Data for Actual/ Plan Cost and Budget

Hi All,
Can you please adviseme  which content i need to activate to get the Actaul, Plan cost and the Budget Data in SAP BW.
Do i need to exploer CCA cubes or Fund managment Cubes.. Please let me know... I need to know the Tables in R/3 Side for budget data to make sure that in R/3 we have budget data..
Please let me know.
Thank you
SAP

Hi there,
For those check in here:
[http://help.sap.com/saphelp_bw33/helpdata/en/d3/561be24e8c11d596f30000e835339d/frameset.htm]
[http://help.sap.com/saphelp_bw33/helpdata/en/60/0f07d3532c864aab7ec5f113146da2/frameset.htm]
[http://help.sap.com/saphelp_bw33/helpdata/en/26/d0cccc8d98c344925915ec81d5a421/frameset.htm]
[http://help.sap.com/saphelp_bw33/helpdata/en/43/de43fcf6e2154bbbbcecbc63cdf287/frameset.htm]
[http://help.sap.com/saphelp_bw33/helpdata/en/23/d5cf85683c3348b2189199e49a35cf/frameset.htm]
[http://help.sap.com/saphelp_bw33/helpdata/en/ad/be383fd98d1201e10000000a114084/frameset.htm]
[http://help.sap.com/saphelp_bw33/helpdata/en/1a/8c42588afe11d496d80000e835339d/frameset.htm]
[http://help.sap.com/saphelp_bw33/helpdata/en/d3/29ae399c1a6651e10000000a114084/frameset.htm]
Hope this helps.
Diogo.

Similar Messages

  • Data Source to upload plan data for CO_OM_CCA_: CC: Costs and Allocations

    Hi Guru's,
    We have Data source that which upload Actual data for CCA (0CO_OM_CCA_1 - Cost Centers:cost and allocations).  Every time it is full upload before loading the data deletion of previous load request will be done.
    One more information required that i have checked in the BW cube for plan data it is available in the info cube for one cost center and rest of the costcenter i don't have the data now the users are requesting to upload the plan data for rest of cost centers.
    Now as per the business requirement the users are requesting to upload the plan data in to the same i am not sure whether it will pull the plan data with actuals in to BW cube. Is there any alternate with the same data source or else is there any specific data source for uploading Costs and Allocations plan data
    Please suggest me how can i go a head with this requirement.
    Thanks in Advance.
    Ganni

    You can use the same datasource to load plan/budget data to the cube for all the costcenters. And regarding the actuals, you can use 0CO_OM_CCA_9 datasource to load to actuals cube and create a multi on top of both plan and actuals cube for reporting purposes.

  • In which table production order planned cost and actual cost i can see?

    Dear PP Guru,s,
    from which table i can see productuion order planned and actaul cost. i checked following tables AUFK, AFVC, AFVV, CAUFV, AFRU, AFKO, AFPO. but i did not found planned cost and actual cost field. is there any other way to get this data with respect production order?
    Regards,
    sree

    Dear,
    Planned and actual costs of prod order from COEP, COSS, COSP  S027 tables
    production order shows the planned cost based on the quantity structure.
    Please refer my reply in this thread for details,
    Re: Actual Halb Material Cost
    Regards,
    R.Brahmankar

  • Dashboard content is not populated with Planned Cost and Actual Cost

    Hi
    We are working in cProjects 4.0 + ECC 6.0 implementation. I could not get the data for columns in Planned Cost and Actual Cost in cProjects Project Dashboard. I have properly mapped the config settings and created and assigned a Project in PS
    Has anybody got this data in the Dashboard?
    Kindly suggest the solution
    with regards,
    K Rama Krishna
    9394712743

    Hi Rama,
    It is difficult to say, where the problem is.
    but typically, the causes of the problem are
    customizing is  set incorrectly or the evaluation is not carried out.
    You can run the the evaluation DPR_EVE_BATCH_DPO additionally, please untick the flag 'check the last changed date'.
    Hope, it helps.
    Kind regards,
    Zhenbo

  • Function Module to find Planned Costs and Actual Costs against WBS element

    Dear All,
    We have a requirement where we need to find out the Planned Costs and Actual Costs booked against a WBS element, in a year. The costs can be against all the plan versions or on individual plan version.
    Are there any function modules to retrieve this value?
    Thanks for the help.
    Warm Regards,
    Judith

    Hi,
    The easiest way would be to get the OBJNR for all WBS elements from PRPS and look up RPSCO and summarize for Value type (RPSCO-WRTTP) 1 for planned cost and 4 for Actual cost.
    Please let me know if this helps.
    jibat

  • IW32  needed Plan Cost and Actual Cost table name

    Hello ,
    In IW32 transaction Plan Cost and Actual cost in cost tab ---Table Name.
    Req: needed  plan cost & actual cost table names  for particular order number.( For New Report )
    Can you please let me know where Plan cost & actual cost get stored in IW32 in Cost tab ( table name / function module name ) or how its get calcualted for particular order number.
    Thanks in advance !
    Regards
    Rahul

    hi ,
    i too had same issue , i wrote following FS for that :
    Actual and planned cost  from PMCO-WRT00 to WRT12(the sum of values should be considered for actual as well as planned ) for  PMCO-OBJNR taken from CAUFV -OBJNR for order number  AFIH-AUFNR  and also currency from CAUFV-WAERS .
    Actual cost will have valuation type PMCO-WRTTP = 4 and planned cost will have valuation type  PMCO-WRTTP = 1 , which will be placed in different column
    hope this helps
    regards
    satish

  • Which data sources I need to use for Actual&Plan comparision of GL Account?

    Could you please let me know which datasources I need to use for Actual & Plan comparision of GL Account data?
    Current SAP BI version is BI 7.0.
    As per my knowledge, I am thinking of using the datasources 0CO_OM_CCA_1 for Plan data & 0FI_GL_10 for Actuals.
    Is this right?
    I have one more question here:
    While extracting the data from ds 0CO_OM_CCA_1, I am getting only the Profit & Loss Account data where as the Balance Sheet Account data is not coming.
    And also there is some confusion in VTYPE because the standard ds 0CO_OM_CCA_1 is giving the data with Value type 10 is & Version 000.
    As we all know the VTYPE '10' stands for Actuals then how can we say that this ds 0CO_OM_CCA_1 gives Plan data?
    Please clarify.

    Hi,
    Basically 0CO_OM_CCA_1 data source is used to extract actual, plan, and commitments.
    This data is differentiated with value type, you can see sap note 523742 for more details on value type.
    For balance sheet accounting data check the below link,
    [http://help.sap.com/saphelp_nw04s/helpdata/en/5d/ac7d8082a27b438b026495593821b1/content.htm]
    Regards,
    Durgesh.

  • Actual Costs , Planned Costs and Variance

    Hi,
    I know that there is a standard function module that gives the actual costs , tha target costs and variance, K_KKB_KKBCS_ORDER_REPORT. But is there any Funcion Module  for calculating the Actual and planned costs and variance?  or could the same FM be used for the purpose?

    OK

  • In IW32 no Planned Cost and Actual is showing Zero

    hi,
    In IW32 no Planned Cost and Actual is showing Zero,since activity type is mentioned.
    how it could be displayed.
    Thanks

    Dear Sharma,
    1. This is regarding Maintenance order, frist you confirm by clicking on the operations tab-> double clicking on the work center->click on costing tab, check here activity type, activity unit is maintained.
    2. then in in KP26 check the activity price in the current period.if it is zero u will get zero
    3 then in the order click on components, if components are consumed  also check the component price in material master.
    this will resolve your issue
    sree

  • Costs and Budgets in a PEP Element

    Good Morning dear friends!
    Now, I'm dealing with a problem with PS module.
    I need to select from DB the data of PEP elements related to costs and budgets in a determined period.
    I have two tables that the functional person have passed to me: RPSCO and COEP.
    But when I access the CNS41 transaction, the values that appears there are incompatible with the values of the tables. I've saw that are differences that distinguish real values from planned values, budgets and costs.
    But I don't have the values yet that appear at CNS41 transaction.
    Anyone already dealed with this problem or know about this information in PS?
    P.S. I've used the ST05 transaction to map the tables used, but this didn't work.
    Hope you can help me.
    Regards,
    Diogo Patriota.

    Hi Joe,
    You can get revenues into BPC in exactly the same way you would load project costs. Either via BW InfoProvider or via flat-file load. Generally in BPC Netweaver, building a BW InfoProvider will be the most advantageous way to move data into the system for things like Revenue that should reside in your Enterprise Data Warehouse in any case.
    Of course, the most difficult part of this is not going to be loading the data itself, but rather determining the process by which your business will map revenue onto projects, then building and testing this process in whatever system you decide to use to stage your data.
    Good luck!
    Ethan

  • Function modules or BAPI for posting plan costs for WBS Element

    Hi all,
    Does anyone know, whether there exists a function module or BAPI for posting plan costs to a WBS Element? K_COSTS_PLAN_PS does not work, because RKP1 is not allowed.
    Greetings

    check
    BAPI_COSTACTPLN_POSTACTINPUT   Activity Input Planning: Posting                
    BAPI_COSTACTPLN_POSTACTOUTPUT  Activity/Price Planning: Posting                
    BAPI_COSTACTPLN_POSTKEYFIGURE  Stat. Key Figure Planning: Postings             
    BAPI_COSTACTPLN_POSTPRIMCOST   Primary Cost Planning: Postings                 
    BAPI_PDTRANSCO_POSTPRIMCOST    Transfer of Planning Data: Post Primary Costs   
    K40C                           CO Actual Postings, Manual                      
    BAPI_ACC_PRIMARY_COSTS_POST    Accounting: Post Primary Costs                  
    BAPI_COPAACTUALS_POSTCOSTDATA  BAPI Operating Concern: Post Costing-Based Actua
    BAPI_PRIM_COST_CHECK_AND_POST  Primary Costs: Formal Parameter Check           
    S@meer

  • Actual & planned costs calculated while creating Plant Maintenance Order

    Hi All,
    I would like to know how the actual & planned costs calculated while creating Plant Maintenance Order (PM Order)
    Thanks,
    Ajay

    You need to create an activity rate for 2014 for cost centre 51260201 and activity type NAHG20.
    This can be done via transaction KP26, but is usually performed by your Finance team.
    PeteA

  • Service Order Planned Costs and Cost Center Planned Line Items

    Experts,
    I am curious of Service Order Planned costs, and whether or not these planned costs are being posted to the Cost Center linked to the Service Order Operation's work center.
    I am a but puzzled as I don't see any planned costs from any Service Order Operation in a cost center linked to the Operations work center, when reviewing "Cost Centers: Plan Line Items" report.
    BR,
    Cenk

    The planned costs were input in one of the Service Order operations as planned hours. There is a column for it in the operations list. The amount of hours have incurred a planned cost on the Service Order header.
    I simply assumed that this cost would be credited to the Cost Center linked to the operation's Work Center. But that is obviously not the case. I am not familiar with the PLICC field and the functionality it provides.
    Thanks!

  • Raw material planned cost and qty in table MCKALKW

    Hi,
    Raw material planned cost and quantity in table MCKALKW is not equal to cost analysis in CO01 / CO02.
    Could you please let me know how to get the planned cost and quantity for production order components for report development. i checked other tables like AFPO and AFKO and it is showing only for main material and not for its compoen

    Hi,
    You can check the cost of the individual components in Bill of materials of each material seperately. Hope this works for you.
    Thanks and regards,
    Murali krishna Maganti

  • Delete Transactional data for one (1) Cost element

    Hi All.
    How to Delete Transactional data for one (1) Cost element?
    i know T code OKC3 but it is saying I can delete only at controlling area level,
    I want to delete only data (Transactional) for one cost element .
    Please let me know, Thank you ,
    Paartha,

    it is not possible to delete the data, if u want u can repost from one cost element to the another cost element if u are feeling the entry was posted to wrong cost element.
    Otherwise if u want restrict the transactions further to that cost element, u can restrict through cost elmenet master where in u can select the direct postings and secondary postings etc.,
    regards
    madhav