Cache directory of Project Pro 2013 connected to Project Online

Hello,
Where is located the local Cache directory for Project Pro 2013 connected to Project Online ?
Thanks

Check here
HKey_Current_User\Software\Microsoft\Office\15.0\MS Project\Options
once you will be in Option --> Save --> Cache Location -->Click
on Browse 
You can also try form Open MPP --> File --> Option --> Cache location --> Click on Browse 
kirtesh

Similar Messages

  • Project Pro 2013 with Project online

    I want to confirm that Project Pro 2013 can connect to Project online in the same way that Project Pro for O365 does. In other words, is it largely a licensing difference in the way the two products are licensed?

    Hi,
    See my reply about a similar concern: 
    http://social.technet.microsoft.com/Forums/projectserver/en-US/85889598-c54f-4168-a662-91b77211f81f/how-to-work-with-status-date-and-option-reschedule-uncompleted-work-to-start-after-in-project?forum=projectserver2010general
    And a useful reference:
    http://blogs.technet.com/b/nitinsha/archive/2013/06/24/project-online-or-project-server-2013.aspx
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project Pro for Office 365 vs. Project Pro 2013

    Hello,
    As I already have Project Pro 2013 installed on my PC (which is able to connect to Project Online) I'm not sure if the MS Project I'm using is Project Pro for Office 365 vs. Project Pro 2013.
    Is there any difference in the interface of the 2 products, as there is a noticeable difference between Word 2013 and Word Web App?
    Thanks

    Hello,
    Project Pro 2013 is the same product as Project Pro for Office 365.
    Word 2013 and Word Web App are totally different, Word Web App is web based, Word 2013 is the client tool.
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • MS Project Pro 2013 won't activate on Win 8.1 Pro

    Hi there. I'm trying to install Project Pro 2013 and Visio Pro 2013 (both MAPS apps) to a Windows 8.1 Pro machine. It has a copy of Office 365 installed just in case that makes a difference. It's also using a domain login.
    Anyway, If I try to activate, the key seems to be accepted but it doesn't 'stick' and once the app closes down I need to reactivate again.
    Using the product key, I've tried activating at...
    The First dialog when opening the app
    At the "PRODUCT NOTICE. Project hasn't been activated..." bar
    Programs and Features > MS Project Pro 2013 > Change > "Enter a product Key"
    None of which work.
    I've also tried
    Uninstalling and reinstalling
    Using our MAPS account login (something I'm trying to avoid)
    Attempting the above activation in Administrator mode where possible
    Is there anything else I can try?

    Hello Daleos
    That is very weird indeed. I don't have a good answer. Make sure that Office and Project are using the same bit version.  Don't mix.  For example if office is running 64-bit then make sure that Project is 64-bit.
    Cheers!
    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

  • Date and Time Submitted in Task Notes to show in Project Pro 2013

    I wonder if anybody could assist.
    I am running PWA 2013 and Project Pro 2013
    When a resource updates a task on PWA and creates/updates the notes on the task, it pulls to the notes section for the task in Project Professional.  This is great but…
    Is there a way to pull the Date and Time Submitted next to the resources’ name in the note too?
    I would appreciate any assistance.
    Many Thanks :)

    Hi,
    I don't think this is feasible out-of-the-box. Note that the information is available in the task details when you click on the task (either in the task update page or in the approval center).
    A workaround would be to train the users to start their comments by typing their initials and the date-time.
    Another way more complex would be to do some custom code.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project Pro 2013 60 Day Trial....didn't last 60 days

    I download and installed the Project Pro 2013 60 day trial and it disabled most of the features after about 7 days. Does anyone know if this can be fixed so that I can use the entire 60 days?
    Many thanks in advance if you know the answer.

    Soloanom, I anticipate you might be bounced around with a problem like this, but I think that what you're experiencing is due to the design or a problem with the project product itself, and so you'll need to ask the office experts over in the office-related
    forums for assistance.  
    Unfortunately your post is off topic here, in the TechNet Site Feedback forum, because it is not Feedback about the TechNet Website or Subscription.  This is a standard response I’ve written up in advance to help many people (thousands, really.)
    who post their question in this forum in error, but please don’t ignore it.  The links I share below I’ve collected to help you get right where you need to go with your issue.
    Soloanom, the two links in this paragraph are your best bet: For technical issues with Microsoft products that you would run into as an
    end user of those products, one great source of info and help is
    http://answers.microsoft.com, which has sections for Windows, Hotmail,
    Office, IE, and other products. Office related forums are also here:
    http://office.microsoft.com/en-us/support/contact-us-FX103894077.aspx. 
    For Technical issues with Microsoft products that you might have as an
    IT professional (like technical installation issues, or other IT issues), you should head to the TechNet Discussion forums at
    http://social.technet.microsoft.com/forums/en-us, and search for your product name.
    For issues with products you might have as a Developer (like how to talk to APIs, what version of software do what, or other developer issues), you should head to the MSDN discussion forums at
    http://social.msdn.microsoft.com/forums/en-us, and search for your product or issue.
    If you’re asking a question particularly about one of the Microsoft Dynamics products, a great place to start is here:
    http://community.dynamics.com/
    If you really think your issue is related to the subscription or the TechNet Website, and I screwed up, I apologize!  Please repost your question to the discussion forum and include much more detail about your problem, that could include screenshots
    of the issue (do not include subscription information or product keys in your screenshots!), and/or links to the problem you’re seeing. 
    If you really had no idea where to post this question but you still posted it here, you still shouldn’t have because we have a forum just for you!  It’s called the Where is the forum for…? forum and it’s here:
    http://social.msdn.microsoft.com/forums/en-us/whatforum/
    Moving to off topic. 
    Thanks, Mike
    MSDN and TechNet Subscriptions Support <br/> Read the Subscriptions <a href="http://blogs.msdn.com/msdnsubscriptions">Blog! </a>

  • How to make Project Template in MS Project Pro 2013

    Dear All,
    is there any method by which Standard Template can be build in MS Project Pro 2013 as Global Calendar etc?
    As far as i know, we can do this in PWA once we made EPT but looking something by which if project manager wants to create any project then he can choose such template in MS project Pro 2013 itself?
    Is there any way?

    Just to add on to Guillarme's reply, this might help, if you want to create projects and templates directly in Project Pro 2013, this might help:
    http://epmainc.com/blog/creating-project-templates-microsoft-project-2013
    Cheers,
    Prasanna Adavi, Project MVP
    Blog:
      Podcast:
       Twitter:   
    LinkedIn:
      

  • MS Project Pro 2013 - Auto Level (Not responding)

    Hi,
    One of our users has an issue in MS Project Pro 2013 with Automatically levelling (See below). Can anyone suggest what the possible cause of this is? The user is running Windows 8.1 Pro and more than enough RAM + Graphics card is fine.
    I would start with the both the Resource Pool and Sharer projects open (as I’m supposed to).  When I select ‘Auto Level’, MS Project would then turn the mouse
    into a swirl circle and state (Not Responding) at the top of the page.  If I hovered over the MS Project symbol pinned to my task bar, I would notice that it had opened a third window, though I couldn’t see what that project was as it was greyed out. 
    I tried this a number of times and had the same result.
    Thank you

    Intellitrain --
    Given the fact that no one else has replied to your post, let me just take a stab at it.  A couple things come to mind:
    Is the project in question a LARGE project with a large number of tasks and resources (maybe numbering in the thousands of tasks and resource assignments)?  If this were the case, leveling all overallocations at once would take a long time, which could
    be why the software seems to go into Not Responding mode.  By the way, I have seen Not Responding messages a lot in Project Server 2010 and 2013 when opening a very large enterprise project.  Microsoft Project shows the Not Responding message, even
    though it is actually working at opening the project.
    If the project is not a large project, but is smallish in size, then the user might try opening both the project and the shared resource pool file in Read/Write mode, disconnecting the project from the shared resource pool file, saving and closing both
    files.  Then the user should reopen both the project and the shared resource pool file, reconnect them, and save both of them again.  Then try leveling.  Does the problem still occur.
    If this does not help, there is a possibility that the project is corrupted.  If this is the case, the user should disconnect the project from the shared resource pool file and save it.  Then the user should save the file as an XML file and close
    the project.  Finally, the user should open the XML file and save it back as an MPP file.  This is how to resolve a corrupted MPP file.
    Just a few thoughts.  Hope this helps.
    Dale A. Howard [MVP]

  • Cut and Paste with MS Project Pro 2013

    We have and issue where if we try to Copy and Paste a task in MS Project Pro 2013, the PASTE option is not highlighted and we cannot do this. We can copy and paste field in the project but not a task. The task include enterprise fields and I tried to Cut
    and Paste even in off-line mode and it does not work.
    Anybody has an idea?
    Thanks

    Hi Johan,
    This normally happens when a sort is applied to the view. Sorting by ID then solves the problem.
    Greetings,

  • Project Server 2013 - Graphical Indicators - Not showing until the project is published via Project Pro 2013

    Greetings -
    I have a custom field on a PDP that is used to manually flag a project for review.  Once the field is set to "Flag" a red flag should show on the Project Summary page prompting the Portfolio Manager to follow up.  The red flag only appears
    after publishing the project via Project Pro 2013 not by just editing the PDP via Explorer (Save and Check in).
    This occurs on both projects that were created prior to the graphical indicator being added to the PDP and new projects.
    Now if instead of using the red flag graphical indicator I just used the text "FLAGGED" that would work fine.
    So is this a bug?  Or is something setup incorrectly?  Or is this how PWA is supposed to handle graphical indicators on the project summary page?
    Any help would be much appreciated.

    Hi Gunnery,
    I made the following test: I create 2 project ECF both inserted in the Project details PDP:
    for review: flag type field with graphical indicator in case value = yes
    for review_2: text type field (with a yes/no look-up table) with graphical indicator in case value = yes
    Whitout going to Project Pro, I'm able to modify the 2 fields for any project (created before or after the ECFs creation) and the graphical indicators are instantaneously shown in the summary project center view (just pressing F5).
    Note that the graphical indicator is not shown in the PDP, just the text value. Note also that I've not been to Project Pro neither to PWA/schedule PDP to publish the project plan.
    Then
    Does that correspond to your need? Can you reproduce this example and validate wheither or not it works.
    Guillaume Rouyre - MBA, MCP, MCTS

  • Saving MPP to SharePoint 2013 site from Project Pro 2013 fails

    When syncing from MS Project Pro 2013 to SharePoint 2013 it does not save the MPP file in the Site Assets
    Have MS Project Pro 2013, SharePoint 2013, IE 9, Windows 7
    The scenario is as follows.
    1. Have a SharePoint Project site
    2. I open up the task list in the SharePoint site and added tasks just using the available default fields that are provided. NO external links
    are in the task list.
    3. Selected the Open with MS Project option in the task list ribbon. MS Project 2013 launched from my desktop with the task list opened in it.
    4. In Project selected the Sync with SharePoint option and it did sync successfully with task list but it did NOT save the project file in the
    SharePoint site.  In addition, No error or warning message appeared.
    5. Selected Save button in MS Project – again it did not save to SharePoint but instead brought up the Save As screen again.

    Karen,
    To the best of my knowledge synching a Project file with a SharePoint task list and saving the project file to a library on SharePoint are two separate processes.
    You may synch the file to the SP list and then save the Project file to a library.  Are you using Project Server?

  • Project Server 2013 - Cannot see project schedule in PWA

    Project Server 2013 and Project Pro 2013
    I have admin authority but for some of the projects loaded to the server, and published, i cannot see the Schedule option in the left frame. At least on project has this option available but several others do not. For the projects where I can't see the schedules:
    - Some of these projects were created with imported MPP files from Project 2010, and imported using the wizard,
    - Some were created with imported XML files from Project 2010, and imported using the wizard
    - Some were created with Project Pro 2013 and saved, published to the P13 server.
    Are there some obvious things that I should check as a new admin to this version of Project Server? I'm stumped.
    For all of the above projects (with the issue or not) I can succesfully see everything in Project Professional 2013, and everything seems to function normally in the publish process.

    Hi,
    the first thing to check would be the EPT (Enterprise Project Type) of those projects. Go to server settings, Enterprise Project Types, select the appropriate project type and ensure that the Schedule page is on the left side of the section "New Project
    Page/Project Detail Pages".
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, MCP |

  • Using sharepoint designer 2013 - connected to sharepoint online - but getting " data source file cannot be saved" after making a new linked datasource

    using sharepoint designer 2013 - connected to sharepoint online - but getting " data source file cannot be saved" after making a new linked datasource

    Hi,
    Based on your description, I have done a test and I can’t reproduce your issue.
    I have used SharePoint Designer 2013 to open a SharePoint Online site and there are no issues.
    I’d like to clarify whether you encounter any issues when accessing SharePoint Online sites. If there are no issues during the accessing procedure, SharePoint Online service should be working fine at your side. The issue may be caused by specific SharePoint
    Designer client or network. I suggest you refer to the following steps to troubleshoot the issue.
    1. Use SharePoint Designer to open another site and check whether it is successful.
    2. When you are prompted to enter Office 365 account and password, try other users’ accounts and select the remembering the credential.
    3. Perform the connection procedure under another environment and verify whether the issue is resolved.
    If the issue persists, can you provide related screenshots for further troubleshooting?
    Best Regards,
    Lisa Chen
    Lisa Chen
    TechNet Community Support

  • Project Pro 2010-hide closed projects?

    We would like to hide closed projects from the project pro listing of all projects in server, but still have data show in our SSRS reports that we have created.
    I've been able to hide closed projects in PWA project center view but not having luck with Project Professional Server version 2010
    Ideas??
    Debbie (Clary) Dixon

    Hi Debbie,
    Here is a proposal to archive closed projects without deleting them, so you can include them in the reporting.
    You can create a dedicated group and category.
    First, create the security and the group:
    create a security group for non-admin users
    create an archive security category, associated with the new non-admin group. Refuse all the cross autorizations between the group and the category. In the "projects" section, check the box "only designated projects" (or however it is named in your langage),
    and do not check any box after.
    Now the archive process must be as followed:
    unpublished all project tasks, inserting the "publish" column
    in PWA, close to update all project tasks to prevent users to update task progress on archived projects
    add the project to the archive category
    The project is archived (unpublished and closed to any updates) but still in the databases, accessible in the reporting. At any time and for any reasons, administrators can "restore" the project by removing it from the archive category.
    Then you can put in place on a regular basis the usual process of physically deleting the archived projects once you're sure that they won't need to be accessed anymore and data are not needed anymore in the reporting. They still will be accessible by the Archived
    native DB.
    Hope this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • Project Pro 2013 client Deployment with Lync 2010 and Team Explorer Excel Issues Following

    Current machines are Office 2010 SP1 or SP2 32-bit
    Just deployed Project 2013 Pro and Std to the existing machines that had Project 2010 Pro or Std.  We selected the full install since people use integration into different tools.
    Results:
    lync 2010 64-bit when attending a meeting prompted user to start using and download the Lync Web Component, which breaks features such as muting, etc.  
    A repair sent to the workstations for Lync 2010 64-bit fixed that.
    Team Explorer 2012 Export to excel from queries gives error Unable to cast COM object of type 'Microsoft.Office.Interop.Excel.ApplicationClass' to interface type 'Microsoft.Office.Interop.Excel._Application'. This operation failed because
    the QueryInterface call on the COM component for the interface with IID '{000208D5-0000-0000-C000-000000000046}' failed due to the following error: The interface is unknown. (Exception from HRESULT: 0x800706B5). 
    Repair of Team Explorer, Office, Test Manager 2012, etc did not assist.  if we go into excel and connect to TFS, we can then retrieve the query data.  Just not from TFS exporting to excel.  Had to unload Project 2013, repair Office 2010
    and rebooted with project off the machine and now it works.   It seems maybe the setup with the shared features and Office tools are breaking something?  We need the ability for VBA and .net functionality, but what could be breaking this?

    Hi,
    Your environment will support 32 bit of Project professional 2013 (x86) as you have Windows and Office of (X86).
    You try to modify registry then you wont face issue.
     The issue when you hit a "1653" is that Windows
    Installer "DisableRollback" is set. Office 2013 requires that "rollback" be enabled. If you are getting a "1653"
    error in your logs as Ken did then the solution is to delete the "DisableRollback" (or set to '0') at the following registry keys:
    HKEY_CURRENT_USER\Software\Policies\Microsoft\Windows\Installer
    HKEY_LOCAL_MACHINE\Software\Policies\Microsoft\Windows\Installer
     these are the issues I've seen:
    Scheduler service was stopped. At a cmd window typing "net start schedule" resolves the problem.
    CMD.exe was customized via the following registry key. Solution was to temporarily disable the customization by changing autorun value to autorun_old. 
    HKEY_LOCAL_MACHINE\SOFTWARE\Microsoft\Command Processor
    HKEY_LOCAL_MACHINE\SOFTWARE\Wow6432Node\Microsoft\Command Processor
    Permission issues - seems some custom permissions affected Ingram's install which he explained in his previous post.
    Environment variable "ComSpec" had been modified (semicolon added). Fix was to remove the added semicolon (there should be no semicolon).
    The way to identify you are hitting this specific issue is if in the %temp%\OfficeSetup.log there is a mention of "Office64MUI.msi" failing to install with return value of 1603
    If you want to enable verbose logging via the following key, rerun your failed install, and collect all the setup and MSI* logs that will give more information.
    [HKEY_LOCAL_MACHINE\SOFTWARE\Policies\Microsoft\Windows\Installer]
    "logging"= "voicewarmup"
    kirtesh

Maybe you are looking for

  • External hard drive is not recognized after attempt to format

    I just got a new macbook and couldn't use my external hard drive because it was formatted on a PC and only allowed me to read the data. I backed up the data on the 250gb hd and then used Disk Utility to erase the hd and format it as "Mac OS extended

  • Acrobat 9.5.5 Windows 7 Page opens as a 3/4 page

    I cannot expand or minimize the page, the page is incomplete, and I cannot close the page without going to task bar.  When I click on Acrobat on the task bar, I then get one identical page over the other, again covering about 3/4 of the page.

  • Error : Invalid/unknown SSL header was received from peer

    Hi, I am having Weblogic 8.1 (SP5) Application Server running in US. I have a GUI application which is talking to this application server using SSL protocol. We have same SSL certificates installed machines from where this GUI application is executed

  • Quicktime error message.. can't update!

    I am trying to update my version of Itunes/Quicktime. However, when I run the update, I'm given this message and the update is aborted: The InstallScript engine on this machine is older than the version required to run this setup. If available, pleas

  • Subject Gets Overridden

    In my form, I specify the 'submit' email address and subject, yet when I test, a different subject ("submitting completed form") populates my outgoing email.  I have the form set to manually collect responses, and my response file is on network serve