Cost element wise monthly budget
Hi,
I have put original budget on a WBS thorough CJ30.. Now i want to put budget for a particular cost elemtent monthwise for that WBS. How can i do this?
Regards,
Kalpesh
Dear kalpesh Agrawal,
Cost Element wise Budget is not there in SAP. these are the possiable soluation for your Quarry.
1. Cost Element wise Planning is Possiable, but is different from the Budget.
2. But a valadition for Each Cost Element to Internal Order link, then Create a Budget for Internal Order. in this way you will get
Internal Order Budget based on Cost element.
Revert Back.
Raj
Similar Messages
-
Budgeting -Internal order - monthly -cost element wise
Hi!
Got a problem! Want budget for single internal order - cost element wise. We created one employee as internal order. For this internal order, want budget for Telephone exp Rs. 500 /- per month, Travelling Rs.1000/- per month.
I checked in budgeting and came to know that we can budget for one internal order for one year not month wise. Another thing is we cannot budget cost element wise.
Is there any solution for this requirement. Pls. let me know.
I appreciate your efforts and thanks in advance.
- SRKAs you righly mentioned budgeting is not possible cost element wise/period.
If you want for planning/reporting purpose alone (and not for availability control) you can create a seperate plan version and use cost planning with cost element and period wise.
Regards
Sreenivas -
hello guru,
our client want to make the budget on cost element wise. is it possioble or not? if possible plz guid me how to configuration to be do.
Rega
laxmiHi Friends,
I have an option which i am guessing is in T.Code-7KE1 you can give ur controlling name> give the layout name>version>from period>to period>fiscal year>co.code>profit center>account number>free in Entry down>select in top 2nd buttion period screen (F6) and ENTER so now you can give ur budget cost element wise for each and every month.
Hope the explanation is clear.
Have a nice time.
KUMAR. -
Cost Center Budget-Cost element wise
Dear SAP Gurus,
My client needs to create cost center budgets cost element wise. For e.g. Salary paid (code 430000) in Development Cost center (code 9901).
We now use KPZ2 to create cost center budgets and KP06 for cost element planning. Kindly guide.
Regards,
SivaHi Ramesh,
Thank you for the reply. I did suggest them to use KP06 but they require some sort of validation when posting an expense (cost element) to and cost center.
For e.g. If the travel budget for Marketing cost center is $1000, they need the system to prevent posting once that amount is exceeded.
Any help in this regard would be appreciated.
Regards,
Siva -
COST ELEMENT WISE BUDGETING AND AVAILABILTY CONTROL
Dear Experts,
I am looking at Cost Element wise Budgeting and Availabilty control in internal Order, Availabilty control also should be Cost element wise.
Regards
DeendayalDear Surya Narayana,
Thanks for your prompt response, well i know that Budgeting is at summary level, want to just explore any other way out, is there any possibilty to link planning to budget as plannig is done on cost element wise.
you can also send me the details of budgeting and avaiilability control at dayal05 at gmail.com.
regards
Deendayal
Edited by: DEENDAYAL RAMACHANDRAN on Mar 3, 2009 2:15 PM -
Cost Center Report with Cost Element wise Subtotal
Hi All,
We have a requirement where customer wants a Cost Center report with Cost Element wise Subtotal and selection options required are Company Code, Cost Center, Cost Element.
KSB1 solves the requirement, but when executed for 2 or more company codes it is taking 3 to 4 hours.
The other alternative report we tried is S_ALR_87013611- Actual/Plan but this report gives debit and credit values in seperate columns.
Please let me know if we can copy the report S_ALR_87013611 and change it using report writer to have the output by Cost Element wise total.
Also please let me how we can increse the speed of KSB1 report.
Thanks
Satishfor KSB1 Report the following is my suggestion
1. Please go to the selection criteria for the cost elements and de select the secondary cost elements in the the exclude range and try running the report this is generate the report faster.
2. also check the date range please give the date range for 3 t months and if you want to run for multiple company codes. if you want to execute it for longer periods say 9 months or 6 months generate the report in 2 to 3 installments and download them to your excel and consilidate them in excel for your analysis
Best Regards, -
Dear All
Our client requirment is Cost element wise MIS report as per co.code wise for given below format wise
1. cost element group
2. Cost Element
3.Cost decription
4. Amount Prd 4
5. amount (1-4)
Pls advice.
Regards
avijitHi
Try report S_SL0_21000007 it may be useful
Regards
Sandy. -
Hai,
How to develope cost element wise report, i mean what are the tables and fields to be used for this.Hi,
Field - KOSTL - Cost Center
KSTAR - Cost element
Tables : CSSK
CSKS
CSKB
CSKT
CKIS
CKHS
BSEG
BSIS
BSAD
EKKN
Thanks,
Senthil -
Cost elements not appearing in report
Hi,
We have reports done in report painter. we use cost element group to retrieve the amounts posted to that group.
I added 2 more accounts to the cost element group and saved.
but it is not appearing when I run the reports which shows cost element wise amounst for teh period.
rgds
NehaHi sanjay,
thanks.
But GR53 gives me Library and report group.
when i go to GRR2, gives the library I see in GR53, and search report group in list of values ,
I am not able to see the report group as above.
When I manually type in it says
Report Y511 does not exist
Message no. KH 502
Diagnosis
You tried to change a row/column structure which does not exist.
Procedure
Choose an existing row/column structure or creating a new one using
'Row/column structure' -> 'Create'.
Pl advice.
thanks
neha -
Planning at cost element group level
Is it possible to plan values at cost element group level instead of at cost element level in CCA?
ThanksHello,
Yes it is possible. In t-code-KP06 Cost Center/Activity Input planning, we can select input values in the combination of individual Cost Center-wise OR Cost Center Group-wise and individual Cost Element-wise OR Cost Element-wise. Here if you give Cost Element Group as your input value, you can plan cost for each Cost Element.
Regards
appalas -
Sales Pricing without Inquiry using detailed Cost element Planning
Deal All,
I need to use use Sales Pricing without Customer Inquiry to Genrate Quatation from Project.
In my project client is asking to use deatiles cost element planning for same. So, let me know
Weather its possible to use Detailed cost element planning for doing Sales pricing in DP82
or Do we need to use ECP only to do Sales Pricing??
Also, let me know if there will be any change in RA method also.
regards,
AtulHi Atul,
You can use any of the cost planning method (i.e Details cost element planning, ECP or Network Costing) to create Quotation using DIP Profile.
Coming to the second point..any effect on RA calculation..This Quotation creation process is no where effects RA calculation.
basically for creating Quotation usign DIP Profile, there should be cost element wise planned cost required.
Hope this clears you...
regards,
Hari. -
Cost element group wise budgeting
Hi All ,
Can any one tell me how to do cost element group wise budgeting?
Thanks in advance,
ManishaHi
In transaction KPZ2 you can do budgeting for a group. However you need to actually budget for the elements in the group thereby consolidating for the group.
You cannot budget for a cost element group directly without budgeting for a cost element in SAP.
Anand -
Need a report for actual cost by WBS element by month
Hello all,
I am looking for a report that will give me the total costs charged to a series of of WBS elements by month. Does anybody know if such a report can be run and what the transaction number of this report would be?
ThanksHello Stacy,
Thank you for your help.
I tried the S_ALR_87100185 report as you instructed but I cant get it to display as I would like to see it. What I need the report to do is display actuals by month and WBS elemnts from January through August. However the report cuts off at the May period. Does anybody have a workaround so I can see the charges from January through August?
Thanks -
Exempted cost element not working for budget availability control
Hi,
I have configure the exempted cost element in our sandbox client. In the SAP IMG menu Project System -> Costs ->Budget-> Specify exempted cost element I maintain the following entry.
COAr cost element Origin Group
0200 433010 *
Then in the material master of a material I maintain the origin group in costing 1 view as 001. Then I do a material issue against the network of a WBS in MB1A tr code mvt type 281 and post the cost to the cost element 433010. As per the exempted cost element logic this should not affect the budget availability since the cost element 433010 is define as an exempted cost element. But the system shows actual incurrence for this transaction and reduce that must amount from the budget. I check this is the S_ALR_87013558 report. To re-ensure I do the Project Info database rebuilt in CJEN tr code then activate the availability control in CJBN but this is of no use. The S_ALR_87013558 still shows the budget available as total budget minus the cost incurred in the cost element 433010 in the above transaction.
Please let me know if anybody has configured the exempted cost element in their client and have resolve this issue.
Thanks and regards'
PreetamHi,
This is a std SAP Functionality and system should exempt the costs for the cost element maintained in the Configuration for that Controlling Area.
Muzamil -
Primary Cost Element Report - Cost Center wise Totals
Dear Seniors,
Requirement is to have a report which gives Cost Center wise Totals (Net posted amount) for Primary cost elements with the following fields --
Company Code
G/L account
Business Area
Cost Center
Accounting Period
Fiscal Year
Net Posted Amount
Debit / Credit Indicator
Currecny
Which Table gives me this information ?
Thanks and Regards
KVKRHi
If you are on New GL - Then FAGLFLEXT (Totals table)
If not - Then GLT0 or tables startng with GLT*
You can also use reports FBL3N and subtotal on Cost Element/Cost Center
br, Ajay M
Maybe you are looking for
-
Vendor Replication and Different Back-end Systems
Hello, Currently, we have vendor replication were the vendor number from the back-end is used in SRM-EBP. Now, we want add another back-end but there are vendor number conflicts. Is there a way to configure it so that the new back-end replicaition
-
Problems with german language in golive 9
hello i have problems if I want to past a text form word or another text editor into a new golive 9 html page. The letters like öäü are not shown correctly. what can I do?
-
My ipad got disabled, saying "ipad disable connect to itunes"
my ipad got disabled, i don't know hot it happens it's saying "ipad is disable connect to itunes" but itunes cannot connect to my ipad because it is protected with password... what should i do? i need help, can someone help me,,, pleeeeeeease
-
Report Painter - missing column in GRR1/GRR2 but appears when executed
Hi I have a report with 10 columns in addition to the first column that contains the descriptions of the rows, i.e. Sales Revenue etc etc. The columns across are different projects. However, most strangely, the first of the projects does not appear
-
Unable to create AAM,or Recurring Document/Sample document
Hi, I am not able to create AAM,or Recurring Document/Sample document, it comes up with a ABAP runtime error, dont know what to do, Can some one Advise? Regards, Raj