How to track costing in Production order

Hello Everyone
I would like to get some details about how to set the product costs for Finished Goods and also how to track the expenses like packaging, labor, electricity, other charges etc, for individual production order.
I have created the labor and packaging as a non inventory item and have used it in the BOM, now after the production order is closed, i find these two costs to be in the Actual Additional costs as shown below, till this is great.   
But the requirement was, when they want to view the expenses or a month, then they require individual split up of costs against each production order. Is this even feasible?
Please require help from you guys.
Appreciate your help in this regard.
Thank You

Product Costing
The cost of a FIFO or moving-average product is the sum of its component costs and additional costs (such as labor and overhead). To ensure accurate calculations of product cost, even if the components were issued manually, SAP Business One uses the cost of the items issued to production order and not the cost of the items currently in inventory. This avoids differences between the actual cost of components used in the order and the value of the product.
Note
The cost calculation method described here is relevant only for standard and special production orders, but not for disassembly for companies managing perpetual inventory.
In the case of disassembly the components enter the inventory with the same cost as the items currently there. If the component is managed by FIFO, the cost of the oldest layer is used.
The cost of returned components does not change; it is the cost of the last one that was issued.
The product cost calculation is determined by the item management method.
Standard – When the product is managed by standard cost, no calculation is made, and the cost is copied from the item master data upon report completion.
Moving Average – When the product is managed by moving average, two figures are required for product receipt into inventory: receipt quantity and total value added to the inventory. The total value is the product cost, which is the sum of all component costs used for those products.
FIFO – When the product is managed by FIFO, each report completion opens a new cost layer for the product in the inventory. The quantity in the layer is the quantity of the products just reported as completed. The cost of the products is the sum of all component costs used for the completed products divided by the quantity of the products.
On every report completion, the system checks the following three quantities for each manually issued component:
Issued Quantity – The quantity already issued to the production order.
Used Quantity – The quantity already used for the completed products (completed products multiplied by the base quantity of the component).
Needed Quantity – The quantity needed for the products that were just reported as completed (quantity of products reported as completed multiplied by the base quantity of the component).
If the Used Quantity is greater than or equal to the Issued Quantity, this means that all items issued for the production order have already been used, and the Needed Quantity is yet to be reported as issued from the warehouse. Since the cost of the items that were actually used for the products is unknown, SAP Business One takes the current prices from the inventory.
If the Issued Quantity is greater than the Used Quantity, SAP Business One finds the cost of the components that were issued and not used, and uses them in the calculation of the product cost. When finding those components, the issuing order of the components is taken into account, meaning that the first components to be issued are the first to be used. The components following those that were used are the first to be used for the cost calculation.
If the sum of Needed Quantity and Used Quantity is greater than the Issued Quantity, meaning that not all needed quantity was issued, SAP Business One needs to make an assumption for those items’ costs, so it takes the current prices from the inventory.
Upon the completion of a production order, on the Production Order Window: Summary Tab, you can check the product cost figures of the production order.
Regards
Kennedy

Similar Messages

  • How to see cost componentwise production order actual cost-not planned cost

    Hi,
    Can anybody tell me how to see cost componentwise production order actual cost ?
    Thanks,
    Bijay

    Hi,
    CO03->Goto-> costs-> Anlysis
    or use the std. report KKBC_ORD
    std. reoprt MCRI
    KVBI - Actual Costs
    Regards,
    R.Brahmankar

  • Actual cost of Production Order settled to Fixed Assets

    Dear all,
    My client is doing in-house production of moulds (internal order suggestion is not accepted by the client) for which
    they have the following
    1. BOM
    2. Machine hour
    3. labour
    4. overhead etc
    5.plan value
    6. actual value
    Can i settle the actual cost of production order to Fixed Asset ?
    If yes
    what are process kindly give me if any process other then the below
    1.production order created
    2. settlement profile - FA is settlement optional
    3. allocation structure
    4. Asset created
    5 define asset in settlement rule
    Kindly give me your valuable input
    regards
    elango

    Hi,
    Although i am not CO expert , please check with your FICO consultant who are expert before make the final call.
    During settlement to a G/L account or a fixed asset, the system ignores additional account assignments that were manually specified in the distribution rule.
    Based on what i know .
    you can stipulate that settlement may be made to cost centers and orders, but not to fixed assets.
    The Settlement profile is something that you need to create a settlement rule to settle the actual costs of a sender object.
    About the Settlement rule is something that  contains the distribution rules for the sender. It will define how the way to settle the cost.
    Allocation Structure
    In the settlement structure you combine the primary and secondary cost elements into groups, in which debits are then posted to the sender objects. For each group, you specify whether (for settlement to a given receiver type) settlement is performed
    by cost element or using a settlement cost element.
    For example, you might use settlement cost elements:
      To document the purpose of an order (such as, repairs or maintenance)
      To reduce data volumes (you can combine a number of debit cost elements
    under one settlement cost element).
    TQ

  • How to confirm the CO Production Order?

    Hi,all
    The PP Production Order can confirm by TCode CO15.
    Then how to confirm the CO Production Order(Created by KKF1)?

    Hi,
    As you are aware that Co Production Order is being used when there is no quantity structure. Hence, there shall be no routings with details of activities and the quantity of activities, etc and we cannot use confirmation as we are doing in regular Production Corder. Consequently,  we are left with one alternative of passing on the activity cost(qty x price) to the CO Production through Direct Activity Allocaiton(KB21N).
    Trust this helps much!
    Cheers!

  • Function module for calculating planned and actual cost of production order

    Hi ,
    Do we have any standard function module for calculating planned and actual cost for production order?
    i need to implement this in a Z-report.
    Thanks
    Srini

    Hi,
    try below function module
    CRMCO_GET_PLAN_ACTUAL_COSTS
    CO_IH_GET_PLANNED_COSTS_TOTAL
    Regards,
    Sankaran

  • To see the cost of production order  after settlement to header material

    hello guys,
       In make to stock,we settle the total cost of prodution order on header material,right(if we keep as the default rule( distribution rule in order type)?
         If i want to see that cost of production order which we settled against the header material,where should i check it?should i check in material account or somewhere else?
             Thanking you guys in advance.

    Dear,
    There is a little missunderstanding in your thought.
    If the material of price control S, When you do the GR, the STD cost of material is deducted from production order cost, then when you settle the production order, the variance is settled to variance account/PD account. hence the production order cost balance is zero.
    Example- Production order cost is 60000
    After GR the production order cost balance is 60000-50000 = 10000.
    After settlement production order cost balance is zero.
    Now your question is where can i see the production order cost?
    You can see the production order cost in the production order itself.
    In the production order...cost disply option just filter the origin with test settlement and GR.
    Then total up the cost, then you can see the cost as 60000.
    please come back if you need more help.

  • Material cost in production order plan cost

    Dear all,
    -we are in sales order cost object with non-valuated stock...
    -we have created two production orders from MRP run. First one is for semi finished material and second one is for finished material.
    Issue-1
    Both production orders not showing material cost in production order plan cost...
    Issue-2
    When i consumed raw material against semi-finished material production order (261-E), system not gnerated any document and material cost not updated either in production order or sales order...
    where should i do changes in configuration to get updated material cost in the production order...
    Best regards
    Kishore

    Hi
    Issue 1 : Check Whether Standard cost is present for header material of prod order, and under control tab of order costing variant for plan is present.
    Issue 2 : Use 261 instead 261E.
    Rajneesh

  • Costing the production order for the configured material

    We are trying to cost the production order for a configurable item.  But the system is not calculating any cost in the production order.  Sales order related to this configurable material is costed.  What additional setting I need to cost the production order for the configured material ?

    Hi Niki
    If your SO is costed, thats enough from a System's perspective... Planned cost will be the sales order cost estimate because SO saves the Chars required for the Configurable material
    Planned cost in Prod order depends on the Costing variant you have assigned in the order type... Check the error log if there is any error in cost calculation in prod order
    br, Ajay M

  • Operation wise cost through production order

    Hi Experts,
    Is There any standard report to get Operation wise cost through production order.if it is there please provide the details.
    Thanks & Regards,
    Prabhakar

    HI,
    I don't know a standard report but table CKIS contains the costing details line item wise with the corresponding operation number (CKIS-VORNR).
    So a query/quick view using KEKO + CKIS should be sufficient.
    Best regards, Christian

  • How track changes in production order which is already Read PP master data

    Hi Gurus,
    Due to some unavoidable reason my client has to do Read PP master data time and again, now my client having a requirement that want to see what has been changes in Production Order.
    We already created 1 report for that which tracks whatever has been changed in Production Order but having a constraint in it.  That It could not be able to distinguish to which order READ PP MASTER DATA done.
    So my query is how to map that in report. As sytem Status directly changed to CRTD phase.
    Any table which can track the changes once the order been through with READ PP MASTER DATA?
    As there are huge number of Production Order so we can go and open each order to see the Status changes in each and every order.
    Hope to get a reply soon.
    Regards,
    Sap User

    Hi,
    A suggestion:
    Change the specification as, log changes at each save instead of Read PP Master Data, as the changes would become effective only upon save. So if this is acceptable then 2 options, 1. Go with OCM feature or 2. Refer note - 390635
    Revert if you face any issues.
    Regards,
    Vivek

  • How to know whether recalculate the cost of production order?

    Hi Masters
                    We know, the valuation of  goods receipt is determined by the plan cost of the production order for production order. But often, production order was recalculated after partial delivery to stock.
    So I want to know when was the PO recalculated?

    HI,
    You can go to Administration tab in production order, you can find who has changed last the production order.
    I still doubt, is it possible to recalculate the production order after partial delivery.
    Vijay

  • Actual cost of production order in inventory valuation

    Hi,
    Kindly tell me in our client requirement to "capture actual cost of drum manufactured. This cost will go to finished mixer. So actual goods receipt of drum should be with actual production order cost . Also actual mixer cost should be taken from actual production order cost. How to map this s cenarionin in SAP" ?
    Best Regards,
    Anindita

    Hi Shyam,
    In SAP product costing we use generally standard cost estimation. Raw material ara taken as moving averagae price as v and finished products are taken as standard price i.e, S. Before cost estimation we update plan price in material master costing view 2 for accurate cost estimation. In case of standard cost estimation price variance is occured which is post to separate gl account. Our client wants actual cost rather than standard cost. Without implementing material ledger is it possible to do actual costing in SAP. Please let me know the process of actual costing...
    Regards,
    Anindita

  • Adding fixed cost in production order and creating liability

    Dear All,
    We are manufacturing one of our grade of material in a plant which we do not own.We pay some fixed charges to the owner of that plant @ Rs150 PMT produced in that plant.This  fixed charges is to be included in the production order and at the same time liability for that  fixed charges is also to be created so that payment can be made to that vendor.
    For charging this expenses to the production order we have created one activity type and one secondary cost element.But with this the liability can not be created.
    Please advice how to proceed in this circumstances.
    Regards,
    Shivaji

    hi
    I am following this thread...but want to add some views on this..
    As I understood from your requirement that you are sending this material to a third party for some conversion with a fixed charge...so you must have a conversion contract with that party. In my views the process should be...
    1. Conversion contract with the party (MM)
    2. Material will be received from third party with conversion cost at the time of GR (MM)
         Example... Original cost + fixed conv cost = GR value
    3. Invoicing ... MIRO ..Party will be credited at fixed conversion cost
    4, When the same material is issued to another prod order the GI will be at cost as per sl.2
       Please revert back if you have any question
       Kamal 

  • Settling of Cost for Production Order via WBS Element

    Hi Gurus,
    Just would like to briefly understand, how I can make use of the WBS Element in the Production Order (Assignment tab) to use as cost settling for a production order? How do i automate the WBS Element in the production Order for a set of given parameters? Is there a config I can use to set a profile?
    I have a scenario here as below:
    I have various types of production orders:
    PO 1 = Production A
    PO 2 = Production B
    PO 3 = Production C
    And for each of the above, I will individually have a WBS Element.
    PO1 - WBS Element A
    PO2 - WBS Element B
    PO3 - WBS Element C
    And WBS Element A, B and C is a Level 2 WBS Element which are tied to WBS Element Z (Level 1 WBS Element), which will be settled to a project.
    Appreciate your kind feedback on the above on how I can make it work in the PP Order.
    Thanks.
    Rgds.

    Hi Manoj,
    I need to understand your process in more detail.
    How do you procure?  Create a sales order with TAS item category to create a PReq and PO?
    Very simple explanation: Resource Related billing/DIP profiles are used to accumulate costs on WBS elements and then bill the client as needed.

  • Recognizing external production costs for production order

    Hi Experts,
    Our company is new to SAP and one issue we have not resolved is whether it is possible to attach costs to an Inspection Plan, and ultimately have these costs flow with the production order to Cost of Goods Sold (COGS).
    The objective is to enable us to analyze which specific customers/products require us to incur these additional costs.  Any advice you have to accomplice our objective would be appreciated.
    We are a Process Industry, and many materials are sent out for external testing. These costs are significant and some customers and/or products require more testing. We currently have Inspection Plans set up for each Material that requires testing, but have not found a way to burden the material with the appropriate COGS for the external testing.
    For example, if a product must be tested for the following characteristics, and each test cost is known, how do we get the test costs attached to the production order for the total of $200?
    Product 1 Inspection Plan
    Salmonella $70
    EColi $59
    Coliform $25
    Yeast/Mold $46
    Thank you!

    Richard,
    Are you able to advise which forum is the proper one for this question?
    Thank you,
    Esther

Maybe you are looking for

  • RFC Lookup error after moving to Quality from Development

    Hi All, For a scenario,I am using the RFC Lookup in message mapping. I am not using it in a UDF but for directly for an target element.... The scenario was wrkng properly in development... but in quality it's not wrkng giving the following error....

  • Files not opening correctly

    When I try to open a 3rd or 4th file in Illustrator, all I get is a gray page. I get the rulers, but the artboard and document don't show. It appears to me that I am running out of memory, but why whouldn't virtual memory be kicking in? I have over 5

  • About the Calculated Key Figures

    Hi, I have included a CKF in the query. In the results area it is not showing any units. But it is required to show the units in the output of the query for that CKF. Pls advise.

  • Methods

    I am trying to create two methods to work inside one class and it keeps giving me the illegal start of expression at compile time. Any idea what I am doing wrong /tag mport javax.swing.*; import java.awt.*; import java.awt.event.*; public class Grade

  • How do I eliminate the "community Toolbar" compatibility notice/error??

    Hi everyone!  Thanks for reading and I look foreward to all useful suggestions!  My situation: With Safari running... 5.1.7 (but even on 5.1.6)  at some point i downloaded or installed some "community toolbar....i imagine it was a throw in with some