Which prod. ver will consider for costing?

Dear Guru's,
I have three prodution versions for material with three different alternative BOM and same recipe for all three versions. All three versions are with same lot size and date validity. when i do cost running which version will be considerd by system as default? is frist version? if it is frist version what seeting is required to pick req version to consider for costing?
sree

the system considers the first available active production version as its default costing version for a period cost.
alternatively if u want to select another version you would have to lock the other ones.
eg:
if you want the 2nd one selected than mark the 1st production version as Locked for any Usage from C223.
than the system would pick Version 2.
same is true for the 3rd one, the first two versions would have to be locked.

Similar Messages

  • Which Access sequence will use for sales tax condition type for TAXINN

    hi.,
    which Access sequence will use for sales tax condition type for TAXINN procedure.pls give one example (Access sequence) and give fields.
    Because i couldnot create the condition record,the system not accepted for tax indicator.
    Regards.,
    lakshmanan

    We also got the same problem with our client and escalated it to SAP.
    they advised to use the access sequence <b>JIND</b> which consists of condition tables in the order given below
    <b><u><i>Step    Condn Table</i></u> 
    10            354
    20            355
    30            40</b>
    Attach this to your condition types.
    Rewards if it helps.
    Regards,
    Anbu

  • Which scenario u will suggest for Iron & Steel industry & why?

    Which scenario u will suggest for Iron & Steel industry & why?
    Product - Galvanised Plain/ Galvanised Corrugated Sheets
    Process- Pickling-Cold Rolling -Galavanizing- Cutting /Corrugation
    Kindly suggest manufacturing scenario Discrete / Repetitve ?
    Madan

    Hi
    Please clear the following doubts:
    1. Is it working on Make to order scenario or Make to stock scenario?
    2. Will the sheets that come out are of different sizes and shapes?
    if so the final operation will be different for different sizes.
    Chandra

  • Which frame works will support for blackberry application developement.

    Hi
    Which frame works will support for blackberry application developement?
    Thanks
    Achyut

    hello,
    I think you'll have much more answers if you post in one of the three discussion boards "Blackberry Development" :
    http://supportforums.blackberry.com/rim?category.id=BlackBerryDevelopment
    Anyways, RIM has a website for people who want to start developing, it's here :
    http://na.blackberry.com/eng/developers/started/
    The search box on top-right of this page is your true friend, and the public Knowledge Base too:

  • In which table we will update the cost that  is calculated thru ck40n

    hi
    does anyone know where we will update the price or cost calculated when we perform the costing in ck40n....for standard cost

    it will updates Material masters ?
    Regards
    Peram

  • Which Creative Suite will work for a G5 2.5ghz PPC Dual?

    I'm using OSX 10.5.8 on a G5 2.5ghz PPC Dual Core Mac that is not intel-based.
    I have 4gb of RAM, 500gb HD and I'm mainly interested in using Photoshop & Illustrator but,
    all other apps would be welcome. Which Creative Suite can i buy for my Mac?

    You can't. The last version of CS that was usable on a non-Intel machine was CS4. With the release of CS5 a year or so ago, Adobe stopped selling CS4. You will be hard pressed to find a legitimate copy of CS4. Sorry, but the sad truth is that you'll need to buy a new computer at this point.
    Bob

  • Which video formats will work for sure in FrameMaker 11?

    I have done multiple test with somewhat discouraging results now. I want to embed a small video file in a FrameMaker 11 file and have it work in pdf. But even though this features should be able to work in both FrameMaker 10 and 11, my results are poor to say the least. I have tried multiple videoformats and sometime I am in luck and the video embeds and works, but most often it does not embed or it opens somewhere else on the page than the place where it was inserted. Is there a best practice for embedding video regarding file formats, distiller settings etc. I have spent several days now trying to make this work the way it is expcted to.
    regards
    Bjørn

    I am looking at a new project where I will have to do exactly this, so I am also interested in an answer to studiosm's query.
    Thanks,
    Laurie

  • Cost Analysis: Planned Vs Actual Cost Variance for cost

    Hai
    Which is the standard cube for "Cost Analysis: Planned Vs Actual Cost Variance for cost"?
    Because i need these fields
    Cost Element
    Actual Cost
    Plan cost
    Debit Posting
    Credit Posting
    Controlling Area
    Cost Centre

    Hi nvr,
    Cost Element : Cost Element nothing but a which product your spending
    Actual Cost : How much amount your spend on particular product
    Plan cost : How much amount you need to spend on particular product
    Debit Posting : In Accounting they are doing one positng that is depend on Debit and Credit.
    Credit Posting:
    For Exp: your parchase one product RS.500/-
    In FI they are posted like this.
    Product Name DR.(Debit) 500
    to Cash                                      500 (Credit)
    here product name is debit posting
    cash is credit posting.
    Controlling Area : Which area your spending the money
    For Exp: You have Man.Company your doing some processes which process that cost is spend nothing but a Controlling Area.
    Cost Centre : cost Centre nothing but which process.
    Hope its' helps .
    Thanks and Regards,
    Venkat.

  • TAble for cost center group in 3.0 F transaction.

    hi, 
    i need to develop a report to extract cost center data from r/3 in 3.0 F version.
    can u guys help me that which table has got entries for cost center group.
    waiting for  your replies,
    Regards,
    Rachana

    hi  ,
    I have checked in csks, cska, cskb, and cssk as well, but i didnt find a field which holds the cost center group information ..please help me as this is a bit urgent ..
    Thanks in advance , 
    Regards,
    RaAchana

  • Which data we will store in infocube?

    hi experts,
    i am in little bit  confusion, i think this is basic level question.
    can any body tell me where we store analysed data. that means which data we will store in infocube( raw data or analysed data). which data we will use for reporting?
    please clear this confusion.
    thanks & regards
    venkat

    Hi Venkata,
    I have a basic simple understanding and explainantion. You get some raw data from a system such as R/3 which you apply transfer rules and transformations. Applying this will help us remove any inconsistencies, and standardizing the data we get from R/3. After this process, we have the data ready which can be stored in the Infocube/ DSO. Thus, Infocube contains data that is cleansed and standardized. Now, since you have the data ready, you design queries on the Infocube, which will generate reports according to the requirements. These reports will be used for analysis of all the data presented in the report through appropriate query.
    Hello All, Please correct me if i m wrong.
    Regards,
    Kunal Gandhi

  • KP06 - No transactions for cost planning are defined in the Nos range table

    Dear CO Experts,
    I m trying to post Cost Planning using T-Code KP06.
    please help, the Error which pops is :
    *No transactions for cost planning are defined in the number range table*
    *Message no. K8007*
    *Diagnosis*
    *You want plan primary or secondary costs/revenues in controlling area 9000. This is not possible because no entries exist in the number range table for the cost planning transactions you want to perform.*
    *This is an internal system error.*
    *System Response*
    *Processing is terminated.*
    *Procedure*
    *Start program RKTKA04C.*
    *Execute*
    *After the program has run successfully, start planning again.*

    HI,
    the planning subobjetcs to be assigned in KANK to a CO-number range are (maybe you do not need all of them):
    KAZP
    KOAP
    KPPB
    KPPZ
    KSP0
    KSPB
    KZPP
    KZRP
    PAPL
    RKP1
    RKP2
    RKP3
    RKP4
    RKP5
    RKP6
    RKP7
    RKP8
    RKP9
    RKPB
    RKPL
    RKPQ
    RKPS
    RKPU
    RKPV
    RKPW
    RKPX
    RKPZ
    best regrads, Christian

  • What will be the cost for iphone 5 replacement which is in warrenty but accidentally damaged.not screen it's just back glass of camera,so what will be cost to fix it or replace the phone in indian rupees, USD will work.

    what will be the cost for iphone 5 replacement which is in warrenty but accidentally damaged.not screen it's just back glass of camera,so what will be cost to fix it or replace the phone in indian rupees, USD will work.

    If you are in India, contact your local service center for a price quote. I don't know if Indian service centers can replace just the back glass or if they will need to replace the entire iPhone. To locate a service center, see:
    https://locate.apple.com/in/en/
    Make sure you select "iPhone" for the product time. Only certain service centers can handle iPhones.
    Regards.

  • Which bom & routing selection for costing

    hi
       i have 9  multiple BOM for a finished product and 1 routing.
      i want to run CK11 AND CK24 for standard cost estimate.
    my problem is that which bom & routing should be considered for std. cost estimate.
    for each combination calculated std. price in CK11 is different.
    how i should address this issue  so that i can calculate std. price

    Hi Rajeev,
    If you have ( BOMs and 1 Routing that means you have 9 different Production version or not than create it.
    Now How system will pick the Production version for Costing.
    it Depends on
    - Costing Lot size - Costing 1 of Material Master.
    Now as per your Costing Lot size system will pick the nearest prod. version.And If there are more than one Production version found which match the costing lot size then it will pick the first one (See the production version sequence in  t.code C223).
    And depends on that Production version system will pick the BOM and Routing attached to it.
    But if you want to run MRP as per your Selection then Select BOM and Routing in Quantity Structuer or Production version in
    Costing Data 1 View of Material Master.
    It will become default Selection for BOM and Routing for Cost estimate.
    Regards,
    Dhaval

  • Which extraction methods are used for extracting AR , AP, GL , cost centre

    which extraction methods are used for extracting AR , AP, GL, cost centre  account   data from R/3 system.
    please let me know what type of extraction we use...generic or FISL.... OR COPA
    ON WHAT SCENARIOS WE USE  THIS EXTRACTIONS..
    if any have documents on it please  email...please  send  an  email    documents ..
    to  [email protected]  
    iam bit confused with sap help...
    will reward full points
    please reply

    Hi,
    For general ledger :
    http://help.sap.com/saphelp_nw70/helpdata/en/57/dd153c4eb5d82ce10000000a114084/frameset.htm
    This is the best how-to guide on AP,AR,GL and TAX.
    http://help.sap.com/saphelp_nw04/helpdata/en/af/16533bbb15b762e10000000a114084/frameset.htm
    Hope it helps.
    Regards,
    Srikanth.

  • For financial report requirment can we consider secondary cost element cost

    For financial reporting requirment can we consider secondary cost element cost to profit and loss a/c

    In our senario _ cost is booking cost centers and revenues booking concern profit centers .
    for Financial reporting requirment can I include secondary cost to profit and loss a/c
    what is the impact on the report
    exp: salary booking in primary cost,than Per hour man hour cost computed by costing dept for allocate to concern department
    it is cost center activity price we specify in kp26 at the time of pm order confirm it will confim the activity quandity price will from planning area only,  so for salaries in primary g/ls already captured, if we consider secondary it may double booking
    srinivasa reddy

Maybe you are looking for

  • I need a student well versed in Illustrator to finish a project

    I began a book project about 4 years ago and had a illustrator who produced 200+ illustrations for me before dissapearing off the face of the earth! I'd like to finish the project so I need someone versed in Illustrator to finish about 100 illustrati

  • Import SWF's that use components

    I'm using a Flipping Book component in Flash that's really cool, and I'm trying to get the exported SWF into Director. When I import the SWF, everything in it works except the flip-book component. It just doesn't show up. My only guess as to the prob

  • Combining two programs to make one

    Is there an easy way for me to combine these two programs? What I am wanting to use an array for the different loans. Display the mortgage payment amount for each loan and then list the loan balance and interest paid for each payment over the term of

  • R25run command line syntax

    Hi, This is my first time working with reports. I can't seem to run my report from the command line. I have reports 25 installed. I can run r25runm, motif, and it prints to printer or to screen fine. But when I used r25run, no motif, I can't get it t

  • Setting a ViewCriteria on all instances of a ViewObject

    Hello, ViewObjectMaster           |           -- ViewObjectDetailWe've got the setup above and we add filtering dynamically to the ViewObjectDetail. We do this by accessing the ViewObjectDetail instance using the application module and calling our fi