Hi,
I have a framework order which GR Non Valuated is checked and GR Bsd IV is unchecked. When goods receipt is performed, under PO history in the framework order, the value of the of the GR is shown as 0.
Is this standard in SAP? Am I right to say that this is the case because GR Non Valuated is checked? Amount will only be shown at IR instead.

Hi
Pl. Note that,As per SAP Best Practice,
For Framework Order with Item Category "B"....."GR Not Possible"
Only IR is possible.....
This details you can see in OLME ---> Define External Representation of Item Categories and go into details....
Reward if useful
Regards
S.Baskaran

Similar Messages

  • How to activate the Check box in Purchase Order after Goods Receipt

    Hi All,
    How to activate the check box after Goods receipt of Purchase order in Item view (Goods Receipt is completed).
    Where t make the settings in SPRO.
    Regards,
    Shailendra Hadkar

    Hi
    SPRO - SAP IMG- Material management - Inventory management and physical inventory - Goods receipt - create purchase order automatically - activate auto Po creation for movement type.
    Then activate the auto PO creation in Vendor master - Purchasing view
    Check it out.
    Regards,
    raman

  • Restrict changing the tax code in purchase order after goods receipt.

    Hi,
    Po is created with tax code x1.
    Gr is done for partial quantity.
    IR is still pending.
    User has changed the tax code to x2.
    This case we want to restrict the tax code change in PO after goods receipt.
    Please advice.
    Regards
    Ravi Kumar

    Hi Sumit,
    Po created with wrong tax code x1.
    Stores person has done the receipt and consumed the stock.
    Now user has suddenly realised that tax code is wrong and changed the tax code in PO.
    In IR we will use correct tax code and post the accounting entry.
    Stock values will be adjusted properly. to stock ac if stock is there and to price diff ac if stock is consumed.
    Point is user's are asking that how system is allowing to change the tax code after receipt.
    Point to be attended is restrict the change of tax code by any means after Gr has happened.
    what are the possibilities to restrict the change of tax code.
    Regards
    Ravi Kumar

  • Change of Purchase order after Goods Receipt

    Hi Guys,
    Can the Purchase order be changed after the Goods Receipt??
    If then what is the transaction Code used or what are the steps followed for the change of PO after GR(goods receipt)???
    Regards
    Jino

    Sir,
    It's not possible to change the PO for specifica line item if GRN exist against it..
    Pl revese the GRN and then ammend the PO in terms of quantity or price or delievery schedule..
    The Relase strategy for PO will get affected..
    Typical exception..
    In certain cases it can be seen.
    The GRN exist for line item..
    The ammedndment done in TAX breakup resulting in  derelease of PO..
    and again PO has been release..
    So Sir,
    If the changes is in terms of quantity then pl reverse the GRN..
    Otherwise go for ammndments,,with the pending GRN..
    Edited by: nj on Jun 9, 2009 8:46 AM

  • How to change Purchase Order currency after Good receipt and Good issue?

    Hi,
    I've a PO created last year. The PO currency has been entered wrongly.
    My store colleague has been performed good received and consumed it.
    Now, I am not able to change PO currency to correct one, due to this message:-
    Currency can no longer be changed
    Message no. 06489
    Diagnosis
    As a basic rule, the currency cannot be changed if there has already been a goods receipt against a document.
    If the document contains external service and/or limit items, or if an invoicing plan has been assigned to an item, the currency cannot be changed following the receipt of an invoice either.
    If external service items exist, the currency also cannot be changed if services that have actually been performed have already been recorded or if the item in question has been assigned to a preventive maintenance (servicing) plan.
    Is there anyway to change PO currency after Good receipt and Good issue? Thanks !

    Diagnosis
    As a basic rule, the currency cannot be changed if there has already
    been a goods receipt against a document.
    If the document contains external service and/or limit items,
    or if an invoicing plan has been assigned to an item,
    the currency cannot be changed following the receipt of an invoice either.
    If external service items exist, the currency also cannot be changed if
    services that have actually been performed have already been recorded or
    if the item in question has been assigned to a preventive maintenance (servicing) plan.
    Answer in question itself,need to cancel all documents of wrong currency in order of LIFO,
    Create a new purchase order.

  • Lock Purchase Order fields after goods receipt

    Hello everyone,
      I need to be able to set a couple of fields in ME22N as display only after goods receipt has been done for the PO. Is there any config that I can do to get this done? Any idea or suggestion?
      Thank you very much for your help!
    Kelly.

    You can change PO after GR in standard SAP and there is no standard customization feature available to block that.
    Use ABAP to check for GR against the PO and block PO fields once GR is posted.
    Use tables MKPF for GR posting, EKKO and EKPO for Purchase Order.
    ABAP will have to change the field status of Purcahse Order screens as blocked, if GR is posted.
    It might be added as a subroutine that gets triggered after each GR posting.

  • One issue regarding update open Qty. of PO in PP/DS after goods receipt through interface.

    Dear experts:
    We are implementing APO-PP/DS integrated with Non-SAP ERP system, as the standard CIF can’t be used between ERP and APO, we have to use BAPI to transfer data.
    Now we are facing a problem, after final confirmation & goods receipt of production order in ERP, the open quantity of production order should be updated in PP/DS, but we can’t find any BAPI can help on this.
    We’ve tried BAPI_MOSRVAPS_CONFHEADMULTI and BAPI_MOSRVAPS_CONFOPRMULTI for production order confirmation, but failed, as SAP said, confirmation without goods receipt will not update the order open quantity. We also tried BAPI_MOSRVAPS_SAVEMULTI3 to change the receipt quantity, but failed, as after partial confirmation, the quantity of production order can’t be changed, but we can’t find a field of “open quantity” (open quantity = total quantity – delivery quantity) in the BAPI. So how can we update the open quantity of production order in PP/DS after goods receipt from ERP?
    Appreciate for your input, thanks.
    Regards
    Kevin

    Dear Uli
    Thanks for your information, we tried it again according to your
    instruction via Function module /SAPAPO/CIF_ORDER_INBOUND, but failed.
    For import parameters:
    OBJECTTYPE = 6
    LOGSYS = “Our logical system”
    The screenshot is as following:
    In the IT_OUT table:
    ORDNR = “Production order number in our ERP system”
    ORDERGUID = “Internal order number of this production order in
    APO” (we also tried to keep this field blank)
    METHOD = C
    GR_QUANTITY = 2
    The screenshot is as following:
    The ET_RETURN has no response
    And nothing gets update in product view.
    Is there anything wrong in my parameters?
    Thanks & Regards
    Kevin
    Best Regards

  • Import Declaration after goods receipt - Inward Processing Help

    Looking for some advice on setting up Inward Processing as I am running into issues.  Our system makeup is this:
    ECC - 617
    GTS - 10.1
    One of our facilities is setup so that they have duty deferment for imported components that are used in manufacturing and re-exported within a 36 month period. Based on this requirement we have determined that we could be leveraging the Inward Processing functionality in GTS to manage / track the inventory for duty purposes.  With that being said, this is what I have configured so far.
    Configuration:
    Purchase document in ECC is setup to transfer to GTS and create an import customs document, the check box for Customs Services is checked.  The corresponding purchasing document in GTS is activated for compliance and customs services.
    Inbound delivery in ECC is setup to transfer to GTS.  I am worried I have done something wrong in this configuration with how it maps in GTS. The document is currently creating a customs document that can be viewed in the import side of compliance.  The document type I mapped in GTS “Inbound Customs Delivery”
    Movement type 101B has been configured to come over from ECC to GTS.
    I configured in ECC the prelim. Document type T1 and also maintained that doc type in GTS which I mapped as prev. doc cat 01.  I then assigned Service LECTPR with prelim doc type category 01 as duty unpaid and target procedure 01 – Transit.
    I configured the authorization for both transit and inward processing, created the “license” for these items, and configured the activity sequence for the matching legal regulation.
    My process has been this:
    Create purchase order in ECC
    Create inbound delivery in ECC
    Update inbound delivery with the prelim doc type T1 and doc number / date
    MIGO with reference to the inbound delivery (movement type 101 against purchase order stored in MSEG)
    In GTS I go to create a customs declaration AFTER goods receipt, but I get a “no data found” information message.  When I debug I can see the that a check is done to pull records from table /sapsll/cuswlo, I have no entries in this table.
    I can see all the documents definitely made it over to GTS because they show up in the General List of Display Customs Declaration Quantities and Goods Receipt quantities (/SAPSLL/CUSWLM).  So at this point I have to be missing some key piece of configuration to allow the Import Declaration to create so the goods become available for inward processing. Any ideas on what I should be looking at that could be missing?
    Rachael

    Ok, then that's (at least) what you need to fix.
    In the Plug-In area, make sure that you've added your Inbound Delivery type to transfer for Customs purposes ("Query Customs Management for Document Type"), and that the technical activation has been turned on for Application MM0B.  For the moment - although it shouldn't make any difference - don't tick to transfer the Inbound Delivery for Compliance Management, or for Placement into Customs Status before GR.
    In GTS, make sure that Document Type 'TRLOIM' is active for Transit, and that the Document Type has an active Number Range.  Then check that the Legal Regulation for Transit (TRSxx) is active for your country code and that the Process Template is assigned in the Control Settings.
    Then see if the IBD is transferred ok.
    Regards,
    Dave

  • Purchase Order Module  - Goods Receipt PO - Goods Return - AP Invoice

    Hi all expert,
    I have a senario is :-
    Open Purchase Order Module  -> Goods Receipt PO -> Goods Return -> AP Invoice
    Puchase Product A by "Purchase Order" with Qty 6,000 After "Good Receipt PO", found out 3,500 pcs is out of spec then "Goods Returns" 3,500 pcs. Then continue do "AP Invoice" with Qty 2,500 pcs.
    Question is 1 week later, the supplier replacement back 3,500 pcs, so how am i going to start to steps? since PO have been close.
    When i at  "Goods Receipt PO" wanna to copy from "Goods Return", it is show nothing.
    Your advise is highly appreciated.
    Thanks.
    Regards,
    Danny

    Hi Danny
    i think you have to create a new PO then GRN then PI...since you copied the PO to GRN it will show as closed as there is a target doc. linked to the PO. A PO can be changed only if there is no target doc linked to it .
    Hope this helps.
    Bongani

  • 2LIS_02_ITM delta missing after good receipts

    Hi everybody:
    We are using 2LIS_02_ITM for extracting purchase order, in some cases, delta changes are not uploading to BW, it seems, when good receipt is posted.
    We have found the note
    Note 485650 - BW: Missing entries in delta queue after goods receipt.
    But this note is for SAP_APPL 4.6 and our version is SAP_APPL 4.7 patcht level 14.
    We have no be able to find a note for our release but we think that the poblem should be similar than described in that note, but any other clue is good received.
    Thank you.

    LBWE -- maintain Lo **** pit
    Step by step
    Go to RSA6 and check the availability of the data source
    if data source is not available then go to RSA5 (all business content object available here) make a copy of the required DS.
    RSA6 - check the DS is available or not..
    lbwe - lo customising **** pit...
    select required fields - hide - inversion...
    do statistical setup run
    login to bi
    replicate DS..
    go to info package
    do initalization delta   (Delta Q will be generated only after a successfull delta initializtion done.  when you do the same system will load historical data from setup table after loading from set up table (init delta) delta Q will be get posted with records for all changes/creation which is happening in R/3 (related to MM) through events. )
    i suggest you should go for unserialized v3 (store and transffer on demand )
    1. V3 Unserealized ---unsort records
    Unserialized V3  -> Update Q> (V3 Coll. Run)---> Delta Q
    [When a transaction happends those delta will be get posted in Update Q, in order to transfer those record from update Q to Delta Q you should do V3 collective Run, (the process of loading data from update Q to delta Q is known as V3 Collective Run) ]
    2. Qued Delta  [SAP recommended]--
    It will not sort record or stop record while transferring to to delta q but will continue until the whole record finish.  it will have the track of failure record
    3. Direct Delta  --->Delta Q
    it will directly post records to delta Q when transaction happends
    hope it will help you
    binu v. rajan

  • Change Conf.Ctrl (ekpo-bstae) after goods receipt on ME22N

    Hi all,
    we have the following issue:
    is it possible to change the field  "confirmation control key" (ekpo-bstae) after goods receipt on transaction ME22N?
    Thanks in advance and best regards.

    Hi
    Let me explain in details about your requirement
    It is not possible to change the confirmation control key after a goods
    receipt because it is very complicated or impossible to calculate the
    MRP-relevant quantities or the reduced quantities for MRP new when
    there exist some confirmations yet. With the confirmation control key
    ou fix the rules for the calculation of the MRP-relevant quantities.
    If you then change the confirmation control key (and before you had
    some confirmations) and with this change you get completely new rules
    it's impossible to get the correct MRP-relevant quantities.
    Note 451060 discusses potential problems that may occur when the
    customization of an existing confirmation control key is changed.
    The reason why after a partial good receipt the field confirmation
    key is greyed, and the reason is that there is a link between the
    confirmations and the GRs. If you change the confirmation control key
    this link can get lost (the link is the field ETENS in tables EKES and
    EKBE). If this would be possible you would get a lot of inconsistencies
    in the system.
    Note 451060 contains the changing of the customizing of the
    confirmation control key, which is nearly the same as if you would be
    able to change the control key in the purchase order after a goods
    receipt.
    regards,
    Ramana

  • Report to Purchase Orders with Good Receipt and pending for Invioce Receipt

    Hello,
    I'm looking a report bring me Purchase Orders with Goods Receipt and waiting for Invioce Verificacion (MIRO).
    I appreciate any help.
    Regards,
    Hector

    Hi,
    ME2N - In selection screen, enter Selection parameters as
    WE102 i.e. Goods receipt exists and in output screen put a filter on "Still to be invoiced (qty)" and "Still to be invoiced (val.)" as not equal to zero OR greater than Zero.
    OR use RECHNUNG i.e. Open invoices and execute the report
    OR Use MB5S - GR/IR Balances

  • Possible to Update ERS indicator on PO after Goods Receipt

    He all,
    We had failed to update the ERS settings in the plant data view of the vendor master purchasing data. We have about 1000 PO that were supposed to be paid through ERS but are now not invoiced. Is it possible to set the ERS Indicator after Goods Receipt?
    Thanks,
    Justin

    You can change the Purchasing Group on the Org. Data tab in the PO header in ME22N.  If you have PO release strategies they will not be reset unless PGrp is a characteristic in your release strategies and you change PGrp to a value outside of the range the strategy is using.
    Also, in your system you may not be able to change the PGrp if the screen layout changes the field to display once a GR is posted.  You can see this in the document type field selection or "Define Screen Layout at Document Level".  If the PO release strategies are used, you may need to check the changeability setting for the Release ID.
    Hope this helps.
    Edited by: Paul Shrewsbury on Apr 4, 2011 3:06 PM

  • Automatic Purchase Order upon Goods Receipt 101/161

    Hi Guys,
    Hope everyone is well. I would like to know in as simple terms as possible, what is the use of Automatic Purchase Order upon Goods Receipt mvt 101 or 161. Can someone explain to me the purpose of this? or applicable in which type of business scenario?
    Because i think, if it is upon Goods Issue, then it is understandable, you would want to top up the stocks, but upon GR? Why?
    This is a non configuration question, just a business process question..

    >
    Nazrin84 wrote:
    > Hi Guys,
    >
    > Hope everyone is well. I would like to know in as simple terms as possible, what is the use of Automatic Purchase Order upon Goods Receipt mvt 101 or 161. Can someone explain to me the purpose of this? or applicable in which type of business scenario?
    >
    > Because i think, if it is upon Goods Issue, then it is understandable, you would want to top up the stocks, but upon GR? Why?
    > This is a non configuration question, just a business process question..
    This process is used in case of emergency when stock is required in the plant and we dont have time to first create PO and then get its approval and follow the normal process. In the case of emergency, we tell the vendor to deliver the material and on receipt of this material we take it into the system through GR and the corresponding PO is automatically generated.
    Usually this is option available in system, but it depends on the clients requirement whether they want this option available to end users or not. Mostly our clients prefer not to have this option enabled, as this way can lead to irregularities by the users.
    So they prefer to follow the normal process, but this process for above scenario is followed on war footings that way the GR takes place immediately when Goods are received.

  • Last purchase order and goods receipt for material

    Hello to everyone,
    is there any standard report where I can see the last purchase order and goods receipt for a material?
    Regards

    Hi,
    Latest PO you can get from ME2M, by giving input as material and scope of list as best.
    Latest GR date can be get from MB51, by giving input as Material and movement type as 101.
    Regards,
    Prabu

Maybe you are looking for

  • Java Web Start aborts after upgrading to 10.4.4

    After the upgrade to 10.4.4 Java Web Start (and any clients) aborts as soon as I try to launch them. I have two clients (CGoban2 and Pokerpages Poker Client) I think uses Java Web Start and they worked fine under Mac OS X 10.4.3. Even if I try to sta

  • How to connect to the internet

    I installed Solaris Express Developer Edition 9/07 yesterday.I have a ADSL USB modem AT-AR206.I want to know How to create a connection to the internet

  • How to make the Wallet opened automatically?

    Hi All, I want any wallet that I created to be opened automatically without executing an order to do it. How Plz?

  • Chart/Columns labels

    I am building a Column chart I'm not sure what its called but its where you add different series together to make a column chart (this option is second from the top and on the left side in the charts selector). I would call it a additive column chart

  • Unable to update application error