Cost of UNBW Material in Process Order

Dear Gurus,
We have created UNBW Material for Raw Water used in our production process.
(Since we dont want any accounting effect of the raw water we have created it as UNBW Material)
Now when I do costing of product X which uses raw water the cost of raw water is getting added to arrive at the standard cost of product X.
But in the process order report "KOB1" though PP has confirmed the material the cost of it is not calculated.
Please guide how to bring the cost of raw water in the actual process order report of product X.
Thanks and Regards,
Amit Dhanurdhari

Hi,
As you have mentioned that it is a UNBW material, it carries no value and in real time absorbed as some expenses.
There is no price for this material and there is no account to capture the consumption as this material goes directly
to expense account.  Apart from that you require that no fi entry is needed.  Let me put in this way now.
Create Raw Water Consumption as a secondary cost element.  Create Activity type Raw Water and assign this
cost element.  Define activity price for this activity type for a cost center through KP26.  Assign this activity in
a work center (this material need not figure in BOM).In OKTZ cost component structure enter this cost element
and assign it to Cost Center/Order.  In this you have only CO postings for the cost estimate and no fi postings.
Regards,
Sadashivan

Similar Messages

  • Cost of QC sample on Process Order

    When we are posting GR of our Finished or semi finished goods an inspection lot will be created. when we take the Usage Decision on this lot and took samples from the total and post the remaining quantity in unrestricted. the cost will be charged on Process order, which is wrong. we want that the cost should be charged on a QC cost center. when we take Usage Decision on raw and packing material the it always ask for the cost center and the cost is charged on that cost center. in case of finished and semi finished it is not asking. and if we forced it to a cost center it always charged it to a process order.
    1. explain me that charging of qc cost or sample cost on process order is standard?
    2. what could be the solution of this problem?
    3. what could be the work around of this?
    Do participate points are guaranteed on value added input.........

    Hi Syed ,
    In that case what I can think of is introduce a new operation as quality inspection in routing & then implemenent activity as activity cost for the same . Now confirm the operation & there you can capture the time spend in quality & translate that in amount through the activity pricing ......
    But in this also it will have effect in the order cost but you can differrentaiate the amount spend in mfg & amount in quality seperately...........
    Thanks
    Kaushik

  • Costing data from Tables of Process Order Confirmation.

    Dear Friends,
    In which table is the Costing relevent data for process order confirmation stored.
    We are developing a report for which we require  material specific-
    Target quantity / Actual quantity
    Target costs / Actual costs
    Thanks in advance.
    Regards,
    Vikrant Sood

    Hi,
    Using the Table : AUFM you can get the data.
    VVR

  • Reverse Material Ledger Process Order Revaluation

    Hello,
    I have settled process orders for Material Ledger and revalued them.  More postings have been made after this has occurred.  How do I reverse this process?
    Thanks for any help you can give me.
    Joe

    Hi
    Go to the following path in SPRO:
    Controlling -> Product Cost Controlling -> Actual Costing/Material Ledger -> Actual Costing -> Activate Actual  Costing. Double-click on "Actiavte Actual Costing" and change the indicator from "2" to "1".

  • Actual Cost & Quantity not update in Process Order

    HI,
    Process order confirmed from Production person before maintain the actity price rate.
    hence those confirmation are gone in to the error & found in t.code COFC
    afterword the activity rates are maintained & we reprocess those confirmation thorugh COFC, now there is no COFC entries
    but still actual quantity & cost not updated.

    Hi Ajay
    'Z_UPD_ACT_IN_OPR_UNICODE in the note 736018.... Ask your ABAPer to implement the program and execute the same
    You may need to raise an OSS message incase the program is not available to download
    BR,Ajay M

  • Batch Determination for material in Process Order

    Hello,
    I need to set up a Batch determination strategy for the Raw material at IM level for a Process Order.
    Basically the materials are Batch Managed and already have a Batch number assigned to it.
    I just want to use a simple strategy of determining material with the oldest GR datel(FIFO) during the Process Order creation/release or during the Process Order confirmation.
    Can you guide me how to set up the strategy and the conditions to do a FIFO for the materials during the Process order.
    Thanks in Advance
    SAP FANS....

    Hi,
    Only Problem with this FIFO strategy in which you want to do Batch Determination with reference to Oldest GR date is GR date itself.
    Batch determination will only possible if Batch Characteristic values are maintain.What I have observe for this GR date is if we use this as a Reference Characteristic in that case also Value is not set automatically in the Batch Data, so value of the GR date is maintain manually.Pls check it your end if no problem then The rest of the things for Batch determination are not difficult.
    Use below link for Batch determination,
    [Batch Management and Determination |Re: Browser Based PI sheet]
    Regards,
    Dhaval

  • Auto GR creation against PO after consumption of material in Process order.

    Hi GURU's
    My client is asking about automate GR against Purchase Order when he confirm the porcess order of GR consume material means when he confirm the process order, the GR is created for the comsume material( GR must be equal to consume qnty) against Purchase Order.
    1) Is thier any material type issue
    2) what are the setting need to be done
    Please take an Urgent action bocs its a critical point to me solve.
    Hope for the best for ur response.
    My ID:- [email protected]
    Thansks in to all
    Parminder

    Hi Guru's
    My Requirment is...............
    Suppose I have material  X (GAS) type ROH.
    I have already made  a monthy base Purchase Order this.
    We Get GAS through Pipe Line.
    stock my be vary( zero or some stock)
    my question or requirement is when I create a Process Order for Material Y where this Material X is consumed ( 261 Mov Type).
    When I confirm the Created Process order for Material Y(suppose 20) & require quantity of X for this Material Y is 40 & we have no stock or may be less than the require quantity at this time system check the availability & Generate GR for this material X against Related Purchase Order or If have Multiple Purchase Order then ask for Purchase order selection & then post the Confirmation (GOODS Movment).
    Hope u understand my requriment ,Please suggest
    Thanks
    Parminder

  • Requirement calculation of material in process order

    Dear Friends,
    we have one raw material whose base unit of measure is maintained as CAR (cartons) and the unit of issue is in EA in material master.
    now, when we create the process order of Header material, the system calculates the requirement qty of raw material in EA and this is properly shown when i click the material icon for the details of componen.t
    but when i click the icon of material availability check the system gives the message as missing part list even if the current stock fulfills the reqmt. qty.
    hereafter when we click the missing part list overview the reqmt. qty is calculated as per the base unit i.e. in cartons , it rounds of the figure obtained and re-converts to the unit of issue as in EA.
    for eg.
    one carton contains 1472 pcs EA
    required qty of x material as per process order is 16000 EA ,
    when we click on materials icon it shows the figure as 16000 EA correctly,
    but now when we check for material availability and seee the missing parts overview , here the requirement qty is shown as 16192,
    system calculates as follows:- 16000/1472 = 10.869 cartons,
    here it rounds off to 11 cartons and equivalent of 11 cartons is 16192 EA.
    so if, say for e.g. my stock of raw mat. is 16000 EA which can fulfill my reqmnt as per BOM but due to the above calculation shown the release of order is rejected.
    please suggest for the issue to get resolve.
    thnx in advance
    rgds
    Amitabh Rathod

    Dear Amithab,
    Frist thing is always ur base unit of measure should be the minimum one. in ur case u hae done ulta.your BUM sholud be EA and yor altrnative unit of measure should be CAR this u define in material master basic data view. at this piont of time system will not allow u to change unit because stock and other movement document exists.
    Now the only solution to get CAR in exact decimals ask ur MM consultant to enable 3 decimal placess for the unit CAR in SPRO, then ur issue will be resolved
    sree

  • Info Related to Material No, Process Order No

    Hi Gurus,
    Can you tell the Master and auxillary tables related to Process Order No, Material No and Plant.
    I have to run t-code : COPI
    which is used to generate Feedback list ( Process Order )
    I have Process Order no with me but do not have material no and plant...From which table can i obtain the same..
    Thanx,
    Navin..

    Hi,
         You can try the tables AUFK, AFPO, LTAK, LTBK.
    <REMOVED BY MODERATOR>
    Edited by: Alvaro Tejada Galindo on Jun 12, 2008 4:17 PM

  • WM material staging & process order

    HI Team,
    1. Is there any relationship between the control cycle with the TR creation process in process order?
    Suppose there is one process order created (COR1) with production schedule profile saying 'No creation of transfer requirement on release'.
    So this time no matter what, the system will not create any TR while releasing the process order, is this correct?
    2. Suppose there is a process order for finished good 'A' and 'B' is the component.
    Process order is having production schedule profile saying 'Only creation of Transfer requirement on release'.
    Now control cycles are maintained for material 'B" with material staging indicator '3'.
    Would the TR be created while releasing the process order?
    Is there any relation between the control cycles and the process order and also with production schedule profile?
    Please advice on the query in detail.
    Thanks,

    The system determines the material staging type on the basis of the control cycle and determines the production storage bins, in which the components should be staged. 
    Please take a look at this topic: WM-PP interface - material staging
    This information: Material Staging - Warehouse Management System (WMS) - SAP Library
    And this one too: Control Cycle - Warehouse Management System (WMS) - SAP Library
    This will help you understand the staging process in detail and is quite easy to read.

  • Difference between cost center for material and sale order

    Hi,
    I'm having an issue related to profit center. Our business of Reverse Logistics Process is taking the wrong profit center which should be taken from sale order master data, not from material master data as currently. As a developer, I'm confused the definition of profit center in this case. What are the differences between the profit center defined in sale order and in material ?
    Thanks,
    Paulb

    Hi Paul
    SAP allows you to change the PC in the sales order... If you dont change, it adopts the PC from Mat Master
    You can define substitution of PC for sales order in 0KEM and assign them in 0KEL... You can change the PC based on Sales Org, Dist Channel, Division, etc
    For a more complex logic, you can also use an exit
    br, Ajay M

  • Back Flushing Vendor consigment Material in process order

    Dear Experts,
    I have a question Regarding Vendor consignment back flushing
    while i am doing order confirmation system not proposing vendor name and in good movement tab
    may i know what configuration or master data setup is missing
    My requirment is i need to back flush vendor consginment material automatically
    currently i need to manually choose the vendor while confiming the order
    Thanks in advance
    Rgrds
    Raj

    Dear Experts,
    I manage to use stock determination group for back flushing consignment material
    it works fine system automatically picking up vendor as we do not have multiple vendors
    now i have new issue
    for instance
    i  have a   RAW material A  used in a Product A  when i do confirmation system can able to do back flush with movement type 261 K
    i am using same RAW material A used in product B and when i do confirmation system give me a error
    as below
    Pipeline/consignment movement posted without value
    Message no. M7234Diagnosis
    The system has determined a consignment/pipeline price of 0.00.
    Possible reasons:
    The system could not find any valid condition for the posting date in the consignment/pipeline info record.
    A price of 0.00 was defined in the info record.
    System Response
    Depending on how the system is configured, the message can be either a warning or an error message.
    A withdrawal from this consignment stock or from the pipeline will not create vendor liabilities. For materials with moving average price control, withdrawals are posted without value. For materials with standard price control, a price difference posting is carried out.
    The message is also issued when materials are received into consignment stock, as the system must check whether a consignment price of zero is required.
    Procedure
    If you have authorization, check whether the conditions or the price has been defined correctly in the info record, if necessary. If there is a condition with a price other than zero, check whether the posting date of the movement lies within the condition's validity period.
    Proceed
    just wonder does any one have this issue
    so strange i can issue to product A and not product B
    Please help me if you have any problem
    Rgrds
    Raj

  • Process Order Cost Analysis Target and Actual Quantity Missing

    This is related to Process order costing .
    Issue : Before activating  Material Update field in Costing view 1 of Material master , we have created few process orders and Delivered .
    Hence cost analysis shows Actual and target cost fields  Empty in COST ANALYSIS  report of  order  . After Updating field in Material master , New Process orders are calculated with Actual and Target cost .
    Solution needed : How to do Actual and Target cost estimation back in cost analysis report  for old process orders which are created before Material Update field ?

    You have deleted the Component in the BoM.
    Then you have created a production order, check if the start date of this order is after the date change in the BoM..... Can be that the component stills exists in the order ? Have you tried deleting the compoent in the order BoM ?

  • Confirmed Process order but with mistake on quantity for material.

    Dear All,
    The case is ,  User make mistake on putting large volume into material quantity within process order,  However, this process order has been released , confirmed and delivery (DLV) status. 
    Since this large vquantity material will make the Cost extra larger than normal.  
    Therefore, is there way to change material quantity and recalcuate the cost again? 
    Many thanks !
    Marco

    Dear all,
    After commuicated with User again,  user has been done as below.
    Step1)
    User has been cancel the process order confirmation by T-code:  CORS,
    Step2)
    Revesed the extra amount Quantity to Block stock to prevent Sales Person touch this extra quantity.
    However,  I checked there is no different on Actual costs after the cancel the Process order confirmation.
    I have some confusing now..
    1) is that once Process order confirmation cancelled,  is that there Must no Actual cost in Accounting view?
    2)  If there is part of physical product produced,  but the Process order has been cancelled afterward. How the cost calcuated?  is that include the cost or exclude the cost? 
    Many Thanks for your help!
    Best Regards
    Marco

  • Can we assign process order in MB21 RESEVATION for extra material

    Sir,
    in Production sometimes we required extra raw material but already we issues raw material against  process order then that time where we assign extra raw material in process order or where we check costing of extra material qnty aginst process order.
         can we asssign extra material against process order in MB21 with movement type 261

    Dear,
    It is not possible to create the manual reservation against the order for 261 movement type. Because system generate the automatic reservation for an order whcih can not be modified. Better you go for component or operation scarp to plan the extra requirement. MB21 you create the reservation with 311 movement here you give reference of an order also maintain the long text for same. By this you can transfer the extra consumption from main storage location to production storage location. And issue material against the order with MB1A 261 against the oder as unplanned consumption.
    Hope clear to you.
    Regards,
    R.Brahmankar

Maybe you are looking for

  • Understanding complex query with selections(customer exit variables)

    Hi experts, I am trying to understand one query having  a combination of selections and BEx variables in it. In Characteristic Restrictions panel of Query Designer: we have some CHARs restricted by means of authorisation variables In Default Values p

  • How do I edit a PDF file on my Macbook Pro?

    I'm working on a PDF file as school assignment and one of the requirements is inserting a picture into a little box. How do I do that and then continue to edit other parts of the PDF file so I could write stuff and revise?

  • Please Urgent help needed.........Cant open Downloads !!

    After the download completes i am unable to open any file.....its says this..... THIS IS THE MESSAGE........ SAFARI CAN'T OPEN THE FILE SAFARI CAN'T OPEN THE FILE  "filename" BECAUSE "filename" HAS MOVED SINCE YOU DOWNLOADED IT.

  • My Quicktime Mp4 Video Archive is Converting into Sound Files

    I archived a number of videos using quicktime, in mp4 format. I don't know if this was caused by a software update; but, these videos only play as sound files now. This has happened on quicktime videos stored independently on both of my Macs - so I d

  • Trigger email for exceeded budget

    Hi, I want to know how to trigger email (and also maintain the person name/userid) to the person resonsible if the budget is exceeded. There is a standard 'action' no. 2      Warning with MAIL to person responsible in 'Fund Management Availability Co