Goods receipt for Shedule agreement

hi all
we are using SA to go for subcontracting .
Process is like creating agreements by  ME31L and then Delivery schedules are created by ME38.
then goods are issued to subcontractors by MVT type 541 with SA as ref.
then challan is created by J1ifo1.
GR is divided into 103 first at gate and then 105 entries at shop floor.
we made 3 103 entries for a specific SA .now when we try to do 105 we are getting the error message
Of the required quantity of material &, & & remain(s) open----this message has status Error in customizing in standard. version is 00 and application area is LB which is for batches.
does anybody has any idea  regarding the above message? what could be the possible reason for this?
thanks in advance for ur considerations
raja

HI ALPESH PATEL
THNX FOR UR HELP. BUT I CHECKED THE 103 MVT AND IT WAS ACTUALLY TO BLKD STOCK SINCE THE MOVEMENT ITSELF IS GR TO BLKD STOCK.(103).AND ALSO IN MB5B THERE IS NO REVERSE FOR 541 AND ALSO STOCK IS AVAILABLE AT VENDOR SIDE.
MOREOVER THERE IS NO CHANGES IN BOM OR INFORECORD SINCE THE DELIVERY LINES WERE CREATED.
MESSAGE WAS ACTUALLY THE SYTEM COULD NOT FIND THE COMPONENTS SAYING THE MAIN ITEM COULD BE ZERO OR NO BOM COULD BE THERE. BUT BOM WAS CREATED WELL BEOFRE AND 103 QTY WAS ALSO CORRECT. I CHECKED THE 103 QTY AND ALSO CHANGES MADE IN BOM.
THEN I TRIED CANCELLING THE 103 AND AGAIN DOING 103 AND 105 WITHOUT REEXPLODING OR MAKING ANY CHANGES AND IT WENT OK. I JUST WONDER FOR THE CAUSE.
HOWEVER THX FOR UE HELP AGAIN
RAJA.

Similar Messages

  • Goods Receipt For Scheduling Agreement

    Dear Experts,
    Can anybody please explain, the step by step procedure for the Goods Receipt of Scheduling Agreement.
    I have created scheduling agreement (ME31L) and delivery schedule (ME38) with 15 schedule lines (e.g. from date 01.04.2008 to 15.04.2008).
    But in goods receipt it is showing the single line with total ordered quantity. so how to take the reference of actually scheduled quantity for posting goods receipt ?
    Thanks in advance

    Hello Kiran,
    Let us assume your total quantity is 15 that mean 1 qty each day (from 01.04.2008 to 15.04.2008).
    On 01.04.08 system will allow GR of 1 Qty only.... in this way, you will get 15 Qty after 15 days.
    But in case you donu2019t do any GR up to 14.14.08 and on 15.04.08 system will allow doing GR for all 15 Qty. And same will come in single line.
    If you do GR on daily basis, you will get the reference with schedule qty.
    Rewards are helpful.

  • Goods receipt for Schedule Agreement

    Hi
    I cannot make a goods receipt today, for a future schedule line date, in a schedule agreement, in MIGO transaction. I know it is standard functionality, but please inform is  there any settings available to make it happen.
    Also i would like to know whether the goods receipt for a future schedule line is possible in MB01 transaction.
    Regards
    Arvind

    Hi,
    1. In JIT it will allow only exact date what it is showing in that SA schedule lines...
    But we can manually cahge the date we can do the MIGO. But in this case i hope there is no setting ....
    2.I hope there is a link B/w Calendar if we make as working day it will allow i hope
    Regards
    Murugan J

  • Goods Receipt for scheduling agreements

    Dear Experts,
      I have created schedule lines through MRP in MD03. But when i tried to do  goods receipt for that scheduling agreement , it is telling
    "Document xxxxxxxxxxx does not contain any items ". I am doing GRN w.r.to that scheduling agreement. How do i do GR w..r .to that scheduling agreement ? I dont have release for sch.agreement. Kindly help me..
    Regards,
    BBR

    Hi,
    Go to MIGO enter the Sch.Agreement number  and do the MIGO
    Please check the following
    1. Whether Delivery date is today date (MIGO date)
    2. Whether Delivery completed indicator is set.
    Regards
    Ganesh

  • Goods receipt for schedule agreement  / schedule line

    HI Dears,
    could u pls help me, how to carry out goods receipt - MIGO- for sch agreement po or sch ag sch lines.
    thanks in advance
    rgds
    Jay

    It's a normal process as we do for Normal Po in MIGO...
    But the GR allowed on the scheduled Delivery date...
    Go to MIGO Select Goods recept & Purcahse Order
    and  Enter the SA number in the Purcahse Order  filed..
    Edited by: Manohar Raju on May 15, 2008 7:04 PM

  • Unable to create Goods Receipt for Scheduling agreement

    Hi,
    I am have setup Scheduling agreement. When i try to create the Goods receipt on MIGO by entering the agreement #, I get an error : Purchase Order not yet released.
    Please help, I couldn't find similar issue reported on this forum.
    Thanks
    Ramya

    Release SA by T-code ME35L , If it's PO Release by ME29N

  • Error in good receipts for sch.agreement

    hi frnds,
       while i make gr w.r.t sch.agreement. it is telling that " Document xxxxxxxxx does not contain any items ". i have maintained delivery schedules in day format. and iam trying to do gr in tht date too. but still it is not showing.
    how could i resolve..kindly help me..
    regards,
    prasath

    Hi Prasanth,
    There have been several reasons which can be attributable to this problem -
    1) This PO is subject to release strategy and since the final release was not made, this PO is considered as 'blocked'.
    2) You have been using the confirmation control category where in respect of the last confirmation category key, the GR assignment check box is flagged. In this particular case, GR is only be posted if the confirmation is not maintained.
    3) Early delivery date i.e. the GR date is coming earlier than the PO delivery date.
    Check also the movement type used:should be 101.
    Regards,
    Nani.

  • Transaction BORGR: No tolerance on goods receipt for Kanban calloff

    Hello,
    we have the following situation:
    - MM scheduling agreement with tolerance of 10% for under and overdelivery, production supply "summarized JIT call" is set.
    - KANBAN cycle has 1 empty container with a summarized JIT call for replenishment, quantity 10 pieces.
    - ASN has been created with BORGR transaction, it contains: 1 line item for the material with delivery quantity 9 pieces, assigned to this line item is the JIT call with notified quantity 9 pieces as well.
    My expectation was that the JIT call can be booked with 9 pieces as it is inside the 10% tolerance defined for the scheduling agreement. In addition, I expected the KANBAN container be set to full.
    Instead, the following error message is given:
    'Post GR' carried out without success
    (Message no. BORGR215)
    Because of previous error, dispatching is not possible for ID 0180573431
    (Message no. /SPE/ID_HANDLING011)
    Inbound Delivery 0180573431 00010
    (Message no. BORGR210)
    Total of the summarized JIT calls does not match the current delivery qty
    (Message no. BORGR540)
    Changing the delivery quantity and the notified JIT quantity to 10 pieces, the goods receipt is booked correctly.
    I only found the following notes that deal with tolerances but they are outdated, as we are using DIMP release 603:
    https://service.sap.com/sap/support/notes/393421
    https://service.sap.com/sap/support/notes/508215
    Has anybody faced a similar problem or can help me with this?
    Thanks!

    Hello Jiaul,
    Sorry I may have mislead you.  The actual error message is "Goods Receipt for Production Order XXXX can only be made on 2010.08.25 to 2010.08.27".  These two dates are the Start Date and FInish Date for the Production Order in CO03, 
    The Basic Start Date for the current Production Order is  2010.08.25
    The Basic Finish Date for the current Production Order is 2010.08.27
    I think what it means is that you can only Post Goods Receipt for the Production Order only after the Basic Start Date of the Production Order.  Do you know where I can find the configuration for this message?
    Thanks

  • Reversal of a goods receipt for PO in EUR is differently valuated.

    Hi,
    Do you know how can i solve such problem:
    The return delivery or reversal of a goods receipt for a purchase order, scheduling agreement, or production order is valuated differently than the original goods receipt becouse system takes exchane rate form the posting date. I wolud like to have such solution that system would take exchane rate from dokument date. Is that possible?
    Maby you know some sap Notes?
    Thanks for reply.
    Katarzyna Gac
    Edited by: Gac Katarzyna on Jun 10, 2009 3:47 PM

    Hi
    In the header of the PO there is a provision.
    Check the box in the header Exchange rate fix Under the Tab Delivery/Invoice.
    Exchange rate will be fix  from then onwards.
    I am suggesting for PO because for external procurement PO will always come into picture.
    Regards
    Ankur

  • Perform Post Goods Receipt Against Scheduling Agreement

    Dear all,
    I've weird problem here. This is concering GR against Scheduling Agreement. I've a "LPA" type Scheduling Agreement and all the delivery schedule maintained and schedule line released successfully in ME38.
    When I do GR via MIGO by entering the Scheduling Agreement #, a prompt was given with no items selected. Note: My schedule line delivery date = GR posting date.
    What I did was, inside MIGO I go to Settings | Default Values and check on "Propose All Items". Finally, the affected line item appears but with "blank" quantity. So, I key in the actual quantity per the released schedule line and complete the GR posting successfully.
    Question 1: Why do I need to perform the MIGO propose all items setting? Normal PGR against PO doesn't require this.
    Question 2: Is this a standard SAP behavior or I'm doing PGR - scheduling agreement process the wrong way?
    Appreciate any expert clarification.
    Thanks in advance.
    Steven

    Hi Jurgen,
    I've read Notes 493404 and I'm facing Question 10
    10. Question:
    For the goods receipt for the scheduling agreement the system displays error M7 064: "Document xx does not contain any selectable items".
    Answer:
    A possible reason is that the document is subject to a release strategy and has yet to be released. You can check this using transaction ME33 and release it subsequently if necessary.
    Another reason can be that although a confirmation control key that contains a confirmation category with GR assignment has been maintained for the scheduling agreement item, this category has yet to be confirmed. You can check this using transactions ME33 and OMGZ. If necessary, create the relevant confirmation.
    Another reason may be that no undelivered schedule line exists up to the posting date. If nevertheless you want to post the GR, you can use transaction ME38 to bring the next schedule line date forward, or in transaction MB01 you can select the "Suggest Zero Lines" field or in transaction MIGO the "Propose All Items" field under Settings - Default values.
    From the snapshot of the notes 493404 above:
    1. I don't have a release strategy for the scheduling agreement. Have checked via ME33L
    2. I didn't implement any confirmation control in the scheduling agreement. Have checked via ME33L
    3. I've a delivery schedule line up to the posting date. In my scenario, schedule line date = GR posting date
    Therefore, I'm still truly puzzle with the system behavior. Any further help will be most appreciated.
    Thanks.
    Steven

  • Good Receipt against Scheduling Agreement

    Hi,
    I have created Scheduling Agreement and maintained delivery Schedule.
    No while making Good Receipt against scheduling agreement, system give message that no item exist.
    I have given date in delivery schedule for e.g 27.06.2008 and I am entering good receipt on 26.06.2008. But it is not possible.
    Once I change the date to 26.06.2008 in delivery schedule, then system allow to post a good receipt.
    Why, Is there any setting to remove this?
    Waiting for your reply.
    Thanks,
    Samir Bhatt

    Hi,
    Definition of Scheduling Agreement: - A form of outline purchase agreement under which materials are procured on predetermined dates within a certain time period.
    This means schedule lines are fixed and you can only do Goods Receipt on the prodefined schedules. If you do not want this function then better create Contracts and then PO w.r.t. Contract.

  • How to post good receipt for an inbound delivery with HU in the stock?

    Hello,
    We have an inbound delivery of a purchase order with 10 Handling Units inside on.
    The HU's has been put in a storage bin (by transport order + confirmation) before a good receipt has been posted for the whole delivery.
    Due to this it's not possible to post good receipt for the inbound delivery, and the available stock quantity is in minus on zone: '902-GR Area External Rcpts' since  the handling units are already in a storage bin.
    Can anyone help me on this matter?
    Thanks

    Hi,
    my situation is:
    - a WM managed warehouse, society A;
    - a HU managed warehouse (without WM), society B;
    - a purchasing process of HU from society A towards society B.
    Society B have a scheduling agreement; when a delivery schedule appears, in society A born a sales order and a delivery. After the registration of the delivery good issue, an idoc transfer information for inbound delivery creation.
    This process is ok without WM, but with a WM managed warehouse the idoc has the following problem:
    "V51VP - item was not found - process cancelled".
    Can you help me to transfer these HU?

  • Doing a goods receipt for a customer material that is ASEQ status

    We are needing to find a way to be able to do a goods receipt for a child part in ASEQ status.  Most of our customers will send in their part after disassembling it themselves.  Since we can not receive the part our present process is to dismantle so the system status changes to ESTO and we can receive.  The problem with this is that the end user forgets to assemble the part back and we end up breaking the linkage.
    We have looked into using User Status in the equipment master and have configured that.  However the user status button, nor name shows up in the equipment master.  I have looked at the field selection in IMG and it is not hidden.  I am assuming it is being supressed by a user exit we have.
    Can anyone give me any suggestions on how we can improve the process using SAP for material that is ASEQ status and being able to create an inbound delivery so we can receive in our warehouse for this status without dismatling the unit? 
    We are on ECC

    Hello Kimberly
    You lost me while describing your current process, so  please provide more details as to how you dismantle and reinstall etc.  Also how the part goes back to the customer.
    However I can provide you  clarifications to some questions you raised..
    You see both system and user statuses in the field 'Status' itself. This is the 3rd row in the Equipment display screen under Equipment number and Description. If you see carefully you will see 2 sections, the one on left is system status and the one on right is User status. If you click on the i (info) icon, you will be taken to a screen where you see more info like status and business processes etc.
    ASEQ is a system status and it is determined by what you did ( example dismantling) and can't be changed by you (user). If you see the 'Business Processes' tab, you will also see the this won't allow assignment to a Delivery and so on. So my point is having a user status will not help you. Based on the combination of system and user statuses, some processes are permitted, some not. For example if Goods Receipts are allowed, may be you can receive without an Inbound delivery.  I am mentioning this as a thought initiator, I know you will have a Return/Repair order process including a return delivery.
    I guess you have to systematically prevent the user from  doing whatever they are doing out of turn, e.g., forgetting to reassemble (install?) and for this User statuses can help.
    Let us know your process more in detail and I am sure SAP will have a standard way to receive a child part of a big assembly. Other members will share their practices also.
    Take care.

  • Value of inventory after Goods Issue, before Goods Receipt for open order

    Dear Experts,
    Raw materials R72 and R82 are required to produce Semifinished Product S10.
    Semifinished product S10 is required to produce Fnished product F20
    On 10th August 2011, I created and release a Process Order for material S10 copying component materials R72 and R82.. Goods issue for component materials R72 and R82 were done for this process order using tcode MIGO (mvt type 261).
    It  takes four to five days to properly blend components R72 and R82 to obtain S10.
    It means Goods Receipt for this process order will be done on 14th or 15th August when this blending has been completed.
    Management suddenly issues a directive that stock take should be carried out in the plant on the 12th August 2011, and my process order is still open and cannot be closed ( or goods receipt cannot be done)  because blending is yet to be completed.
    Please how do I take care of this scenario/situation since Goods Issue has been done already?
    How will the Accountants see or get the correct value of inventory?

    When I run WIP Calculation for my Process Order, what will be the effect ? I mean what accouts are updated by WIP Calculation within a period (not across a perion or  at period end)?
    GI values issued to the Process order will come into WIP GL .( Since your client want to know the stock take should be carried out in the plant on the 12th August 2011- we are doing WIP calculation)
    > After  this WIP Calculation is run,  and say about 2days later, Goods Receipt for this process order is to be posted, what steps am I suppose to carry out?
    After GR Made, Run a WIP calculation again for the order so that The WIP from the GL account will get reduced ,now WIP= (GI value + confirmation ) -(GR Value),
    Check in DEV system before doing in PRD,
    On Month end, do the variance calculation and do the settlement

  • Error while doing Goods receipt for process order. Error code: "BS027"

    I am getting error while doing GR for a day whereas previous day(s) GR is already done and also 2 days post that day are also done successfully.
    Error :  ""Goods receipt for prodn. order" is not allowed (ORD XX-CEMTSAL) " (XX = First two characters of plant code)
    Error code: BS027.
    Thanks to all in advance.

    Hello,
    This issue would occur when you want to post a confirmation for a production order. The error message is generated if you wanted to post a backflush for a component and if this component was assigned to a sales order stock. The sales order itself was assigned to a work breakdown structure element which should be debited with the actual costs. However, the business transaction 'Confirm' is not permitted for a work breakdown structure.
    Please look into SAP Note 62367 and 64370
    Hope the information is helpful
    regards