Hi Experts,
We are using WBS Elements in Procurement Process, When we creating PR with account assignment to WBS with Category P
System is checking Budget and availability control is working fine but when i Creating PR against the AA Category Q
System is not checking the Budget Availability Control
Please help to fix this issue.
Regards
BK

Hi Barath,
I believe that your configuration is such that the inventoried materials are not taken under commitment whereas the direct costs/expenses are taken as commitment lines.
All you need is to check if a cost element is create for the G/L that appears while you are creating PR or PO. If no cost element exists, then system will not check with the Budget.
I will give you a simple example to understand this:
Make a PO with acc *** cat "P" and see the account assignment tab. Now see the G/L. Make a note of it. Now enter the WBS in the relevant section and you will find that the G/L has changed. If you check that G/L, a cost element will be assigned to that.
Now again make a PO with acc *** category "Q". See the Account assignment tab. Note down the G/L. Enter the WBS element and you will find that the same G/L appears again. If you analyse that G/L, there will be no cost element created for that.
The G/L basically appears based on the Automatic Account Determination by your MM/FI Consultant against the Relevant Transaction Keys.
Hope it helps you.
Raghav

Similar Messages

  • Budget check for purchase order

    Hi everyone!
    We have NO problems with budget check for the SC. But when we create a PO and exceeds the budget no message are displayed. The only thing that happens is that the PO gets status "error in process". But if we change the PO (still exceeding budget) we receive a correct message. Is this a program error?
    Sincerely
    Anders

    Hi
    Temporarily deactivate budget check: SRM: using Badi
    BBP_BUDGET_CHECK, AVC Backend customizing.
    Did you do budget check while creating sc? what did it says?
    Refere this old notes.
    Note 740933 - Incorrct purchasing budget for currencies w/o decimal
    places
    Note 747143 - User purchasing budget in pop-up incorrectly formatted
    regards
    Muthu
    Edited by: Muthuraman Govindasamy on Nov 5, 2008 3:08 PM

  • Budget check for PO based on delivery

    Hi,
    Can some guide how to configure budget check for purchase order based on supply schedule.
    This could be that you have raised a Purchase order for 12 Quantity and the delivery of the same is at 1 per month for 12 months.Budget should  be checked for one quantity for one month and not based on Purchase order which is for 12 quantity.
    We are using Former budgeting.
    Regards,
    Gokul

    Hi,
    I'm afraid you will have to create 12 items within the same PO and assign different delivery date to every one of them; then, the budget will be affected accordingly.
    Regards,
    Eli

  • No budget checking for batch input

    Hi people
    We are using the budget checking functions under Funds Mgmt (Former Budgeting) ECC6.0. Is there a way that we can exclude budget checking for postings done through batch input?
    appreciate any help.
    TQ
    darth maut

    Hi,
    Please check the SAP note 573409
    Regards,
    Abhijit

  • Budget checking in item category U

    Dear sapient
    I am posting a PR  document in ME51N for stock transfer with item category U. But system is not checking the budget.
    I saw in FMRP_RW_BUDCON line item has been created in document journal as Zero value.
    Please let me know whether budget checking is possible for item category U or not. If it is possible then please suggest me.
    requirement is for stock transfer for internal consumption through me51n.
    ECC6 EHP4 fund management is active.
    Thanks & regards
    Soraj

    Dear sapient
    Thanks for the reply i had gone through the sap note, but in my case i am creating PR in me51n not getting any bug.System creates the pr and deriving the fund center and commitment item but when i saw in the report in document journal, line has been created against the PR but not reducing the budget value
    Regards
    Soraj

  • Budget checking for Purchase Order

    Hello All Experts,
    Project Availability control: Tolerance limits
    on All activity groups - warning message for 101%
    on Purchase requisition - warning message for 101%
    on Purchase Order - error message for 101%
    1. Now we created a project with 5000 budget and Availability control activated.
    2. We assigned material to activity and created Purchase requisition for 6000. Here system issued message there is error in commitment and allowed us to save the project.
    3. We created Purchase order for 6000, system is allowing to create, that is any thing less then PR value, even though it is more than 101% and suppose to give the error.
    How do we over come this situation and make the system to look Budget value not the PR Value.
    Thanks,
    Karthik

    Hi,
    you have maintained activity groups ++ so system is considering All activity groups first for budget check instead of individual activity groups(PR,PO...). remove the ++ activity group and maintain individually(PR,PO,GI...) and check.
    regards

  • Budget checking for services with "Unlilmited" indicator set

    hi friends,
    Under normal cases, the budget checking is happening properly for the services in a project.
    But I have certain service activities where I require to set the "Unlimited" indicator set (in the service specification screen)and some other services where I set a value limit to the unplanned services (in the Limit section of the service specification screen).
    In these cases, the budget checking is not happening as expected by the standard methods. Please note that the availability control is active.
    Please help me out.
    regards
    Pratap.V

    Hi Nitni,
    Thanks for the prompt replies.
    Now you have struck the point. Assume I have a budget of rs.50000. The planned services in PR is of Rs.20000 and I have set a limit of rs.50000 for the unplanned services in the same PR. Now my commitment is Rs.20000 only which is right.
    In our specific case, the budget check will not happen at PR.
    Now I am creating a PO of the above PR. So PO commt is rs.20000.
    After this, when I go to the service entry sheet and enter a planned services of rs.20000 and unplanned services of rs.40000 (remember i set a 50000 limit for unplanned services in the PR). Hence my total actual cost is rs.60000. Obviously I want the system to do a budget check here and stop the user at the time of service entry sheet. But this is not happening. The budget check is not happening at service entry sheet if I am having any unplanned services in the PR or if I tick the "unlimited" indicator against a particular service.
    Hope I have put my point clearly.
    regards
    Pratap

  • Internal Order Budget Check for PO with reference to PR / RFQ

    Hi All,
    I have a scenario where the budget availability control is not working for PO created with reference to PR or RFQ. While creating the PO if i modify the PO value more than RFQ or PR value then system is looking for budget control.
    If we create a direct PO system is checking for Budget control where the PO value is more than availability budget.
    We have the budget control check with internal order for services and non stock material based on substitution rule created for cost element group and cost center group.
    In tolerance limits budget availability control we have not activated for PR, itu2019s activated from PO.
    Kindly let me know what is the reason for budget availability control is not active where the PO is created with reference to PR or RFQ.
    Thanks & Regards,
    Rama Mohan

    493900 - FAQ: Release Strategy:
    It is not possible to create a purchase order if the referenced purchase requisition is not released. But the system allows you to put the purchase order on hold and then release the purchase requisition.
    On the other hand you can create a purchase order with reference to an unreleased request of quotation.

  • Budget check for a Training Event

    Hi,
    My client has departmentwise budgets for Training. They want a budget check when the Training Event is being creating in SAP. If the training costs exceed the remaining training budget of the department, the system should not allow it. How to achieve this?
    Please help.
    Regards,
    Sasi.

    Hi
    Temporarily deactivate budget check: SRM: using Badi
    BBP_BUDGET_CHECK, AVC Backend customizing.
    Did you do budget check while creating sc? what did it says?
    Refere this old notes.
    Note 740933 - Incorrct purchasing budget for currencies w/o decimal
    places
    Note 747143 - User purchasing budget in pop-up incorrectly formatted
    regards
    Muthu
    Edited by: Muthuraman Govindasamy on Nov 5, 2008 3:08 PM

  • Budget check for Inventory PR

    Hi all,
    Can anyone explain me how the inventory checking (budget check) happens for inventory PR before the PR is tranferred to SRM?

    Hi Gurus,
    Please advise.

  • ATP check for item category TAB

    Folks,
    we have item category TAB on our back to back sales orders and will create an individual pourchase order.
    However, there are occassion when there is stock and we want the ATP check to consider and not necessarily create a purchase req.
    is there any way to achieve this?
    Or because TAB has Special stock indicator "E" type it is standard SAP and will always not consider stock?
    Thanks

    The purchase requisition is automatically created, there's no availability check behind item category "TAB". The stock is managed in the special stock segment (sales stock).
    If the case when the stock is available is exception, you could change the item category manually to a normal one (e.g. TAN).
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/48/66b65334e6b54ce10000000a174cb4/content.htm?frameset=/en/51/66b65334e6b54ce10000000a174cb4/frameset.htm&current_toc=/en/30/67b65334e6b54ce10000000a174cb4/plain.htm&node_id=186&show_children=false

  • Budget check for PM orders with main and sub-projects

    Hello
    We have a scenario wherein we have created a main project and a sub-project. We have linked the sub-project to main project. We have also assigned budget to the main project. We have created a PM order wherein we are trying to enter the costs by entering the hours of work. We have configured the budget profile and set the tolerance limites and assigned to main project. The requirement here is we need to have have costs check againt the budget that been available in the main project. But the system is checking the budget of the sub-project. Please share if any specific setting is required to check the budget of main project instea sub-project.
    Regards,
    Basav

    I also double checked, you are right there is no forum for PM, I dont think I could suggest much since there isnt a dedicated forum, but you can try posting this query in the ABAP forum probably some abap'r who has worked with PM module should have a look. Also if possible try to connect with one of the moderators out here and ask for assistance in starting something for PM
    Thanks,
    GLM

  • Budget Check for Stock Materials

    Hi SAP Community,
    I would appreciate if anyone can guide me how to check budgets in case of stock materials against CO order at the time of purchasing and/or at goods issue to cost center using movement 201.
    Thanks
    Atif

    Refer this:
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/a9/ab7721414111d182b10000e829fbfe/content.htm

  • Checking for Equipment Category

    I need to create a role that will allow certain people access to certain equipment categories but I don't think this could be done. Has anyone done this? Is there any way to do this?
    I also found a BADI called INST_AUTHORITY_CHECK which I think might help but how do I activate this? I'm using ECC6 and couldn't find it in SPRO.
    Any other suggestions on how to do this role is greatly appreciated.

    Hello ,
    We can assisgn Insusrance Tab to Equipmnet , Please create the Charactetics name with Insurance using CT04  with Characteritic Value enter YES or No, Create one class using Cl01 , Then assign Characteritic Insurance to Class, then assign clss toequipmnet.
    Thanks
    Monark

  • I need the BADI or the way for WBS budget check at SC line item

    Hi SRM folks,
    Do you have any BADI or the good way to do the WBS budget check at SC line item level.
    Donot suggest me the BBP_BUDGET_CHECK.ie for SC level only.
    Is there any way to do at line item level.
    Thanks in advance.
    srini.

    Hi
    Either use BBP_ITEM_CHECK_BADI or BBP_DOC_CHECK_BADI.
    Note -> Please read the relevant standard SAP documentation provided in this case for using SE18 Transaction.
    <b>Please go through the following pointers, which will definitely help -></b>
    Re: Reg the budget check in Shopping cart
    Re: Budget analysis
    How to implement the badi BBP_DOC_CHECK_BADI??
    Budget check for service PO
    Budget Check error for Fixed Assets ? :-(
    <u>Other related links -></u>
    Budget Check
    http://help.sap.com/saphelp_srm50/helpdata/en/4f/b3e739e62b714be10000000a114084/frameset.htm
    http://help.sap.com/saphelp_srm50/helpdata/en/de/237440116fd279e10000000a114b1d/frameset.htm
    http://help.sap.com/saphelp_srm50/helpdata/en/4e/1d74eff196d64e880fd28d41d4502b/frameset.htm
    http://help.sap.com/saphelp_srm50/helpdata/en/5a/af5eff85d011d2b42d006094b92d37/frameset.htm
    Do let me know as well.
    Regards
    - Atul

Maybe you are looking for

  • How can I delete photos from my iPhone5

    Photos take up most of my memory so I would like to free it up.  Even though I can delete one photo at a time, I haven't figured out how to delete them all at once.

  • AED not appearing in PO.

    We are using TAXINJ, AED condition type appearing while maintaining tax code, but in PO, value is showing as 0%. As for BED we maintain value %ge in J1ID eg 10%, whr to maintain this for AED or SED. in J1ID last tab is having this option but it doesn

  • Do we require an OLTP DB and Data Mart?

    Our data sources are as follows: - An mdb file (downloaded every hour) - Multiple xls files (downloaded every week) Our aim is to develop a BI solution using BISM, Data Mart, OLAP cubes etc. From my understanding, we do not necessarily require an OLT

  • Answer Message without Carrier Silliness

    My first iPhone was a 3G. When I created the answer message I was given the option of not having the AT&T "Leave your message after the beep..." time waster and minutes-used booster. I'm now on iPhone 5, and my answer message still does not include t

  • Clicking problem on popup menus

    When I am on the Amazon.com home page and I click on a sidebar menu a cascading popup menu appears. When I click on one of the popup menu items, the click registers on the graphic behind the menu, which takes me to the page related to the background