Final Delivery indicator in Goods Receipt tab in Process Order
Hello Friends,
I have one doubt, thought to discuss with you.Whats the importance of Final delivery indicator in Process order.I know that if any further goods receipt is not accepted against the order than we should tick this indicator,because of which system sets the DLV status at order header level or if goods receipt qty against the order is equal to order qty than system automatically sets this indicator.
when we do the settlement of order than system looks either for TECO or DLV status of order , if its find there than system consider such orders for settlement.
Now my question is suppose i have done the Goods Receipt against the order less than the order qty, than system will set the PDLV Status against that order.Now no further goods receipt is expected against that order.Now i haven't set the Final delivery indicator in goods receipt tab in process order.But i have technically completed the order,because of which system has set the TECO status against that order.
Will system allow me to settle such order?and viceversa, if order has DLV status at header level and no TECO status, than system will allow to settle such order?If yes than whats the other use of Final Delivery indicator in process order?Is it important to set that indicator from settlement point of view only?
As far as i know, system allows us to do,but on this issue i have got different answers from different person.So bit confused.
Thanks and Regards,
Jitendra Chauhan
Edited by: jitendra chauhan on May 8, 2009 8:42 AM
Dear,
Will system allow me to settle such order?and viceversa, if order has DLV status at header level and no TECO status, than system will allow to settle such order?
Yes
If yes than whats the other use of Final Delivery indicator in process order?Is it important to set that indicator from settlement point of view only?
You need to Final confirm (CNF) the Order to get the DLV Status.
Or if the Delivery completed indicator is set in the Process Order, then also th System status will be DLV
If your order quantity10 and you produced 10 quantity it means that order is fully deliver then Final delivery will automatically be set.
The "delivery completed" indicator has the following effects:
o The item is regarded as closed, even if the total quantity was not delivered.
o A further delivery is not expected, may, however, arrive.
If status is DLV then it cannot be a WIP stage where the the good are posted to stock and production is completed
Please refer this thread fro DLV and TECO,
Re: order settlement
Regards,
R.Brahmankar
Similar Messages
-
Delivery Completed Indicator under Goods Receipt tab in COR2 to be hidden
Dear All,
I want to hide Delivery Completed Indicator under Goods Receipt tab in COR2.
Is it possible with configuration?you may try to create screen variant with tcode SHD0
there are many threads on how to use shd0 -
Final Delivery indicator not in all rows of Purchase Order
Hi,
I am constructing a query in BW where i need to filter out Purcahse Orders for which the Final delivery indicator is set.
The Purchase cube has the data coming in from following three datasources:
2lis_02_hdr (Purcahse Order Header)
2lis_02_itm (Purcahse Order Item)
2lis_02_scl (Purcahse Order Schedule line).
The Final delivery indicator is populated from Item and schedule line Datasources.The Purchase cube stores the data in such a way that the final delivery indicator is not set for a Purchase order in all the rows.
Please advice how can i populate the final delivery indicator in the cube for all the rows of a Purchase Order. Also I do not want to reinitialize the data load from R3 or PSA.
Regards
SapnaHi ,
The answer was helpful but my problem was not solved. But in some of the cases the Final delivery indicator is not getting filtered. Also we have Posting date as a Key field in the Info provider.
Now there are various scenarios. For eg:
1. If the Final delivery indicator is set from me23n then the posting date is saved in my Purchase cube AND hence i can sort the Posting date and get the final delivery indicator against the Max posting date.
2. If the Final delivery indicator is set through MIGO screen, then posting date is blank against final delivery indicator. Hence in Purchase cube the Posting date is blank and sorting will not work.
Please advice.
Regards
Sapna -
Goods receipt tab in production order
hi all,
may i know what is this goods receipt tab for in CO01?
is it GR into inventory or GR into production order?
thanksHi Sam,
The screen itself is self explanatory. Data in Goods receipt is being populated from master data and from configuration also. Few data can be changed in order level which will be valid only for this order.
So the main things are,
1. Type of stock(unrestricted/quality etc)
2. GR proc time(comes from master data-Mat master)
3. GR is possible or not/delivery completion etc)
4. Under and over delivery tol(from mat master)
5. Stor loc(Comes from different sources- Please refer the doc link-Default storage locatio selection for component)
6. Batch -GR
etc
Regards,
Krishnendu. -
Batch entry in process order in Goods receipt tab mandatory
Hi,
There is a field in Good receipt tab of process order (AFPO-CHARG). We want to make it mandatory field. Is there any way to do that & it should be dependent on order type-plant.
regards,
MohitHI,
Good receipt tab of process order (AFPO-CHARG
I think you are asking about batch field for header material.
If you want to make it mandatory then you can do it by creating screen varient (SHD0).
You find many online help documents and threads on screen varient, search it over here on sdn or on net also.
Regards,
Dhaval -
Final delivery indicator unset after underdelivery good receipt.
Hi, If the final delivery indicator is set in the purchase order SAP allows good receipts and then unset the indicator, only if the quantity in the purchase order is equal to the quantity receipt, SAP set final delivery indicator. The user want to set the final delivery indicator to close some purchase orders with underdelivery quantity.
Alejandra,
You can advise your user that the delivery completed indicator is not designed for this purpose.
If the user wishes to prevent further receipts against a Purchase order, for any reason, he should block the item rather than rely on the DC indicator.
ME22N for the order, select the item; hit the 'lock' icon; or Edit>Block.
This transaction is reversible.
Regards,
DB49 -
Setting final delivery indicator on scheduling agreements (ELIKZ)
Hello ALL,
Based on note 199749 SAP does not set the delivery complete indicator for scheduling agreements during goods receipt processing. We're employing thousand line scheduling agreeements where new schedule items are added to the scheduling agreeement items via MRP. When the delivery complete indicator is manually set MRP proposes requisitions instead of schedule lines which is our desired processing but we need the final delivery indicator to be automatically set. Does anybody know the user exit to set this indicator during goods receipt processing including any other helpful information.
Thanks so much for your time.Hello Walter,
this should be possible in BADI 'MB_DOCUMENT_BADI' ,
method MB_DOCUMENT_UPDATE.
Regards Wolfgang -
Hello
My question is
"Explain the circumstances in which the Final delivery indicator is automatically set when posting a goods receipt"
ThanksHi Sunil
Check help given by SAP
Set "Delivery Completed" Indicator
the delivery completed indicator for goods receipts if the delivered quantity lies within the under/overdelivery tolerance.
The "delivery completed" indicator has the following effects:
o The item is regarded as closed, even if the total quantity was not delivered.
o A further delivery is not expected, may, however, arrive.
o In the next goods receipt, the item appears on the selection list but has no selection indicator.
o The item can be reorganized even if the total quantity has not been delivered.
Note
Even if the "delivery completed" indicator has not been set, an item is'nsidered closed once the total quantity has been delivered. This mean that the "delivery completed" indicator is not necessary in this case.
Vishal... -
Final delivery indicator not reflected in BW ODS
Hi Experts,
I have situation like, final delivery indicator not reflected in BW ODS for purchase order. In R/3 it is X, in BW showing space. There is direct mapping from datasource field to ODS for this field.Loading also seems to be ok.
Cna you please give some points where this information is missing.
Thanks
Konda ReddyHi konda,
See the business senerio it is not fetching the data u have to write a formula in transformation based on requirement.
Regards,
Lakshmi -
Final Delivery indicator in PO
Hello,
I am not getting " final delivery indicator " icon in purchase order.
we are using ECC6.
Thanks in advance,
Vikas R.Hi,
Active "Delivery completed" indicator for your plant in t.code: OMCD
For Service(external)
Check Field Selection Key for SERVICE PO Document type & make "Delivery completed" indicator is "Opt.entry" in GR/IR control segment for Field Selection Key PT9F( OR your Field Selection Key you are using for Frame work order document type) in following path:
SPRO-> MM--> Purchasing -> Purchase Order -> Define Screen Layout at Document Level
Now assign Field Selection Key PT9F for SERVICE PO Document type & save.
Go for cycle service PO, SES & MIRO and can view Delivery completion indicator
For more check the SAP Note 735404
Regards,
Biju K -
Problem for Goods Receipt for Subcontracting Purchase Order
Dear all,
Presently, we are using SAP version 4.6C and we need to introduce GR for
Subcontracting Purchase Order. We have developed a ABAP program to handle
subcon Goods Receipt by uploading flat-files from our subcontractor. The
scenario is as follows :
Goods Receipt for Subcontracting Purchase Order
1. In the ABAP program, function BAPI_GOODSMVT_CREATE will be used for goods
movement.
2. Data provided to the function are as follows :
- Posting date
- Document date
- Material number
- Plant
- Storage location
- Batch
- Movement type (101)
- Quantity
- Purchase order number
- Purchase order item
- Movement indicator (B - Goods receipt for purchase order)
3. The function will do data verification and automatically determine GI
item for subcon stock:
- Movement type (543)
- Special stock (O - parts prov. vendor)
- Material
- Quantity
- Plant
Our problem is that :
Only the GR item in the interface is to be transferred and the GI item is
determined by the system. So, the quantity for subcon stock cannot be
changed using this BAPI. Then the system will continue processing the goods
receipt and create material document.
Manually, by using transaction code MIGO, the user can display the subcon
stock data and then change the quantity.
By using transaction code MB01, after the user fills in all the GR fields,
the system comes to line item 002 (subcon stock data) and then quantity can
be changed.
As per user requirement, quantity for GI item must be same with the quantity
that has been transferred to subcon vendor in Delivery for Subcon
(transaction code VL02N).
We cannot achieve this requirement by using the BAPI mentioned above. Would
appreciate any valuable help from anyone who is able to help us on this
matter. Are there any other BAPI's that can help us to achieve the same
result ?
Thank you in advance and best regards.As far as i understood the problem I suggest u to create the
BDC according to user actions that are performed in he manual
operation.
I can't say that the BAPI performs the exac solution what you want.
I have done some BDC work using MB01 and suggest you to be careful
and try to keep the complete in the logic as some chages in rows in BDC will
change the complete scenario.And throw correct quantity val in correct
material
row.
This methodology will help u even in mass uploads.
Or in case of automation u can perform the call transaction BDC in
background mode.
so As per my understanding bdc program is the solution. pls try and let me
know. -
No goods receipt possible for purchase order 'PO#" "Lineitem"
Hi gurus,
Please help on below error.
While doing return to vendor transaction using BAPI 'BAPI_GOODSMVT_CREATE' error 'No goods receipt possible for purchase order 'PO#" "Lineitem"' was encountered. As checked, all data are correct including the plant, sloc, PO#, stocks, batch.
Please kindly advice on how to resolve the issue.
Thank you in advance.Hi,
Few things which immediately comes to my mind.
1. Check if the PO is released?
2. Check if the confirmation control is properly set in Confirmations tab of item details of a PO.
3. Check if the Goods Receipt indicator is ticked at item level of PO.
I hope these helps.
Kind Regards,
Prakash -
No goods receipt possible for purchase order 4800000097
hi,
i am facing a problem while at the time of Doing GR . it says the "No goods receipt possible for purchase order 4800000097" when i try to proceed with the GR.
I have checked all the necessary possibilities such as
1. PO has been released
2. at the item level delivery tab GR is flagged and delivery complete option not flagged.
3. version management is not activated
4. i checked in the table EKPO field statistical . ther is no entry
plz kindly help
regards
sufiyanHi,
Please check the plant in PO and in MIGO are correct and that PO is exist in the system.
Also check PO history in PO.
Regards
ram -
PO 'No goods receipt possible for purchase order'
Hi gurus!
While trying to make Confirmation of a PO in the SRM Portal the user is getting the error 'No goods receipt possible for purchase order'
The scenario used is Classic, so PO is replicated directly to the R/3 system.
Any idea why this is happening?
Thanks a lot!Hi, thanks for the quick reply!
Where i can check the Item category?
I found a field called 'subitem category' but it's blank
with this possible values:
1 Variant
2 Discount in kind: inclusive bonus qty.
3 Empties
4 Discount in kind: exclusive bonus qty.
5 Prepack item
6 Display item
7 Set item
8 Interchangeable items (IBU: A&D)
9 Pre-packing (SLS items)
H GT Bill of Material, Header Relevant
I GT Bill of Material, Item Relevant
About PO type i think it's EC (doc_type?), in R/3 is shown as EBP PO
I checked in backend system, in the item details > Delivery and the 'Goods Receipt' is checked. -
No goods receipt possible for purchase order message number# M7036
Hello,
We are working in 4.7C , Created the scheduling agreements, with Shipping notification(Inbound delivery) .
Created the Scheduling agreement on 25.09.2009 and created the schedule line one same day with date 25.09.2009, (time column Blank).
So in Practice for Goods receipt we are using MB0A t code for GR,(not using MIGO)..while MB0A..iam going to make GR with ref to Shipping notification then system will through below given message.
No goods receipt possible for purchase order
5500001447 0001
Message no. M7036
tried every thing but unable get. shar your views
Regards
Sapman manHi
If you use Shipping notification then you have to create inbound delivery VL31n and do the PGR in inbound delivery VL32N itself.
Incase of scheduling agreement schedule lines you have to make sure the following
1) Schedule line delivery date shoud be todays date or in the past
2) Schedule must be released by using message type based on the type of schedule ( Normal, JIT or forecast)
Hope it helps
Thanks/Karthik
Maybe you are looking for
-
Whenever I use a hyperlink from an MS Word document, Firefox opens two windows instead of one. The first window is the one I need. The second contains a message that the page could not be found and the address bar contains the URL appended with "Fire
-
AppleTV not viewing videos in MobileMe gallery
When I try to view my MobileMe posted videos through my AppleTV, nothing appears. The name of the gallery where the video is posted appears, but there is nothing in there. I have no problems viewing the videos by going directly to the MobileMe galler
-
Battery was drained on mu ipad A1416 and is now disabled it says to connect to iTunes but wont due anything?
-
I have several playlists on my iPod including one that contains just Christmas music. I typically shuffle songs between all playlists, but would like to exclude the Christmas playlist except during the season. Is there any way to exclude this one pla
-
Can I upgrade hard disk storage of Macbook pro retina 15inch 2013 late after purchasing?
Can I upgrade hard disk storage of Macbook pro retina 15inch 2013 late after purchasing? I currently have 256GB.