Actual cost showing doubled after settlement in PS reports

Dear friends,
I have created a project with actual cost 120,000, and then I settled the cost to the AUC using CJ88 , when I run the report S_ALR_87013558 it gives wrong amount and counted the cost double 240,000 (120,000 + 120,000 )
This actual cost error is showing in all the reports plan, actual, budget etc.
Pls heip me for the solution

Hi,
Please check your settlement profile details. You can check after settlement, the debit / credit as after settlement the cost is getting doubled.
Hope this will help you.
Regards,
Rakesh Pradhan

Similar Messages

  • Cost center after settlement in FAGLL03 REPORT

    we have process of material issue thru maintennce order. after issuing material FI entry is on respective gl and maintence order
    in report fagll03 we can see this combination and then after settlement of cost of order on cost center we are not able to see cost center in report  fagll03.
    is it possible to get cost center after settlement in this report.
    if no then how can  we see cost center /  gl /  material report for maintence orders.

    You can't able to see the cost center report until settle the maintenance order to cost center with secondary cost element.
    after settlement also you can't see in FAGLL03, you can see only cost center report with secundry cost element

  • Actual cost showing different

    Hi Expert,
    The actual cost showing different in two report cji3 & cn41.Plz help me.
    Thanks

    I did whatever you have suggested me.but i have not found desired result.
    scenario is- In cn41 report
    suppose the actual cost in wbs is 6649095
    But under this network & activity level the actual cost is 6461522
    In cji3 report at network activity level the actual cost is 6461522 & the actual cost of wbs is also 6461522
    Plz guide me why cn41 report showing different actual cost at wbs level.
    regards

  • Actuals is getting doubled after settlment CJ88

    Dear SIr,
    When my client is running settlment for AUC of Rs.100000/-,
    1)Assign AUC to WBS elment
    2)Executing CJ88 by Automatic mode
    3)Creating Asset Master
    4)Executing CJIC
    5)Executing CJ88
    After all this procedure, actuals in report or in CJ30 assign column is showing doubled of it i.e. Rs.200000/-
    Can anyone suggest how it getting doubled of it?
    Thanks & Regards,
    ARvidn Tirlotkar

    Hi,
    When your  Run First time - Run T.code  CJ88 by Period and  and Later Run  CJ88 T.code .. run it by Automatic.
    Thanks
    Goutam
    Edited by: Goutam78 on May 13, 2011 6:27 PM

  • In order negative actual cost showing

    Dear all,
    I have purchase material from MO and after Good inward against order system shows negative value(cost) against spare and consumable value categary.
    Total panneled cose -26000/-
    Actual cost             -22620/-
    And in the purchase order material cost is 3380/-
    why system is showing 22620 this value in actual cost instead of 3380.

    Hi Shahanawaz,
    Please check your intial stock & cost. Check for sign at Componenet qty tab is it ( - sign) as with this sign the system will make 262 for the item & your stock & cost will get changed . So i suggest first check your intial stocks & then for Material documents deatails once u posted theGRN.
    Ramesh

  • Actual cost of Production Order settled to Fixed Assets

    Dear all,
    My client is doing in-house production of moulds (internal order suggestion is not accepted by the client) for which
    they have the following
    1. BOM
    2. Machine hour
    3. labour
    4. overhead etc
    5.plan value
    6. actual value
    Can i settle the actual cost of production order to Fixed Asset ?
    If yes
    what are process kindly give me if any process other then the below
    1.production order created
    2. settlement profile - FA is settlement optional
    3. allocation structure
    4. Asset created
    5 define asset in settlement rule
    Kindly give me your valuable input
    regards
    elango

    Hi,
    Although i am not CO expert , please check with your FICO consultant who are expert before make the final call.
    During settlement to a G/L account or a fixed asset, the system ignores additional account assignments that were manually specified in the distribution rule.
    Based on what i know .
    you can stipulate that settlement may be made to cost centers and orders, but not to fixed assets.
    The Settlement profile is something that you need to create a settlement rule to settle the actual costs of a sender object.
    About the Settlement rule is something that  contains the distribution rules for the sender. It will define how the way to settle the cost.
    Allocation Structure
    In the settlement structure you combine the primary and secondary cost elements into groups, in which debits are then posted to the sender objects. For each group, you specify whether (for settlement to a given receiver type) settlement is performed
    by cost element or using a settlement cost element.
    For example, you might use settlement cost elements:
      To document the purpose of an order (such as, repairs or maintenance)
      To reduce data volumes (you can combine a number of debit cost elements
    under one settlement cost element).
    TQ

  • Livecache remote cube report shows double the value in BW reports

    Hi,
    We are trying to report against livecache using remote cube and getting
    doubled values in reports where as direct report against livecache is showing different results.
    Transaction: RSA3
    Data Souce: Livecache
    Planning version: 000
    Loaded one particular product
    Then consensus forecast shows a value 250.
    The same information if we try to access using BEx analyzer 3.x then
    Consensus forecast = 500
    Which is DOUBLE the value than it is using RSA3. Why is it doubling? Please let me know if you come across similar issue.
    Thanks,
    Srini

    please check the Remote cube contents as well. Go to ListCube transaction enter the remote cube and check the contents of that cube.

  • Actual cost of spares not reflecting in standard reports

    Hi all,
         we have procured the materials for 2 years and all the materials  are procured as assets and they are being capitalized with INR 0.01 value and when we are using these spares im PM order, the cost of the material is very low.
    can you help me in material management how and where the material procurement cost is captured?

    When you procure the material, and received good receipt than update po history and price store in inforecord if inforecord update, and you can find in material master if that material create in material master record. You can check this way.
    Thanks

  • Burden Cost shows as Financial Item in Workplan Actual Cost

    We are burdening Cost in Project Manufacturing. When Actual Cost shows in Project Management it is displaying Raw cost as Labor and Burden Cost in Financial Item row as unplanned cost. Any ideas? During the planning it is correct --- Burdened Cost.

    Hi Connell,
    For your first question, you have to set the correct parameters in the file menu, options for the earned value analysis. Select the appropriate Baseline (Baseline 1) and the physical % complete:
    Then you are talking about a chart. What chart is it? Have you first checked the BCWP column in MS Project Pro if you do have values before exporting data? Also have you set the status date? Do you have work resources with a standard rate?
    For your 2nd question, depending on your Project version, you can use the visual report (2007, 2010, 2013) or the report feature (2013) using the cumulative fields (actual cost, Baseline, cost...).
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • PS - Report on Planned v/s actual cost of the project

    Hi,
    I have a client requirement on the above subject. In Report S_ALR_87013542, Under actual cost the system is taking both the Revenue and Actual cost booked on the project. Is there any other report wherein the system shows only the actual cost booked on the project so that planned V/s Actual can be compared.
    Rgds,
    Prasad

    Hi,
    You can also refer the report S_ALR_87013543 - Actual/Plan/Variance Absolute/Variance %. This will give the reports based on cost elements. Morever plan cost Vs actual cost can be obtained from Project Infosystem report (CN41/ CNS41).
    In fact the report S_ALR_87013533 is a hiecherachical report for plan & actual cost of project.
    If the system is calculating wrongly both revenue & actual cost under actual then you need to check Cost elements asignments & value category details.
    Hope this will help you.
    Regards,
    Rakesh Pradhan

  • Actual costs for laboratory exams / Material Ledger

    Hi Experts
    I have a doubt for actual cost scenario for laboratory industry.
    My  background is for product cost for consumer goods, specially food companies, so this is a new segment for me.
    This laboratory has baseline version, no service/production order, it means all material consumption goes to cost center and they use activities to send costs from cost center to cost center.
    They have BOM for all exams (finished product). They only run CK40N for standard costs but they don't have actual cost (material ledger - CKMLCP) implemented.
    This is the issue: they want actual cost for every exam in the way we have for consumer goods industry.
    So they can analyse profitability for product (exam) x customers.
    I wounder if the same industry actual cost scenario can be applied to this business segment or if there is a special SAP solution for this segment.
    The main issue is the stock, there is no stock, it´s service. I believe we could change the account in BSX key (OBYC) for some P&L accounts but I´d like your opinion/experience.
    I hope you help me to  clarify these doubts
    Thanks in advance.

    Dear Rupesh,
    I don't think so there will be any std.report in PS module to show plan vs actual cost of material component.
    For looking plan vs actual cost in PS having many std reports but they don't show for material component.
    I think for this you need to develop a Z report which will show Plan vs Actual cost of material component.
    In CN52N report (Component overview report) you can add two fields one is for plan cost & other for actual cost.This can be one of possibilty you can try.Otherwise develop a new Z report for the same.
    For this you need to take yr abaper's help.
    Regard's
    Sandeep

  • PS (plan vs actual costs) Report

    Hi,
    I have to generate the above report. How can I diffrentiate between Plan cost and actual cost. Is there any business contect report for this ? can anybody throw light on this.
    Regards,
    Bill

    Hi Bill,
               There is no std content for this as far as I know , Not sure if your report is based on cost for a given version then its really a mystery . If you are looking to pull the cost for PS then check the table RPSCO in r3 , this is the PS cost table , and you can differentiate Plan/Actual based on the Field Value type .
    hope this helps ,

  • Table of Actual cost of production

    Hi Experts,
    I m developing one Z report for our client which shud contain Standard cost & Actual cost of production of the sold material for that particular month.
    I am following KKBC_PKO tcode for the same.
    Standard cost & Actual cost has a part of secondary cost element.
    Can I know which table will have Actual cost details to present in above mentioned report??
    Thanks in Advance.
    Madhu.

    Dear Madhu,
    Table COEP will help you to check the actual cost.
    Check and revert back.
    Regards
    Mangalraj.S

  • Actual costs after settlement

    Logically should actual costs be displayed in cost reports after settlement?
    In my case line item actuals shows the costs as zero as PRE settlement done to cost center. But in that case should the value be still displayed as actual costs.
    In other systems here the value is still displayed though it is settled to an AuC or CTR. What could be the reason?

    You may reverse the manual posting to asset (credit posting with Dr/Cr indicator of C) and then perform settlement via CJ88. I hope i was able to understand your query correctly and answer it appropriately.
    Regards,
    Syed Ammar Zaheer

  • CProjects Actual Cost = 0 after Settlement Run

    Hi Gurus
    After running Transaction CJ8G (Settlement Run), then I log into cProjects, locate my Project and go to the Accounting Tab, I click on Calculate, then Save, then I return to the cProjects Dashboard
    When I look at the Actual Costs Value it is zero.
    What do I need to do to prevent this from happening?
    My overall process is.
    Approve Time: CATS_APPR_LITE
    Send Confirmed Time to cProjects     SE38 - (DPR_CATS_CPR_TRANSF)
    Transfer Timesheet Data to Controlling     CAT7
    Log in to cProjects
         Locate the Project in question and go into Accounting
         Click on Calculate & Save
         Click on Home          (Actual Costs > 0)
    Generate Settlement Rules     CJB1
    Execute Settlement Run     CJ8G    
    Log in to cProjects
         Locate the Project in question and go into Accounting
         Click on Calculate & Save
         Click on Home          (Actual Costs = 0)
    Many Thanks in advance
    Panduranga

    Hi Panduranga,
    The Badi OLR3_COSTS introduced with the note
    1095514  enable you manipulate the costs showed in the dashboard. Please take a look the longtext of the note and implement (very simple) the codes.
    Kind regards,
    Zhenbo