can call up a dialog box - in which
you can specify the respective quantity with the required unit - in the
usage decision when you use the input help (F4) for the quantity fields.
However, the quantity is always transferred in base unit of measure to the
stock posting.
The BAdI can only be used for stock-relevant inspection lots. You can only
enter the quantities in other unit of measures manually (explicit call of
the input help).
You can implement new BAdI QEVA_ALT_QTY_INPUT using Transaction SE19.
Take also the documentation on the BAdI into account.
You can transfer the BAdI definition together with the respective
documentation using the assigned Support Package.

Similar Messages

  • Error during Usage Decision - Not All Physical Samples are valuated

    Hi,
    I am using Sampling Procedure as follows:
    Sampling Type :   Fixed Sample
    Valuation Mode :  Attributive Inspection nonconf. Units
    Inspection Points : Sample Management
    I have assigned the  Inspection Point as  200  and Sample Drawing  Procdure in Inspection Plan Header.
    I have recorded and closed results for 3 samples. During Usage decision the following message shows:
    Not all physical samples are valuated!  Do you want to force inspection completion? 
    This means that Valuation of Inspection points have not updated. I request your help to solve this problem.
    Thanks & Regards
    V.Devaraj

    Hi
    Check the inspection plan, check for all the operation, by double clicking on operation you enter the opertioa details screnn, pls scrol down, you should have a field called VALUATION, select the option "automatic valuation option" .
    try this
    navin

  • Valuate the non-valuated QM characteristic during usage decision

    Hi Guys,
    I don't understand why during usage decision, system pops up the following message even though I have force the inspection completion on one particular inspection characteristic.
    Valuate the non-valuated QM characteristics manually? Yes button and No button
            After hits Yes button, another message appears...
    Class characteristic QNNVM1 can be manually evaluated.
    There are two inspection characteristics in this inspection lot, and one inspectin characteristic has been record as pass and accepted during result recording, while another inspection characteristic (which is a required characteristic on system setup) did not perform result record. Thus, during QA11, I force this required characteristic to inspection completion.
    My questin is why the system gave me "Valuate the non-valuated QM characteristics manually?" message?
    Thanks
    YY

    Plz. tell me whether sampling procedure is used for these characteristics ?
    If yes then whether valuation mode is 'valuate manually ' ?

  • Error during usage decision for Test Equipment

    Hi,
    I have completed results recording  for Test Equipment using QE51N (results closed and confirmation completed). When I tried to make usage decision (QA11) for the lot the pop-up message shows as "Not all equipment is valuated! Do you want to force inspection completion. I also noticed that in equipment tab of qa11 code valuation column shows as Not  Valuated.
    I request you to help me to solve this problem.
    Thanks & Regards
    V.Devaraj

    HI,
    You may try changing the valuation mode in IA06. In the inspection characteristic overivew, click on details -> operation, scroll down, you will find Quality management inspection points  -> maintain automatic valuation based on inspection points.
    The changes if made will be effective only for the next inspeciton lots.
    Regards,
    M.M

  • SAPscript unit of measurement (UoM) changed during print

    Hi Experts,
    I am doing my SAPscript and its print program for Invoice printing (VF02/VF03). The problem only occurs when its UoM is BOX. It will display in the Invoice printing as '012' instead of BOX. When I debug in the print program, in structure VBDPR (field VRKME), it has the correct UoM which is BOX. When I debug my SAPscript, it will give me 012 as its UoM!! I don't know what is the reason behind this behavior. Please advice.
    Points will be given....Thanks in advance.
    Regards,
    Fauzah.

    hi
    For all other UoM is it coming correct ?
      there is two table fields for UoM MEINS n GEWEI , check which one ur displaying in Sap Script.
        try with do change in that field , thic can solve ur problam .

  • Error during Usage decision

    Hi,
    System status is not updating in the transaction QA32.We find that system status is not updating from certain period earlier which is fine.
    Another thing is We are not able to clear the inspection lots through UD in QA32.If we try to do the UD in QA32 we are getting the error operation QM20 not available for this lot message QV224.
    If we try to view the inspection lot we are getting the error No status object is available for INL 80000000328
    Message no. BS001.
    At the time when system status is updating fine we are able to do these things.Is system status is the reason for this?
    Please help us on the above mentioned problems.
    Thanks & Regards,
    Rajesh

    hi,
    i think none of the lot result is recorded.
    QAC3 & QA02 can help you to create.
    please check and confirm.
    balajia

  • Material Disposition After Usage Decision

    Hi Gurus,
    Im working on a scenario werein I need to change the Defect recording after I need to change the disposition of the material. The process is, the lot will be rejected, and will go to a certain Location. In this location, the user will decide whether it can be rework, return to vendor or use as is. User will need to key in in the system.
    At first, I though I can just use of changing the usage decision. But they say they need the disposition per item in the defect code. But once I have done usage decision, Defect cannot be changed.
    Please help to identify other process that I can do.
    Thank you,
    Raymond

    Dear Raymond
    Then in that case the only solution will be to activate notification.Please follow this process
    1) Maintaina default notification type in the inspection type in the config
    2) When defect recording is done automaticaly notification will be created
    3) When UD is given notification also gets closed automaticaly
    4) Go to notification ( in UD screen , select the defect and click on Notification and put the notification back in process (menu button > function> Put back in process
    5) Here you can edit the defect or add defect and automaticaly gets assigned to the inspection lot
    Please check and revert back
    Regards
    GN
    Edited by: Gajesh Nagesh on Feb 3, 2010 6:14 PM

  • Usage decision related tables

    Hi,
    I do a usage decision for a inspection lot of 10 qty in QA32. I enter UD code A( accept) and quantity as 4 and save.stock gets posted. Again in QA32 I  enter UD code as A1 ( conditional accept) for the same inspection lot and post remaining qty 6 .
    In what table can I get qty as 4 and 6 for a given inspection lot. Kindly help.
    Regards.

    Hi,
    In that functional module, I can get details of the last UD code which I have entered during Usage decisions.Previous UD codes are not there.Same is happening in table QAMB also.
    Pls guide.
    Regards.

  • Quality Management - Usage Decision error

    Hi all,
    My scenerio is - There is a material ABC which is procured from the supplier. The Quality of the material is 'below standards'. However, material ABC, in Tcode QA11 Usage decision was done as ACC1 (accepted). Since the material ABC is not meeting quality standards, Usage decision is changed to RET1 (Bad Raw Material - Return) using Tcode QA12.
    Now the problem is that when I enter QA11, the system does not allow me to enter as a message appears 'Detailed Info- Usage decision made is disallowed' is showing.
    Please provide me a solution as the material is lying in the unrestricted stock and it has to be returned to the supplier. Also please consider costing implications.
    Thanks in advance

    Cancel the inspection lot in QM using the function to change the usage decision.
    Logistics - Quality management - Quality inspection - Inspection lot - Usage decision - Change with History - Usage decisions - Functions - Cancel lot 
    Reward if cleared and close the thread.

  • Work flow for Rejections in Quality- Usage decision

    Dear all
    We are in the process of activating work flow for Quality Inspection, During Usage decision there may be rejections for which we need to trigger a mail to the Internal department , stating the Remarks, description, rejected quantity etc ,
    If any one has come across the same scenario kindly help us so as to implement the same in our organization.
    Regards
    Rahul Bhat

    Hi,
    You can do any of the following according to you Requirement.
    1) Below the Rejection Branch using the Send mail you can send the mail to Respective person.
    2) Other wise using the Function Module you can send the mail, refer this l[ink|https://wiki.sdn.sap.com/wiki/x/nYKdAw ].
    3) Else place this Std. Task TS20000139 and provide the necessary binding below the Rejection branch a popup will open and the user can enter the comments and it will go to the Person whom you want.
    Try any of this according to you requirement.
    Regards,
    Surjith Kumar

  • Issue  in usage decision

    Hi,
    During usage decision, i have moved the stock to scrap by mistake , can you please tell me how to reverse the UD.
    I tried through MB1B. The problem is we dont know in which storage location it is posted
    Can you please suggest me , how to proceed.
    One more issue.
    I want to bring down the scrap field in inspection lot stock screen, how to do it.
    Thanks in advance.
    Regards
    Karthik

    Hi
    To find material document no. :
    1. if you know the lot number, you can use QA03 (Display lot) Tcode and click on the item mat doc. The doc no with type 3 assigned is your required material doc.
    2. Goto MB51, and use movement type 553, material and plant and execute to get the material no.
    To reverse from scrap to QI:
    1. Activate insp. type 05 in QM view of material master.
    2. Goto MB1A, use movement type 554 to transfet the quantity. Lot will be generated in QI, do UD and transfer the lot to unrestricted usage.

  • [HELP] - QM cancel usage decision

    Hello SAP gurus,
    I need dome help with a QM scenario.
    How can I cancel a UD and move the stock again to Quality Inspection?
    Thanks in advance,
    Adelmo

    Hi
    here is some more help,
    Follow the link (page 27) http://help.sap.com/printdocu/core/Print46c/EN/data/pdf/QMIMUD/QMIMUD.pdf
    Reversing Stock Postings
    1. Choose Logistics > Materials Management > Inventory Management > Goods Movement>  Goods receipt > For purchase order> PO number known.
    The initial screen for creating a goods receipt for a purchase order appears.
    2. In the field for the movement type, enter 102 (goods receipt for a purchase order into
    warehouse - reversal).
    3. In the field for the purchase order, enter the purchase order number for the original goods
    receipt.
    You can copy the purchase order number from the inspection lot.
    4. Choose Enter to display the selection screen for the purchase order items.
    5. Select the purchase order item for which you want to create the goods receipt and set the
    Stock type indicator to the stock to which the goods were originally posted with the
    usage decision (for example, F for unrestricted-use stock or S for blocked stock).
    6. Save the goods receipt and exit the Materials Management component.
    7. Choose Logistics > Quality management > Quality inspection > Inspection lot> Usage
    decision > Change with history.
    The initial screen for changing a usage decision appears.
    8. Enter the number of the inspection lot for which you previously made the usage decision and
    choose Usage decision (UD).
    9. To cancel the inspection lot, choose Usage decision > Functions . Cancel lot in the usage
    decision screen.
    Regards
    Suhas

  • Calibration: Error while taking Usage Decision (Urgent)

    Hi Gurus,
    I created one test equipment and installed it on some m/c and while doing calibration during usage decision if i reject the equipment it is giving me the error : equipment installed on superior equipment.
    if i accept the usage decision system gives no error.
    and it is customer requirement that their instruments should be installed on some m/c not on functional locations.
    Please suggest the solution
    Regards
    Pankaj

    Hi,
    As per the SAP general process first you need to dismantle sub equipment from superior equipment for taking UD, since it is assigned with superior equipment System wil not allow for taking UD.
    Regards
    Sendil

  • Usage decision cancellation

    Dear All,
    For the manual inspection lot created i did RR. Then in the usage decision screen i enter decision as rejected and saved. status shows as UD   ICCO STUP. Then i go to the functions and cancel lot. The status now shows as LTCA ICCO STUP. Then again i wanted to give the decision as accepted. that time a message occurs as LTCA Lot cancelled and STIC short term inspection cancelled.
    1. can i change the usage decision results again after giving usage decision once?
    2. what are the steps to do it?
    Regards,
    DTD

    Goto QA12 T-Code revert the Cancellation Status and SAVE
    Again goto QA12 T-Code you can change the UD Code from R to A without any problem.
    Normally if we want to change the UD Code no need to cancel the Insp. Lot diretcly through QA12 we can do it.
    Best Regards,
    K. Raghavendra Nayak

  • Quantity Of Sample Not Scrapped Afetr Usage Decision  (Urgent !!)

    Hello Guru's,
    We have many samples wich are not automatically scrapped during usage decision quantity still stays in sample area 046(Storage Type).
    I don't understand why the samples are not scrapped.
    Can I have your suggestions pls..or any user exits to handle this requirement or how I need to approach this problem to get the solution.
    Points will be rewarded.
    Regards
    Ravi Ganji

    Hi all
    When I am testing the tast thru SWUD its working fine.I have to provide inspection lot no. and workitem go to my workplace.there i can make usage decision and the task is over.I am using task no TS 00008331
    Thanks in advance.
    Ashwani

Maybe you are looking for

  • Error while renaming indexes and keys in the tables

    hi gems...good afternoon.. i am using oracle 11gr2 database. when i am trying to rename the primary key, foreign key, indexes of all the tables as per the standard, then the following error is given... ORA-00604: error occurred at recursive SQL level

  • After system restore CS3 stopped working and can not be uninstalled

    I did a system restore (W7) and my CS3 apps stopped working with the message "Licensing for this product stopped functioning. Currently you cannot use this product. Solve this problem by uninstalling and reinstalling or contact support." I tried to u

  • Commit after locking database ?????

    Hi Experts., Is it necessary to commit work though i am holding a lock on a database ?? reasons and example needed............ <REMOVED BY MODERATOR> Edited by: Alvaro Tejada Galindo on Jun 12, 2008 2:19 PM

  • Business rules from epma to planning

    Hi, In EPMA version 11.1.12 I am having an issue with business rules. I wrote and deployed a business rule from EPMA to planning and everything was fine, the rule ran on save in the data form. Now, I tried to run the rule a few days later and it won'

  • Bandwidth Monitor

    I currently go to a college that monitors my bandwidth for uploading and downloading and I was looking for a real time monitor that keeps track of the amount of data I upload and download. While I know there are some dashboard utilities that do this,