Helloo Experts,
We have a current situation here, Where order type (OR) with item cat (TAN) creates SO then delievry (LF) happened and PGI..
Due to some reasons the order needs to be void.Then the SO has been changed (VA02) by adding item cat YREN with same quantity, then delivery (LF) ,PGR and billing (F2).
Now after final billing the order status coming as "Being processed" instead of "Closed" at the document flow.
Does SAP standard practice supports this process flow OR it should be Return order (RE),Delivery (LR) and return of credit (RE)  to make the Order status  "Completed".
Is there any other ways to make these order's status changed from "Being Processed" to "Completed"
Waiting for some valuable inputs.
Thanks
SM

Then the SO has been changed (VA02) by adding item cat YREN
    with same quantity, then delivery (LF) ,PGR and billing (F2).
This process is wrong.  You have to create a new return sale order with reference to the parent billing document.  If billing has not been generated, then you have to reverse the delivery via VL09.
G. Lakshmipathi

Similar Messages

  • Quotation to Order-Status of Quotation "Being Processed"

    Hello,
    I have a problem with reference to Status of  a quotation.
    I have a quotation with a BOM SKU.
    I have created a sales order which is fully referenced from the quotation.
    Even though the Quotation is fully referenced to create an Order, the status of the quotation is
    Still
    u201CBeing Processedu201D
    Status of Order is u201CCompletedu201D
    I checked the copy control routines for the item categories and also the item category properties,
    It looks fine.
    Any suggestions for the status being shown u201CBeing Processedu201D.
    Ideally I would like the quotation to be shown in u201CCompleted Statusu201D after an fully referenced order is created
    Thanks and regards,
    Venkat

    Hi Venkat
    Check the Completion rule in VOV7  for quotation item category
    Regards
    Srinath

  • Overall Status of order Being processed after complete PGI & Billing

    Dear All,
    Before writing this post i tried all possible solution available on SCN & internet.
    In sales order overall status (GBSTK) is Being processed after doing complete delivery and Billing.
    I tried many things changed the completion rule also run the program SDVBUK00 but the status is not updated to complete.
    Created 1 sales order with 1 material without any reference then done PGI for 1 material then done billing successfully.
    In table VBUK / VBUP the field GBSTK / GBSTA showing Being processed, for delivery and invoice its showing completed "C".
    I checked the Incompletion Log also there is nothing pending.
    Please refer screenshots and provide me solutions.
    Thanks in advance.
    Tarun Kumar

    There is no additional schedule line.
    I have taken 1 quantity and it confirmed.
    I change the completion rule also but no luck.
    Copy control screenshot-

  • Sales Order Status "Being Processed"  after completion for Free Goods Sales

    Hello All,
    This problem is related to Free Goods Sales which is as follows.
    The process-flow for free goods sales is first we raise a sales order, then we do outbound delivery for the sales order and then finally PGI of the goods.We don't raise any invoice and the Free Goods Challan is issued to the customers by running a report.
    The document flow at the end always show the Sales Order  status as " Being Processed" and Outbound Delivery & PGI as "Completed".I want the system to show the Sales Order status as " Completed" and not " Being Processed".How to do that?
    Please suggest some solutions.
    Thanks & Regards
    Priyanka Mitra

    Hi Raja,
    Thanks a lot for your prompt reply and suggestion.
    Now we are able to get the Completed status in Document Flow.
    Thanks & Regards
    Priyanka Mitra
    P.S. -  I would request you to go through another problem which we are facing in Shipment , please go through this and suggest some solution regarding it if possible.
    I have already posted this problem in a separate thread few days back but am yet to receive any fruitful suggestion.
    The problem is regarding Shipment Cost Calculation while doing STO which is as follows -
    In our scenario the Shipment cost calculation is done on two basis -
    1) Absolute Rate / Flat Rate Wise - For example for transporting of goods from Kolkata Depot to Delhi Depot is Rs. 20,000 fixed.
    2)) Gross Weight Wise - where the weight unit is kg and rate for example is Rs. 4 / Kg. So for 10 Kg the shipment cost will be Rs. 40.
    Now I want the system to calculate the shipment cost on Rate / Carton Wise i.e. How will I be able to calculate the shipment cost of 100 cartons if the rate is Rs. 100/ Carton.
    How to configure this ? Please help in this regard.

  • Sales Order status still "Being processed" after invoice (3rd party sales)

    Dear SD gurus,
    Here's what is done so far:
    1. Create a sales order with one line (TAS item cat).
    2. Trigger PR to be created. Approved the PR.
    3. Create Purchase Order. Approve the PO.
    4. Perform MIRO.
    5. Create sales invoice based on sales order (billing based on supplier invoice).
    6. Invoice released to accounting
    Now, when I checked the sales order status, it's still showing "Being processed". However, invoice have already been created and released. I'm just wondering what else have I done wrongly. I believe the status should show "Completed" as well otherwise this order will keep showing up as outstanding in my sales order listing report.
    Anyone got any ideas?

    SAM
    I had a looked at both the SAP Notes provided. Doesn't really apply in my situation. The Sales order was for 10 qty. My PR for 10 qty and I have also done a MIRO for 10 qty. even my sales invoice was for 10 qty.
    I do not want to configure it to follow the PO quantity because I need a control where only vendor has delivered the products to the customer only then I should invoice the customer accordingly. If I allow the invoice to be created based on the PO quantity then the control factor will be lost.
    I have yet to try the program that you recommended... will try that shortly.
    And yes ... since I'm using the standard sap TAS item cat ... the "relevance for delivery" is already turned off and the billing is "F"

  • Order status is still saying processing items

    I ordered my IPad 3 on the 16th of March, so it was after the pre-order thing and I was going to just buy it straight away from a apple store but dicided to order online with engraving and the apple smart cover. Both the items are still saying "processing items". I have recieved an order confirmation email but not the shipped confirmation email unless I didn't read it right but the email just said that they can get it deliverered eariler than expected. This is my first time ordering on the apple website although I have an IPhone 4S which i recieved as a christmas present and I think was brought from o2 so I have no idea how long this would take. Why is it still saying "Processing Items"? Surely it doesn't take apple this long to process the items.

    Further to my original post, I received my iPad on the 29th which was a day after the earliest possible delivery date. The order status did not change until the day before it arrived so don't worru about that. I realised that it had dead pixels, rang up on Thursday evening and arranged for it to be picked up, replacement arrived on the Wednesday after (4th). This one also had dead pixels and a new one arrived today which I hope is not going to have dead pixels! I am impressed by the speed in which they ship out replacements but annoyed at the quality control if I'm honest.

  • Order status is seen as "processing items" for about a week.

    I ordered Iphone 4S on November 21 st, but when I check the order status, it's been written as "Processing Items".
    I also checked my credit card bill and I couldn't see any payment on November 21st. I wonder if any trouble occured during payment. Or is this product out of stock?

    Further to my original post, I received my iPad on the 29th which was a day after the earliest possible delivery date. The order status did not change until the day before it arrived so don't worru about that. I realised that it had dead pixels, rang up on Thursday evening and arranged for it to be picked up, replacement arrived on the Wednesday after (4th). This one also had dead pixels and a new one arrived today which I hope is not going to have dead pixels! I am impressed by the speed in which they ship out replacements but annoyed at the quality control if I'm honest.

  • Process after return invoice from customer

    Dear gurus,
    Would anyone help me on this issue below?
    I created customer orders for one customer in three spesific times. One of these orders is service(no PGI) others are with PGI. Now our client send us one return invoice which includes both service order and material order.
    Can anyone tell me step by step for the next process?
    What must I do?

    Hi,
    Material orders :
    Create a return order based on original invoice for the material orders, than create a return delivery and do the PGR.
    After that create a credit memo wrt return order or return delivery as per your current  settings.
    Service Order
    Create a credit memo directly with reference to original invoice for services or create a return order for services and with reff to order create a credit note .
    HOpe this will help you !!!!
    Regards,
    Krishna O

  • If my IPHONE 5 order status has changed from "processing" to "preparing for delivery" is there a chance I will receive it sooner than the 10/5 date that it is scheduled for?

    I pre-ordered my iPhone 5 on 9/15 at 4am EST. It said shipping in 2 weeks with an delivery date of 10/5... yadda yadda yadda.  This morning my order status showed as 'processing'. This afternoon it changed to 'preparing for delivery'. Is there a chance I will now receive before 10/5? Trying to plan accordingly. Thanks in advance for any info you can give.

    I was in the same boat.  I ordered @ 5:09AM EST on 9/14 and had the 10/5 delivery date.  My status changed from processing to preparing to ship yesterday 9/21.  I got an e-mail from Apple @ 4:22AM this morning 9/22 that it has shipped (along with the precious tracking #)!  I would expect it would arrive by this Friday 9/28 at the latest.

  • Updating service order status in CRM from R3 after the invoice is created

    Hi all ;
    I need to update the user status of an service order in CRM when the invoice related to it in R3 is created, so I have already know  the service order no .
    How can i achieve this by sending BDOC from R3 to CRM? Which BDOC should i use?and is it enough to fill only status data in BDOC?
    Thanks.

    Hi sushant,
    When the R/3 Order status is set to 'Completed' then the system status for order in CRM system is automatically changed to 'Completed'.
    So firstly check whether the User status ('Completed')in SAP CRM has the Business transaction event set to 'FINI'. So when the system status is set to 'Completed' the user status will also change to 'Completed.'
    Secondly even check what are the statuses of item in the Orders.
    regards,
    Anubhav

  • PM order status remains as PCNF even after completion confirmation & TECO

    Hi,
    For some of the PM orders we created, the order status is till in PCNF and operation status in MCNF.
    We have done the following also
    1) Completion confirmation done for all operations
    2) "Fincal confirmation" and "No remaining work" tabs checked for all operation confirmations
    3) TECO is done
    But still the operations are in mCNF-Manual confirmation status and hence the order is is in PCNF.
    Please let me know how to change the order status from PCNF to CNF.

    Please check any Sub operation confirmation is pending or ? if so please do ( IW41 )
    Riyaj
    Edited by: riyajmaner on Feb 24, 2012 5:08 PM

  • How to do order status should be completed even with partial delivery?

    Hi,
    My requirement is i have sales order for 5 units.
    Delivery will be done for 3 units.
    I need the sales order status to be completed after delivery.
    I have tried with completion rule in item catagery'Item is completed with first reference'
    Still the status in document flow is order 'being processed'
    Can any body help me out
    regards,
    Reddyy

    Hi Reddy
    If your requirement has to be fulfilled then assign reason for rejection at item level for all line items after doing delivery .Then the item will be closed with 3pcs only .And when you check the document flow then the sales order will be closed
    NOTE : No need to change the completion rule at the item category level
    Regards
    Srinath

  • After Return Delivery to Vendor cannot remove shipping notification in MD04

    Hi.
    Good Day.
    I would like to ask help regarding to my issue.
    We had to create a return delivery to send the goods back to the vendor A. The packaging item was blocked and we created the outbound delivery via transaction MBRL with reference to material document when we do GR with the inbound Delivery A. After having processed all necessary steps including the posting of the goods issue of outbound delivery, the inbound delivery A is again open and expects a goods receipt of the returned units. This can also be seen in MD04. Meanwhile the supplier has sent a new "compensation" delivery, with a different inbound delivery B. This was goods receipted and with this delivery the complaint/return process is finished from the supplier's and our point of view.
    Problem: What remains is the original open inbound delivery A. Currently we have no idea how to get this one deleted, but we need to cancel it, because there won't be a credit note and there won't be another physical delivery for this inbound delivery A.
    What I have done so far:
    1) Tried using VL09 to inbound delivery A but there was no effects. probably because the inbound delivery A is already closed.
    2) It is not possible to set the item of SA to finished because we my use that item again.
    Thanks for your help.
    Med'z

    Hi Madhu.
    Good Day.
    First of all I really appreciate your response.
    I tried to change the first inbound delivery but canu2019t do much. Because all fields were block since it is already completed.
    The system shows the error "The goods movement status (partially or completely processed) does not allow the item to be deleted."
    I also tried to change the schedule line but it didnu2019t do any effect with the issue.
    Thank you,
    Best regards.
    Medel.

  • Process for Return Delivery and Capture Excise

    Dear All,
    I have done GR for 10 Qty and created Excise Invoice for the same, now I have to reject 5 qty out of 10, so I have done it through Return Delivery movement type 122.
    Now My question is how to adjust 5 qty and its amount in in Excise Registers.
    Regards,Vivek

    HI
    after performing 122 movement type
    now use t-code J1IS ,click on create and give  material document of 122 movement type there give  plant ,excise group ,series group and vendor
    for more info check following link
    [Return to vendor with excise duty..?;
    Regards
    Kailas Ugale

  • I've ordered a book from iPhoto 3 times.  Last order was W29631918.  It says the order is accepted and being processed and then about 4 days later tells me the order has been cancelled.  If I call the help line it tells me the order has been cancelled and

    CLICK.  I've never had any problem like this with Shutterfly, ever.  And Apple gives you no other explanation.  CLICK.  That was my last Apple order.  What a waste.  Maybe someone from Apple can tell my why they do this.  It was for Christmas and I started ordering November 5 and waiting for it to be delivered each time.  This last one I followed and it even told me that the order had been processed and could not be cancelled.  The proprietary company.  Now I'm sorry I started using iphoto.  I'll redo the project with Shutterfly but I'm wondering if Apple treats many of its customers like this.

    i had the same problem .. and the worse is that i am from middle east where we can not get any help from apple.
    like if apple is only for some countries not for all world.
    what happened then? have you ever know what was the problem?

Maybe you are looking for

  • How to use Phone enrolment for an Intune account?

    I have created a Microsoft Intune account and setup a signed company hub for phone devices. But I cannot work out what information to enter into the Windows Phone 8.0 -> settings -> company apps in order to enrol the phone onto Intune. I have an Intu

  • PNP LDB Problem

    Hi Gurus, I have a problem. I have created an HR report with PNP logical database. I created my own report category for the purpose. In the <b>Selection</b> option I have given two select options. One is personnel number and the other is company code

  • Asset values cannot be displayed due to missing text

    Hi guru's,     I am facing the problem while i am displaying the asset values,i am able to create asset through as91 but when i go for awo1n system showing error" Asset values cannot be displayed due to missing" help would be appreciated. Thanks Ravi

  • I can't see all my pictures from my camera roll in photos, what is happening?

    I can't see all my pictures from my camera roll in photos, what is happening?

  • New line, just connected...

    Hi all You might have seen some of my posts in the past where I've been trying to squeeze out the most from a long rural line.. Just moved into a flat whilst working in Canary Wharf so have had new service activated (phone and bband). Was getting exc