I am using component backflush in REM to report my excess consumption of components. The mvt type used is 261 to cost collector. Lets say I do a component backflush for component C1 for qty = 100. I later realize that I entered 100 instead of 80. Is there a way that I can use the component backflush to to do a '262' of qty 20( 100-80) for component C1. In short I want to do a 262 for C1 against the cost collector.
thanks a lot

You can do it in MFBF with following steps
Backflush type – component back flush
Excess com consumption – select radio button Propose BOM acc bom. Enter zero qty here.
Click on document neutral reversal push button
Enter material/plant and other fields required and click on process comp list push button.
In the next screen system will propose all the components with zero qty. Enter 20- (qty with –ve sign) and post the document. This will give component qty reversal with 262 mov type
rajesha vittal

Similar Messages

  • Repetitive manufacturing activity and componenet backflush

    Dear experts,
    We use repetitive manufacturing. We use BAPI_REPMANCONF_CREATE_MTS for repetitive manufacturing. We have a requirement that to change the activity quantities and component in or before confirmation.
    Moderator message: not a proper question, please do more research before posting, show what you have done yourself when posting.
    Edited by: Thomas Zloch on Jun 27, 2011 2:56 PM

    anyone?

  • Repetitive manufacturing

    I have a  knowledge question regarding collective entry of confirmations using  repetitive manufacturing u2013 transaction MF42N.
    Is there an option to get data from planning table (MF50) pre-selected  to simplify final backflushing such as:
    Preselect all planned orders (PE) of a defined plant for a pre-selected planned production date  or all materials with planned orders for a defined planned production date shall be pre-selected.
    I donu2019t see an option to preselect open planned orders  for backflushing .
    I only see the option to manually enter either material or planned order for each single planned quantity from planning table. 
    It is vital  for the central kitchen food production process to be as simple as possible. 
    Whatever can be pre-selected improves usability of this process for Retailers significantly.
    rgds
    sandeep

    Hi,
    Your thought of having pre-select data like Planned Orders (PE) for a particular period in MF42N is really a good one... but I don't see any user exit/anything available for this.
    But this could be achieved by developing a custom report, in which you can first fetch data like Planned Orders for a particular period and then provide those details to MF42N through a BAPI.
    Again not sure how feasible it would be...
    Regards,
    Anup

  • Separated backflush in discrete manufacturing

    Hi All,
    Can we have option  of separated backfulsh in Discrete manufaturing?.It is used  Repetitive manufacturing.
    I want to do GR first and then GI/Activity posting differently.
    Regards,
    Vidya

    Hi,
    Yes this is very much possible.
    Follow below steps:
    1. Create a key to control the confirmation process. Transaction OPKC
    2. Assign this key to the desired order type by entering it in the Process control field under Define control parameters for confirmations. Transaction OPK4
    3. Make sure that the Parallelization type is defined under Parallelized confirmation processes for the processes that you want to parallelize.
    4. Plan the background job for confirmation processes under Plan background job for confirmation processes (program CORUPROC). You can create variants for the individual confirmation processes.
    Regards,
    Santosh Sarda

  • Options on BOM component backflushing (Repetitive Manufacturing)

    We are in the process of implementing Repetitive Manufacturing and we would like some insight regarding BOM
    component backflushing.
    Our requirements:
    1) In a scenario with insufficient unrestricted component stock the entire transaction should be stopped, including the
    Goods Receipt of the assembly. We do not want backlogs generated and we do not want a correction dialog box. We
    only want the GI of component stock to happen for exactly the exploded BOM quantity or not at all.
    2) No opportunity should be given for the end user to modify the GI quantity of the BOM components even if there are
    errors.
    Unfortunately I have not found a combination of configuration settings in the repetitive manufacturing profile that can
    completely satisfy those requirements. Several settings have come close or give us other means of controlling the
    process but none have been a perfect fit. We've also looked into setting the stock deficit message (M7021) to "E" but
    we are worried about compromising other processes with that approach.
    Can you please let us know what, if anything, we are overlooking and what options are available to us to meet these
    requirements?

    Dear Prasad,
    1.Check in the REM profile whether the check box for error correction in dialog mode is mandatory.
    2.Check for this authorization object,under the main object C_BACKFL,check for this object BF_POST ,check whether the tick mark
    is for all these values.1 Post without correction
    2 Display BOM/routing
    3 Change BOM/routing
    Better not include the tick mark for option 3 and i hope this will solve your problem,
    Check and revert
    Regards
    Mangalraj.S

  • Repetitive Manufacturing - Backflushing

    Hi Gurus,
    I am new to Repetitive manufacturing Scenario, I have created a planned order and then done the required steps of Backflushing and GR and completed that.
    After which I found that the components are not correctly consumed during backflushing. One of the component was consumed in less. Now I want to charge this remaining qty to that order.
    But when I try to do this using the same tcodes like MB1A, MIGO with 261 movement against that order, Error message "Internal Order..................."
    is displayed,
    Please let me know on how this problem can be solved, this may look silly, but being new to this scenario Can any one please help me.

    Hi,
    If you want to correct then you have only option to reverse the backflush from MF41 and perform the fresh confirmation (backflush) like same in production order confirmation cancellation and then re-confirmation.
    While reversing syetem updates the stock for components and for finished part its create planned order for reverse quantity (depends on rem profile settings).
    If any question then please inform.
    Regards
    TAJUDDIN

  • Can we use batch management in repetitive manufacturing?

    Can we use batch management in repetitive manufacturing?
    If not, can we use classification or something else?
    or what else options we have.
    Thnx!

    why not?
    http://help.sap.com/saphelp_47x200/helpdata/en/25/283c594f7811d18a150000e816ae6e/frameset.htm

  • Repetitive manufacturing:backflush

    Dear experts,
                      At my client place , repetitive manufacturing scenario is there.
    While doing back flush, I am facing an error "Argument 1061 not contained in table T437D"
                                     "Message no. RM001"
    Please guide me where I am going wrong in customisation.
    Regards,
    Sameer

    Dear Sameer,
    check for this 2 settings,
    SPRO-Production-Repetitive Manufacturing-Planning-Define scheduling parameters for Planned orders (OPU5),Check
    *whether for order type * or for order type PE - Run Schedule*Quantity for Plant RA01 whether you have maintained the
    relevant required parameters.
    Then also in SPRO-Production-Repetitive Manufacturing-Planning - Planning Table-Maintain distribution for Planning
    table whether you maintained the setting for the plantRA01.
    Once after doing this setting,it gets updated in table T437D.
    Regards
    Mangalraj.S

  • WIP FOR REPETITIVE MANUFACTURING WITH VALUATED SALES ORDER

    Dear All,
    We are in the process of implementing Repetitive manufacturing with valuated sales order(MTO). I want to clarify whether in this scenario WIP will be generated.
    Since, at the time of final backflushing, what ever GR done for finished goods, the GI for its components will be done automatically. The components will be issued based on the BOM. I think in this scenario WIP will not be there.
    Please tell me whether i am correct.
    regards
    ranga

    Thanks. I have another scenario. My client wants to transfer all cost of HR,Admin, finance etc and other indirect production cost center cost to production cost center. I mean they want to charge on the product. I have to production cost center. Client will give me the basis for allocating the cost. I have to do assessment and distribution for cost allocation
    But, I want to clarify how do i include the admin, hr or finance and indirect production cost center cost in cost component structure if i do the above process.
    How to do the cost splitting.
    regards
    ranga

  • Repetitive Manufacturing Scenario

    Dear All,
    I would appreciate it if you can provide me with a FLOW of REM, a walkthrough guide with transactions to test the REM scenario and pre-requisites of each transaction.
    Thank you

    Dear,
    Reporting Point Rem
    Steps are as,
    1)You must assign a suitable repetitive manufacturing profile in the material master record to be able to backflush a material using either the mandatory or the optional reporting point backflush function.
    2)You must set the optional or the mandatory reporting point backflush in the repetitive manufacturing profile.
    3)This type of backflushing corresponds to the milestone confirmation in make-to-order production. Therefore, in the routing, you must select a control key which has indicator 1 (= milestone confirmation) in the confirmation field.
    4)You must enter the routing in the production version of the material. The system first looks for the routing entered in the detailed planning section. If no entry exists here, the system then uses the routing from the rate-based planning section.
    5)You must carry out a version-specific or a standard cost estimate.
    6.You are recommended to use the version-specific cost estimate which can be carried out in shorter intervals than the standard cost estimate.
    Reporting point is a concept for REM. This is to be set up just like Milestone operation.
    Select the Control key which is relevent for Milestone confirmation like PP01
    or select a control key which is having the confirmtion selected as *1 - Milestone confirmation
    You need to select REM profile 003 or 004 from sttd REM profiles to have Reporting Point and in OP67 (Control key for Operations) you need to set confirmation to 1 - milestone confirmation .
    Please try and come back.
    Regards,
    R.Brahmankar

  • Repetitive manufacturing:subcontracting

    Dear experts
                  In repetitive manufacturing scenario, I have subcontracted my 4 of operations.
               Now the requirement is I want to create Automatic PR for those operations.
              So please guide me what are the necessary settings to be done.
    Regards,
    Sameer

    Dear Sameer,
    I doubt whether operation sub-contratcing is possible in REM scenario,i have not tried this,but in my understanding if you are
    using a reporting point backflush this may be achieved.
    In one of my project in REM scenario we used direct sub-contracting where this is possible.
    Also refer this thread to explore more,
    Re: Subcontracting in REM
    Correct me if I'm wrong.
    Regards
    Mangalraj.S

  • Query on Repetitive Manufacturing

    Hi PP GUrus,
    I have few queries on REM in PP.
    As in case of REM we dont have Production Orders we only have Planned Orders..Correct me if I am wrong..
    1) Can we calculate WIP in case of Repetitive Manufacturing. If yes then how and will it be calculated on Planned Orders.
    2) I need to do settltmernt in CO. For that the order to be used will be Planned Order or what is the process.
    3) Also if some one can give me a step by step process for REM then it will be really helpful.
    Regards
    Ashish

    >As in case of REM we dont have Production Orders we only have Planned Orders..Correct me if I am wrong..
    Its correct
    1) Can we calculate WIP in case of Repetitive Manufacturing. If yes then how and will it be calculated on Planned Orders.
    While doing settlement in KK87, WIP has posted to financial posting
    2) I need to do settltmernt in CO. For that the order to be used will be Planned Order or what is the process.
    YOu need to give Material and plant to run settlement
    3) Also if some one can give me a step by step process for REM then it will be really helpful.
    1)create plan MD61
    2) run MRP: MD02
    3) create product cost collector- KKf6N
    4) preliminary costing for PCC & costing is carried out In KKF6n
    5) Material staging: MF60
    6) Rem Backflush: MFBF
    7) Run Overhead- Co42
    8) Run variance- KKs6
    9) Run settlement- KK87
    display report of PCC0 -KKBC_PKO

  • Difference between Discerete & Repetitive Manufacturing

    Hi ,
    Can Any  one explain to  me about  difference between Discreet & Repetitive Manufacturing.
    Regards
    Goms

    Dear Gomathi Nayagam,
    Discrete Scenario:
    1.Order Based production & Product produced (Finished product) is changed more number of times.
    2.Order Based Cost calculation.
    3.Varying sequence of operations - complex routing.
    4.Material staging will be based on individual order.
    5.Order completion & confirmation carried out for individual order or operation.
    6.After MRP run Planned order's are obtained which can be converted into Production order (for E products)
    Required Master Data:
    1. Material Master
    2.BOM
    3.Work Center
    4.Routing
    5.Production version (not mandatory).
    REM Scenario:
    1.Period Based production where ceratin quantity is produced per period.
    2.Period based cost collection using Product Cost Collector.
    3.Steady flow through production - continous production - simple rate routing/routing.
    4.Material staging is done periodically.
    5.Production confirmation done periodically - Assembly backflush.
    6.After MRP run Planned order's are obtained as Run Schedule quantity for Inhouse manufacured products
    which can't be converted into production order's.
    Required Master Data:
    1. Material Master with REM profile assigned for all the Inhouse Manufactured products.
    2.BOM
    3.Work Center
    4.Rate Routing.
    5.Production version & Product Cost Collector - mandatory - for all products (Inhouse manufactured).
    I hope this will give you a clear idea about 2 scenario's.
    Regards
    Mangalraj.S

  • Reports for Repetitive Manufacturing Process

    Hi All,
    Can any one please let me know the Reports FOr Repetitive Manufacturing (Like COOIS/ COOISPI)
    I could not find any such for Repetitive Manufacturing.
    I need to get the reports for below data.
    1. Goods Receipt in certain Period for certain Material with Certain Production Version
    2. Component COnsumed.
    3. Activities Consumed
    Please let me know the Tr.Code for these.
    Thanks and Regards
    Khadeer

    Hy Khadeer,
    MCP6  Goods rcpt analysis: repetitive mfg
    MCP8  Goods rcpt analysis: repetitive mfg
    MCRJ  Prod. Cost Analysis: Repetitive Mfg
    MCRK  Prod. Cost Analysis: Repetitive Mfg
    MCRO  Matl consumptn anal.: repetitive mfg
    MCRP  Matl consumptn anal.: repetitive mfg
    MFBF  Backflushing In Repetitive Mfg
    MFHU  Backflushing In Repetitive Mfg
    MFPP1 PackDemandMgt Repetitive Mfg: Plan
    MFPP2 PackDemandMgt Repetitive Mfg: Pack
    OKL4  Report Tree: Repetitive Mfg
    OKR2  Report List for Repetitive Mfg
    OKRM  Report Layouts for Repetitive Mfg
    OKS2  Generate Reports for Repetitive Mfg
    OKSB  Import Reports for Repetitive Mfg
    OKT5  Cost Comp. Groups for Repetitive Mfg
    OLIF  SFIS: Setup-Repetitive Manufacturing
    OPP3  Customizing Repetitive Manufacturing
    OPR4_ Repetitive Mfg and Process Mfg
    OSP2  Repetitive Mfg Profile
    OSP4  Repetitive Mfg: Distribution Functn
    OSP5  Repetitive Manufacturing: Cost Log
    OSPF  Repetitive Manufacturing Line Texts
    OSPT  Repetitive Mfg Profile Assistant
    OT81  Process Repetitive Codes
    Regards
    Dhaval

  • Repetitive manufacturing and 2 ways of manufacturing

    Hello,
    One finished product called A is manufactured using 2 different ways :
    -> one way is to use a supplied component B ( bought from a supplier )
    -> second way is to use a semi-finished product C instead of using the supplied component.
    the two ways can be used in the same time.
    How to manage this from the creation and management of the BOM and master data to the MPS/MRP in SAP in REPETITIVE MANUFACTURING ?
    Is there a best practice for that ?
    Thanks.

    1.You have to Create Alternative 01 & 02 for FG material.
    2.Create two routing if Production process is different using different BOM.
    3.Create the Version 0001 with 1st alternative & 0002 with 2nd Alternative.
    4.Then Create Product Cost Collector for both the Version.
    5.Run MRP. Planned Order will get generate.
    6.Specify the production version at the time of production booking. The material consumption and activity booking will be
    done corresponding to the production version specified.

Maybe you are looking for

  • Adobe flash player not support in android 4.1.2 samsung s2

    Plz give me feedback (private contact info removed by moderator). i have Samsung S2 Mobile. And i have android 4.1.2(Lastest S2 Version). I can install this software. but I cant see any LIVE TV CHANNEL. EveryWhere flash player required. And i READ so

  • Can I copy existing photos from pc to ipad and retain current folders?

    I have existing photos in folders on my pc, I want to copy them to iPad so I can edit them while traveling, then update them back to pc to print, etc. Is this possible and if so, how. Thanks!

  • Print to network printer on Headless Unix box

    Hi I have written an app which prints an image on the default printer of a headless unix box. I have been told that if I which to extend my app to print my document to a named network printer, I will need to get additional software. Is this true?

  • Regarding  Plsql tunning

    Hello Already One function had in database now days it takes more time to execute Please guide me how i tunning this code Please check my code I have check all code and indexces they are exactly pick up FUNCTION balances (p_set_of_books_id IN NUMBER,

  • Need a help with TransformGroup

    Tehere is code fragment: TransformGroup g1=new TransformGroup(); g1.addChild(cube0); g1.addChild(cube1); objRotate.addChild(g1); SimpleBehavior myRotationBehavior0 = new SimpleBehavior(g1); myRotationBehavior0.setSchedulingBounds(new BoundingSphere()