Atp with product allocaton

hi
please tell me what is atp check in regard to the product allocation.i have gone thru the documentation but i am not able to understand how this functionality works in sap if somebody can explain with an example and how it is related with the customer hierarchy and what is the purpose of info structures in this
thanks and regards
vikas

Viaks,
Please see if the following helps: 
Configuration Overview; Allocation Specific Usage 
1.Allocation Procedure (OV1Z) The product allocation procedure is the parent of the entire allocation process. All materials that are to be included in the allocation scheme are required to have an allocation procedure assigned to it in the material master. In addition, as of release 4.0, it is in the procedure that the method of allocation is defined. The user has the opportunity to set an indicator to identify their choice of two different methods (discrete and cumulative allocation) to evaluate the quantities to be considered for product allocation. 
2.Allocation Object (OV2Z) The allocation object is the root level of the allocation process where actual data is entered and planned in LIS. The object allows the user to further break down a procedure into smaller parts for future validation of components comprising a specific material 
3.Allocation Hierarchy Mapping (OV3Z) Primarily, this transaction permits the assignment of an allocation procedure to an LIS information structure. Secondly, a character is assigned to the information structure to permit collective planning. Finally, the user can assign a step level to the procedure and information structure to sequence the order in which allocation quantities are checked. This functionality allows the user the opportunity to check product allocation against several product allocation scenarios, before the required quantity is confirmed 
4.Define Consumption Periods (OV5Z) The allocation consumption periods functionality is only valid if the allocation method flag has been set (OV1Z). If you have de-selected the method field, this functionality is not available. The consumption window indicates the number of past and future periods to be used in the allocation check. 
5.Control Product Allocation (OV4Z) In order for the allocation process to function properly, allocation control records are created primarily to map allocation procedure steps to their corresponding objects so that the allocation data records can be located for validation. Secondly, validity periods must be established to indicate when the allocation control records are active. Finally, the user has the option of establishing a conversion factor per allocation control record to accommodate BOM listings of constrained materials 
6.Activate Allocation for Requirement Class (OVZ0) In order to turn on allocation in the standard order processing functionality, the requirements class must have a flag indicating that allocation is relevant. 
7.Activate Allocation for Schedule Line Category (OVZ8) In order to turn on allocation in the standard order processing functionality, the schedule line must have a flag indicating that allocation is relevant 
8.Create Planning Hierarchy (MC61) In order to adequately establish allocation quantities, the user must initially determine the level at which the allocation is to take place and the aggregation factor of the allocation quantities. In this step, the levels for the collective allocation search procedure are also identified. 
9.Generate Masking Character (OV7Z) Upon completion of the level determination for the planning hierarchy, the collective allocation masking character must be generated to allow aggregation indicators to be established. This transaction simply reads the hierarchy established in the planning table and then generates a collective mask character for each level of the hierarchy 
10.Modify Planning Hierarchy (MC62) This step is a repeat of MC61 where the initial hierarchy was established. In order to complete the hierarchical set up, the collective allocation (mask character) hierarchy must now be maintained with the appropriate aggregation factors 
11.Allocation Procedure Assignment to Material Master (MM02) At the root level of the allocation process are the materials. Each material that is to be considered in allocation scenario must be mapped to an allocation procedure. In order entry, then, when a material is entered with a valid allocation procedure in the material master, the allocation data is verified prior to confirming the line item ordered 
12.List of Suitable Structures (OV9Z) This report is used to identify potential LIS information structures that can be used in the product allocation process. This report simply reads through the data dictionary and selects all the active information structures that contain the field product allocation object (KONOB) as the first field. This data can then be utilized in the mapping transaction (OV3Z) to link the allocation procedure step to an information structure (previous step).
REWARD IF U FINDS THIS AS USEFUL.....
Regds
MM

Similar Messages

  • Global ATP with product allocations and SD returns

    Dear all,
    We have  been setting up an implementation scenario with an ECC 6.0 and SCM 5.0 system which verifies SD orders versus SCM product allocations.
    With SD orders and SD contracts everything works fine. But we have a problem with using SD returns (same material and plant used like the SD orders): We would expect the system also to check the returns for product allocation quantities but it seems that the SCM availability check does not enter the product allocation procedure at all (we have some user-exits in use but these are only accessed when we go via SD orders, no access at all for SD returns).
    Is there any special setting which we have to activate in order to have the SD returns properly processed with product allocations? (Customizing "Set the Transfer of Returns to SAP APO" within ECC is activated) The system somewhere gets stuck during the check within the SCM system.
    Thanks for providing assistance regarding this matter.
    Kind regards,
    Klemens

    Hi folks, did you resolve your issue here? I assume what you are wanting is for the Returns order to free up allocations qtys that had previously been consumed by the originating sales order, that is, incoming orders qty should be reduced by the amount of the returns order. I know that when a sales order line item is rejected the incoming order qty is reduced, but I'm not sure it is possible for a returns order to do this.
    ATP Man, are you saying that as category BZ is not supported by Allocations that it is therefore not possible for the Incoming Orders Qty to be reduced  by a Returns Order? I have a business reequirement to do exactly that.
    If it is not possible to do this through the automatically via the ATP check, the only way I can think to address this, would be to try and transfer the Returns qty to SCM after the order is saved and then to have a macro that reads the returns qty and reduces the Incoming Orders qty by the qty of the return.
    Paul.

  • Material determination with Product selection

    Hi SAP Gurus
    We are using material determination with product selection. The process is that customer will send in one product in a sales order. At the time of doing ATP we have to look for about three or four possible alternatives and confirm that alternative which has the highest stock level depending on the ATP situation. We have configured material determination with SAP standard substitution reason’0006’ to take care of this. The problem with this is that this creates two line items in sales order as the item substituted is shown as a sub-item of the material entered. We do not want to have two line items in a sales order for this. Is there a way we can do material determination with product selection (Based on ATP) and have the item substituted replace the item entered in a sales order? In other words we do not want to see two line items in a sales order. The substitute item should simply replace the original item and the material entered could be stored in field VBAP-MATWA. I have gone through all the standard SAP documentation which clearly states that in order to material determination based on ATP we have to use outcome A or B both of which create a sub-item.
    I was wondering if there is any workaround or if there is any user exit in which we can replace the original item with the substituted item?? Any help or any direction will be highly appreciated.
    Another question is if we were to use APO for doing global/Rule based ATP is it possible to get rid of the double line items. We have also tried to use rule based ATP in APO and use product/location substitution in our sandbox system to see if we can get back only one line item. But even in that case we do get a sub item. Any help on this issue will be greatly appreciated. You can also send me an e-mail at [email protected]
    Thanks
    SDSAPCON

    >
    SAPCON SD wrote:
    > Hi SAP Gurus
    >
    > We are using material determination with product selection. The process is that customer will send in one product in a sales order. At the time of doing ATP we have to look for about three or four possible alternatives and confirm that alternative which has the highest stock level depending on the ATP situation. We have configured material determination with SAP standard substitution reason’0006’ to take care of this. The problem with this is that this creates two line items in sales order as the item substituted is shown as a sub-item of the material entered. We do not want to have two line items in a sales order for this. Is there a way we can do material determination with product selection (Based on ATP) and have the item substituted replace the item entered in a sales order? In other words we do not want to see two line items in a sales order. The substitute item should simply replace the original item and the material entered could be stored in field VBAP-MATWA. I have gone through all the standard SAP documentation which clearly states that in order to material determination based on ATP we have to use outcome A or B both of which create a sub-item.
    >
    > I was wondering if there is any workaround or if there is any user exit in which we can replace the original item with the substituted item?? Any help or any direction will be highly appreciated.
    >
    > Another question is if we were to use APO for doing global/Rule based ATP is it possible to get rid of the double line items. We have also tried to use rule based ATP in APO and use product/location substitution in our sandbox system to see if we can get back only one line item. But even in that case we do get a sub item. Any help on this issue will be greatly appreciated. You can also send me an e-mail at [email protected].
    >
    > Thanks
    >
    > SDSAPCON
    In the substitution reasons ...mark the OUTCOME as blank for this particular 0006. I am not sure for ATP
    rgds
    Sai
    Edited by: Sai on Mar 27, 2008 10:00 PM

  • Rules Based ATP with Stock Transport Order

    Hi All,
       Can we use Rules Based ATP with Stock Transport Order..
       Where to assign the business transaction to the STO order type ?
    Regards,
    Biswajit

    Hi,
    Please follow the link
    Re: Rules based product substitution in STO
    Thanks,
    Pavan Verma

  • Discontinuation functionality with production orders

    Dear Guru's,
    Can anyone please confirm: is the functionality for discontinuation of a material (including follow-up material) not available with production orders?
    Example: in our system we have component A that is followed up by component B. This is set in material master - MRP 4.
    We also have production orders for the upcoming 4 months in our system. If the stock of component A is depleted within these 4 months, we would expect to see requirements (orderreservations?)  on component B, but this is not the case.
    Thanks for any comments,
    Rgds, AJ

    Hi
    Discontinuation works for Production orders.Couple of Checks needed for both Follow up and Discontinued Materials to arrive to actual problem
    1) Base unit of measure must be same
    2) Should have same MRP type
    3) Not defined as Co-Products
    For detailed info pl refer the link
    [Discontinuation|http://help.sap.com/saphelp_47x200/helpdata/en/b1/c044d1439a11d189410000e829fbbd/content.htm]
    Regards
    Brahmaji

  • How Can I Make A Large Photo with Product Detail for My Thumbnails in Dreamweaver

    Hello All:
    New to Dreamweaver, so my code knowledge does not exist yet. Have Mercy!!!!
    Anyway , I am making a typical product page.
    I prefer that when people click the thumbnail product photo to not have to click into another brower.
    Nowadays you are able to click in what is commonly called a "Quick View" that pops up and gives you a full sized
    image along with product detail, and pricing.  That's all I want.
    How can I link this [the larger photo and product detai] to my thumbnails in Dreamweaver???? 
    I want the look that is on every website like Target, Macy, etc.
    Someone, please help me to  !!!!!!!
    These lil' faces are really cute.  They are helping me to smile after hours and days, weeks of frustration.   TWIN MADDOG!!!

    Hi,
    don't understand your problem, ore hope to understand it right. You could put the images on a DW file and link to another file with the larger image and where you have written all your informations.
    I made this here only for a new, larger image (without additional informations):
    <!DOCTYPE html PUBLIC "-//W3C//DTD XHTML 1.0 Transitional//EN" "http://www.w3.org/TR/xhtml1/DTD/xhtml1-transitional.dtd">
    <html xmlns="http://www.w3.org/1999/xhtml">
    <head>
    <meta http-equiv="Content-Type" content="text/html; charset=utf-8" />
    <title>Unbenanntes Dokument</title>
    </head>
    <body>
    <p><a href="pflanze1_l.jpg" target="_parent"><img src="pflanze1_s.jpg" alt="Thumbnail01" width="100" height="75" border="0" /></a></p>
    <p><a href="pflanze1_l.jpg" target="_parent">or this you use an Hyperlink to the larger image</a></p>
    </body>
    </html>
    s=small; l=large
    Hans-G.

  • Calling a stored procedure from a URL with production XE?

    I have granted execute on a stored procedure to the user ANONYMOUS in order to allow it to be called from a URL. But I am getting a Forbidden error, rather than the expected execution of the procedure. Is there a trick to get this working in production XE?

    I think I figured this out. I don't think the grant to ANONYMOUS is going to work with production XE and the online documentation is in need of an update. It appears that production XE has been locked down and you will need to specify the name of each stored procedure you wish to allow to be executed by adding it to the WWV_FLOW_EPG_INCLUDE_MOD_LOCAL function. This is spelled out in more technical detail here: http://download.oracle.com/docs/cd/B25329_01/doc/appdev.102/b25309/adm_wrkspc.htm#BEJCGJFJ
    Another alternative that would work involves creating a separate DAD. Using the DAD approach with my schema made all of my stored procedures callable from a web browser, so I rejected this approach. To make this usable (secure) I would have needed to create and maintain a separate database user for the DAD and then only granted it execute for the stored procedures I wanted to be callable from a URL.
    Finally I read about using an on-demand procedure and having it invoke the desired stored procedure. While I didn't try this out, it sounds like another good approach because it maintains session security. If it can be used to return an image I do not know.
    - Jim

  • M175nw during s/w reinstall - unable to communicate with product

    Windows 7 64-bit / LaserJet 100 MFP M175nw / firmware 20120806 / all device resets done / software uninstalled after broadband hub replaced / re-install undertaken with McAfee firewall OFF / install undertaken with D-Link hub firewall also OFF
    Software starts reinstall, proceeds and then asks for USB to be temporarily connected - after doing so it automatically proceeds (thus indicating that it's communicating OK with M175nw) - says "Product has been detected" - WIndows 7 reports "device installed" - then install stops at 15% completion and says "Unable to communicate with product".
    Can find no way past this.
    Was working beautifully but could not avoid hub upgrade which had to disrupt setup hence re-install.
    HELP!

    Hi @MonicaABC ,
    I see that you are having issues the same issue with the printer installation, but you are on Windows 8.
    I would like to help you out today.
    Some of the steps are the same, I will provide more information for the Windows 8 steps.
    I have also provided steps for configuring the wireless through the ethernet connection.
    On the printer's control panel, touch the setup button, network setup menu, wireless direct, turn it on.
    Here is a document to access the Wireless on Windows 8. How to Connect to Wireless Networks in Windows 8 and Windows 8.1.
    Select the printer's network name.
    Open Internet Explorer and type in the IP address (192.168.223.1) for the printer in the address bar.
    This will load the Embedded Web Server for the printer.
    Select the networking tab, wireless on the left hand side.
    Fill out all your network information, select infrastructure, select your network name, put in password and type of encryption.
    Apply settings.
    Now the printer should be configured over the wireless network.
    Then go to the wireless on the computer and select your network name.
    Run the uninstall from the CD software to remove any registry files.
    Disconnect the USB cable if it is connected.
    Perform a clean boot and disable any Antivirus Software temporarily.
    Then run the latest drivers. Software & Drivers.
    Select your operating system, click next and click on the software to download and install.
    Wireless setup steps through a Ethernet connection steps:
    Connect the Ethernet cable from the printer to the router, temporarily.
    Run the install to see if the drivers will fully install by this connection.
    Follow these steps to configure the wireless now.
    Wait about a minute, print the configuration page to see if you get a IP address.
    Printing a Configuration Report.
    Then type the IP address into Internet Explorer's address bar to bring up the printer's web page. Select the networking tab, wireless on the left hand side. Fill out all your network information, select infrastructure, select your network name, put in password and type of encryption. Apply settings.
    Then disconnect the Ethernet cable.
    Wait for few minutes and you should get a wireless light on the printer, print the configuration page and check the IP address again. Then type the IP address into Internet Explorer's address bar to bring up the printer's web page. Just to make sure it is still on the network.
    Then flip the port with the new IP address.
    Go to start, devices and printers, right click the printer and left click printer properties, select the ports tab.
    Click Add Port, select Standard TCP/IP Port, then select New Port and follow the wizard.
    Type in the proper IP address for the printer.
    Make sure the printer is online.
    Test the printer.
    If you need further assistance, just let me know.
    Have a great day!
    Thank You.
    Please click “Accept as Solution ” if you feel my post solved your issue, it will help others find the solution.
    Click the “Kudos Thumbs Up" on the right to say “Thanks” for helping!
    Gemini02
    I work on behalf of HP

  • Unable to communicate with product message when installing laserjet cp1525nw printer

    I have a cp1525nw wireless printer that use to work fine wirelessly.  I changed my router password (linksys router) and now can't connect.  I have tried changing the password back to the original password and it still will not connect.  So I when back to the changed password.
    I have tried resetting the printer to the default settings, removed all HP software, deleted all temp files, rebooted machine and attempted to reinstall the printer.  The software loads fine, I've connected the USB cord and then get the dreaded "Unable to communicate with product" message.  I have previously tried to connect by WPS and that didn't work either.
    The Wireless Network Test Report shows that the Network Name Found test is Fail.  The Network Summary report shows a different Network Name under the wireless Network Configuration section than my network's SSID.
    What do I need to do?

    Hello,
    I see that you are having issues setting up the printer over the wireless network. I will certainly do my best to help you.
    The password might not be recognized by the printer, if there are spaces or special characters in it.
    Restore the printer defaults. Press the OK button, select Network Config, then select Restore Defaults.
    Print a configuration page to make sure the SSID and the IPv4 address are cleared.
    Printing a Configuration Report.
    Run the printer software again and select Add a Device to setup the wireless again.
    If you are having issues, then uninstall and reinstall the software to configure the wireless.
    Uninstalling the Printer Software.
    HP LaserJet Pro CP1525nw Color Printer Drivers.
    If you need further assistance, just let me know.
    Have a nice day!
    Thank You.
    Please click “Accept as Solution ” if you feel my post solved your issue, it will help others find the solution.
    Click the “Kudos Thumbs Up" on the right to say “Thanks” for helping!
    Gemini02
    I work on behalf of HP

  • Pricing issue with Product hierarchy - Urgent

    Hello,
    I have an issue on pricing determination with product hierarchy.
    I created product hierarchy as following,
    level1 - A0001
    level2 - A0001B0001
    level3 - A0001B0001C0001
    Then, assigned A0001B0001C0001 to material D in material master.
    I created condition record with A0001B0001C0001(level 3),  the system found the condition sucessfully when I created a sales order with material D.
    However, I created condition record with A0001(level1) but the system didn't get the price when I created the sales order with material D.  Since A0001B0001C0001 belongs to A0001, the system is supposed to get the price from the condition record with A0001... 
    Could you please let me know how to fix it?

    Hi,
    Thanks a lot for your kind explanation.
    Here is the access sequence I defined.  I wonder if there is anyway I can define PRODH1, PRODH2, PRODH3 in access sequnce the same way with customer hierarchy so that the system can check higher level data.  If it's not allowed, I think I should define routine in requirement as you advised.  Thanks!
    *Accesses
    AcNo       Description
      1           Customer Hierarchy/Product Hiearchy
      2           Customer Hierarchy/Product Hiearchy
      3           Customer Hierarchy/Product Hiearchy
      4           Customer Hierarchy/Product Hiearchy
    Fields
      AcNo   Condition    Doc. field      field lable
         1      HIENR      HIEBO01     CustomerHierarchy 01
                 PRODH     PRODH       Product hierarchy
         2.     HIENR      HIEBO02     CustomerHierarchy 02
                 PRODH     PRODH       Product hierarchy
         3      HIENR      HIEBO03     CustomerHierarchy 03
                 PRODH     PRODH       Product hierarchy
         4       HIENR      HIEBO04     CustomerHierarchy 04
                 PRODH     PRODH       Product hierarchy
    I wonder if I can assign product hierachy fields, PRODH1, PRODH2, PRODH3 to access sequence like customer hierarchy so that the system can check higher level data to get the price...

  • Make-to order with production in alternative plant

    Hi,
    We are thinking about implementing a scenario with Make-to Order production for our products, but with production in alternative plant (special procurement type 80).
    For example, sales orders will be directed to plant A, but production should take place in plant B - and using a make-to order strategy (in our case planning strategy 50 - planning without final assembly).
    Is there any problems with our approach, making it not feasible to implement? Is it even possible in SAP to combine MTO with special procurement key 80 (production in alternative plant)?
    Is there any other issues that can be foreseen with using this type of production strategy?
    Thanks in advance,
    Lars

    Hi,
    The production strategy which you are going to use is very fine.
    As per me there is one concern. Example you have created a sales order in Plnat A, in plant A that FG is handling through Special procurement 80, then in the MRP run system will be creating a planned order in Plant B without running MRP in plant B. In MD04 screen you can see planning plant as Plant A. In plant B, u r converting this planned order in to Production order and executing the production. While doing the GR against the production order, the goods receipt will happen directly in Plant A.
    This is the one problem (Accountability)  you can face.
    Regards,
    V. Suresh

  • I have upgraded to Lion, and want to upgrade my iPhoto 8.1.2, but when I try it says it was not purchased at a MAC Apple store, which it was.  Then it asks if I want to buy 9.2.3, and I say yes. It responds with Product Distribution file can't be verified

    I have upgraded to Lion, and want to upgrade my iPhoto 8.1.2, but when I try it says it was not purchased at a MAC Apple store, which it was.  Then it asks if I want to buy 9.2.3, and I say yes. It responds with Product Distribution file can't be verified. Maybe damaged or not signed.  How do I get this fixed, so I can download the new iphoto's that are available.

    How did you move your iPhoto library to the new system?  the recommended way is Connect the two Macs together (network, firewire target mode, etc)  or use an external hard drive formed Mac OS extended (journaled) and drag the iPhoto library intact as a single entity from the old Mac to the pictures folder of the new Mac - launch iPhoto on the new mac and it will open the library and convert it as needed and you will be ready move forward.
    LN

  • Valuation with material cost estimate: error with product

    Hi Experts,
    Message no. KE350, Valuation with material cost estimate: error with product "2286940000". Please suggest me to resolve this issue.
    Points will be provided for good solution.
    Regards,
    Jay

    Hi Jaya
    This means that your customization is wrong then...
    In KE4J or KEPC you have assigned costing keys to your material types or some other combination... You should have done this config in a way that costing key is not called  for in the case of non valuated materials...
    In Ke40 you have defined costing key where in you have specified "Issue error msg if no cost estimate found".. This costing key is assigned in KE4J or KEPC in a way that it is getting called even in case of non valuated materials...
    Do you have a separate mat type for non valuated material? If yes, remove this mat type from KE4J/KEPC..
    If you dont have separate mat type i.e. in the same mat type if you have both valuated and non valuated, then you have a problem.. You would get stuck in that case
    Regards
    Ajay M

  • Valuation with material cost estimate: error with product "117122"

    Hi people,
    We have the error:
    =====================
    Valuation with material cost estimate: error with product "117122"
    Diagnosis
    In Profitability Analysis (CO-PA), the system tried to valuate a line item using the current standard cost estimate.
    In order to determine the current plan period, the system needs to read the valuation segment of the material master.
    The system has found that the current plan period is not filled forproduct "117122" in plant "UBE1".
    We have the follow configuration in trans.: KE40:
    . Determine material cost estimate
       . Transf. Standard Cost Estimate
    . Costing Variant
    . Control Data for Standard Cost Estimate
       . Period Indicator = "Current Standard Cost Estimate acc. to entry in mat master
    . Addiitonal data CO-PC
        . Transfer cost estimate in controlling area currency  "activated"
    We think the reason about our error is because the field above is activated and some configuration more is necessary for this case. For examplo: Trans.: OKYW and this one was not configurated yet.
    Do you know what happend?
    If we need to configure some transation, or sonly process the cost estimate?
    Thanks,
    Rosana.

    Hello Guido
    Thank you very much for your return.
    It is happenning in a Client that some people are doing the configuration.
    Before we didin't have in KE40, the fiel "Transfer cost estimate in controlling area currency" activated.
    And now, the people activate that in this new Client and I don't know the impact about that.
    I think we have to make the configuration in OKYW.
    The other transation you told me, we don't have any information.
    Could you tell me some other idea what happend?
    Message error is just "Message no. KE350"
    Abou claculate the cost:
    It was calculated by trans.: CK11N for future planning and the real wasn't not possible to release because this material already have moviments.
    Could you tell us is there is some thing more to do?
    Thanks,
    Rosana.

  • Valuation with material cost estimate: error with product " 200038 "

    Hi,
    I am getting an error:
    Valuation with material cost estimate: error with product " 200038 "  (Message KE350).
    Kindly assist on the same?

    If this material is mto material go to t.code KE40 and maintain define access to standard cost estimate define cost key with
    "Transfer sales orde cost estimatex".
    If it is mts material define costing key with Transfer std cost estimate  and in costing data
    costing variant : ppc1
    costing verstion: 1
    period  indicator:  Release std cost estimate matching with goods issue or material costing matching posting date.
    This will resolve ur problem.