The default for our system was to run the Escalation task once an hour.  The customers want it much more frequently.
What are the performance issues with running it every 5 or 10 minutes.  Does the query just look at ongoing tasks and therefore is reasonably efficient or does it have to look at all tasks in the system?
How frequently are others running it?
Thanks

Are you able to escalate the ApprovalTask to approver's manager. If so, please help me.
I've implemented the ApprovalTask in SOA Composite.I need the task to be automatically escalated to the assignees manager if there was no action within stipulated time.
I get an error:
Error in evaluating management chain participantCould not compute the management chain from user rickyponting upto levels 2 upto title Manager. The management chian is used in the routing slip that is associated with the task definition default/TestEscalation!1.6*soa_d3607f68-6b7a-45e5-9c94-76f733af67c6/Humantask1Verify that the users are seeded correctly to compute the management chain.
Please help me!.

Similar Messages

  • RequestCenter Task Escalations

    Can somebody show me where to find newScale/Cisco documentation regarding task escalations?
    We would like task escalations to fire when a task OLA is breached, i.e. x hours after the task is assigned to a queue.  Is ths within the escalation rules?
    It appears that escalations are not fired until the task due date.  How are due dates calculated in regards to task start date and task OLA?  How do the task OLA, service SLA, queue time zone/calendar settings, affect when the escalation notices are triggered?
    Thanks in advance,
    Brian

    When the entire service is late -- meaning when the due date for the last task in the delivery plan has been breached -- the MONITOR Delivery task will also become late. When this occurs, any escalation notifications which are configured on the Plan tab will be sent for this task.
    While the MONITOR Delivery task does not need to be completed like other tasks, it does have a due date -- that date being the due date for the last task in the delivery plan. When this task is late it means the entire se

  • Monitor Delivery Task Escalations?

    Monitor Delivery Task Escalations?
    Should the monitor delivery task recipient be getting escalation notifications? If so, can they be prevented? When/Why are they triggered?  I have service managers complaining because they are getting escalation emails but the service is still ongoing, waiting for tasks to be completed. How can a monitor task be late? It's not really a task. Thanks!

    When the entire service is late -- meaning when the due date for the last task in the delivery plan has been breached -- the MONITOR Delivery task will also become late. When this occurs, any escalation notifications which are configured on the Plan tab will be sent for this task.
    While the MONITOR Delivery task does not need to be completed like other tasks, it does have a due date -- that date being the due date for the last task in the delivery plan. When this task is late it means the entire se

  • Task escalation through OIM

    Hi,
    Can any one please tell me about task escalation in OIM.
    I mean when approver is not approving a request within a given time period then request should go to next assigned approver for approval.
    Thanks

    Are you able to escalate the ApprovalTask to approver's manager. If so, please help me.
    I've implemented the ApprovalTask in SOA Composite.I need the task to be automatically escalated to the assignees manager if there was no action within stipulated time.
    I get an error:
    Error in evaluating management chain participantCould not compute the management chain from user rickyponting upto levels 2 upto title Manager. The management chian is used in the routing slip that is associated with the task definition default/TestEscalation!1.6*soa_d3607f68-6b7a-45e5-9c94-76f733af67c6/Humantask1Verify that the users are seeded correctly to compute the management chain.
    Please help me!.

  • How to acquire a % Late Task column and produce a visual graph in the report?

    Hi
    I'm looking for help to help count the number of late tasks within a project and to produce a bar chart of the % of late tasks compared to all tasks.
    Is this possible?
    Thanks
    Rob

    Hi Rob,
    The "status indicator" field gives you by default the information on the task status (late, future task, completed). You could simply build a SSRS or Excel Services report using this field and building a bar chart.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • How to set Task Escalation policy at participant level in JDeveloper11 vers

    Hello All,
    Hello All,
    We are developing a custom approval process for resource provisioning in OIM11g. At Operation Level, we are assigning tasks to Resource Administrator and Beneficiary Manager serially. We have a requirement like, task should never expire at Resource Administrator level, but at Beneficiary Manager level, it can expire and must be escalated to one level above.
    We are using JDeveloper 11.1.1.3.0 and we understand that in this version of JDeveloper, there is an option to define an Escalation policy only at Global ( Routing slip) level. Apparently, in this version of JDeveloper there is no option to specify task escalation/expiry settings at individual participant levels.
    Can anyone suggest us how to acheive this requirement?
    A quick response is much appreciated.
    Thanks in advance,
    Venkat

    hi
    i think specifying start of the cycle for each maintenance level is not possible ,since start of the cycle refers to maintenance plan only .
    for SAP standard kindly refer the following [link|http://help.sap.com/saphelp_46c/helpdata/en/94/43a968abc011d395bd00a0c93029cf/content.htm]
    it is better to create one maintenance item per maintenance plan,if you want to control each maintenance item independently
    regards
    thyagarajan

  • Human task escalation ERROR

    Hi,
    I have a BPEL process with a human task. This human task has set the expiration time and the escalation policy (2 escalation steps).
    The BPEL works alright if nobody does nothing to the task. It fails if the task is claimed by a user but after the user doesn't finish the task (doesn't take any actions on the task, neither approve/reject)
    The task is expired and the status is "with errors". In the logs the following error appears:
    <2008-06-25 16:08:40,093> <ERROR> <oracle.bpel.services.workflow> <::> ORA-20003: Error while inserting routing slip
    ORA-06512: en "ORABPEL.WFTASKPKG", línea 47
    ORA-00001: restricción única (ORABPEL.SYS_C005188) violada
    ORA-06512: en línea 1
    java.sql.SQLException: ORA-20003: Error while inserting routing slip
    ORA-06512: en "ORABPEL.WFTASKPKG", línea 47
    ORA-00001: restricción única (ORABPEL.SYS_C005188) violada
    ORA-06512: en línea 1
         at oracle.jdbc.driver.DatabaseError.throwSqlException(DatabaseError.java:138)
         at oracle.jdbc.driver.T4CTTIoer.processError(T4CTTIoer.java:316)
         at oracle.jdbc.driver.T4CTTIoer.processError(T4CTTIoer.java:282)
         at oracle.jdbc.driver.T4C8Oall.receive(T4C8Oall.java:639)
         at oracle.jdbc.driver.T4CCallableStatement.doOall8(T4CCallableStatement.java:184)
         at oracle.jdbc.driver.T4CCallableStatement.execute_for_rows(T4CCallableStatement.java:873)
         at oracle.jdbc.driver.OracleStatement.doExecuteWithTimeout(OracleStatement.java:1161)
         at oracle.jdbc.driver.OraclePreparedStatement.executeInternal(OraclePreparedStatement.java:3001)
         at oracle.jdbc.driver.OraclePreparedStatement.execute(OraclePreparedStatement.java:3093)
         at oracle.jdbc.driver.OracleCallableStatement.execute(OracleCallableStatement.java:4286)
         at oracle.oc4j.sql.proxy.PreparedStatementBCELProxy.execute(PreparedStatementBCELProxy.java:333)
         at oracle.bpel.services.workflow.repos.driver.oracle.OracleWFRoutingSlip.insertRoutingSlip(OracleWFRoutingSlip.java:123)
         at oracle.bpel.services.workflow.repos.driver.PersistencyService.insertRoutingSlip(PersistencyService.java:216)
         at oracle.bpel.services.workflow.task.impl.TaskService.performPostActionOperation(TaskService.java:3321)
         at oracle.bpel.services.workflow.task.impl.TaskService.localHandleRoutingSlipInterpretationResult(TaskService.java:1246)
         at oracle.bpel.services.workflow.task.impl.TaskService.handleRoutingSlipInterpretationResult(TaskService.java:1298)
         at oracle.bpel.services.workflow.task.impl.TaskService.expireTask(TaskService.java:2614)
         at oracle.bpel.services.workflow.task.impl.TaskService.expireTask(TaskService.java:2574)
         at oracle.bpel.services.workflow.task.ejb.tasktimer.TaskTimerBean.expireTask(TaskTimerBean.java:35)
         at sun.reflect.GeneratedMethodAccessor250.invoke(Unknown Source)
         at sun.reflect.DelegatingMethodAccessorImpl.invoke(DelegatingMethodAccessorImpl.java:25)
         at java.lang.reflect.Method.invoke(Method.java:585)
         at com.evermind.server.ejb.interceptor.joinpoint.EJBJoinPointImpl.invoke(EJBJoinPointImpl.java:35)
         at com.evermind.server.ejb.interceptor.InvocationContextImpl.proceed(InvocationContextImpl.java:119)
         at com.evermind.server.ejb.interceptor.system.DMSInterceptor.invoke(DMSInterceptor.java:52)
         at com.evermind.server.ejb.interceptor.InvocationContextImpl.proceed(InvocationContextImpl.java:119)
         at com.evermind.server.ejb.interceptor.system.JAASInterceptor$1.run(JAASInterceptor.java:31)
         at java.security.AccessController.doPrivileged(Native Method)
         at javax.security.auth.Subject.doAs(Subject.java:396)
         at com.evermind.server.ThreadState.runAs(ThreadState.java:648)
         at com.evermind.server.ejb.interceptor.system.JAASInterceptor.invoke(JAASInterceptor.java:34)
         at com.evermind.server.ejb.interceptor.InvocationContextImpl.proceed(InvocationContextImpl.java:119)
         at com.evermind.server.ejb.interceptor.system.TxRequiresNewInterceptor.invoke(TxRequiresNewInterceptor.java:52)
         at com.evermind.server.ejb.interceptor.InvocationContextImpl.proceed(InvocationContextImpl.java:119)
         at com.evermind.server.ejb.interceptor.system.DMSInterceptor.invoke(DMSInterceptor.java:52)
         at com.evermind.server.ejb.interceptor.InvocationContextImpl.proceed(InvocationContextImpl.java:119)
         at com.evermind.server.ejb.InvocationContextPool.invoke(InvocationContextPool.java:55)
         at com.evermind.server.ejb.StatelessSessionEJBObject.OC4J_invokeMethod(StatelessSessionEJBObject.java:87)
         at TaskTimerBean_RemoteProxy_68d4144.expireTask(Unknown Source)
         at oracle.bpel.services.workflow.task.impl.WorkflowTimerAgent$ExpirationJob.execute(WorkflowTimerAgent.java:676)
         at org.quartz.core.JobRunShell.run(JobRunShell.java:191)
         at org.quartz.simpl.SimpleThreadPool$WorkerThread.run(SimpleThreadPool.java:516)
    Has anyone found the same problem?
    Regards,
    Zaloa

    Hi Charles,
    First of all thank you for the reply.
    Right now I'm working in a development environment, where we don't have a cluster. In production environment we do have a cluster for the soa suite so it would be good to know the patch for the cluster.
    On the other hand, I upgraded from 10.1.3.1 to 10.1.3.3 but I didn't run the database script. After reading this post, I executed the upgrade_10131_10133_oracle.sql script but I'm getting the same error.
    One thing that I don't understand is that the log says:
    java.sql.SQLException: ORA-20003: Error while inserting routing slip
    ORA-06512: en "ORABPEL.WFTASKPKG", línea 47
    ORA-00001: restricción única (ORABPEL.SYS_C005188) violada
    ORA-06512: en línea 1
    I connect to the database using orabpel user and I don't find the WFTASKPKG table. Is this normal? What is going on?
    Also, the escalation works alright if no user claims the task.... so I guess it is not an LDAP configuration issue. (both users exist and have title and manager set up)
    Regards,
    Zaloa

  • Problems with task escalation in SOA11g

    Dear All,
    I need some help with task esclation in SOA11g,
    I am working on SOA 11.1.1.3.0 and weblogic 10.3,
    i have a requirement where in i want a task *(that expires after a certain period) to be escalated to the user's manager and at the same time make it available in the user list of task's.*
    i am able to escalate the task to the user's manager after it expires but it get's removed from the user's list of task.
    is their a way in which i can do both,i mean escalate the task to the manager as well as make it avaialble for the user rather than removing the task from his list.

    I considered even this option i.e to assign the task to the user and escalate it to the manager at the same time
    But the problem with this is approach is that the status of the task thats assigned to the user will be ASSIGNED or REASSSIGNED and not ESCALATED.
    Thks for the reply anyways!!!
    Regards
    Ajay.v

  • Human Task Soa Custom escalation

    Hi ,(Human Task SOA suite)
    We have a requirement where we have to determine how many times the task has been escalated.
    Can anybody please tell how to determine the counter for task escalation.
    Based on this escalation count we have to set the task expiration time.
    Please help

    OK, I've realised that the date format is the standard XML schema dateTime (http://www.w3.org/TR/xmlschema-2/#dateTime).
    After a bit of searching around, I discovered the XMLGregorianCalendar class (http://java.sun.com/j2se/1.5.0/docs/api/javax/xml/datatype/XMLGregorianCalendar.html) which could be used in a function like so:
    import java.util.Date;
    import java.util.GregorianCalendar;
    import javax.xml.datatype.DatatypeFactory;
    import javax.xml.datatype.DatatypeConfigurationException;
    import javax.xml.datatype.XMLGregorianCalendar;
    Date parseXsdDate(String xsdDateString) {
        if (xsdDateString == null || xsdDateString.trim().length() == 0) {
            return null;
        DatatypeFactory factory;
        try {
            factory = DatatypeFactory.newInstance();
        } catch (DatatypeConfigurationException e) {
            throw new IllegalStateException(e);
        XMLGregorianCalendar xmlCal = factory.newXMLGregorianCalendar(xsdDateString);
        GregorianCalendar cal = xmlCal.toGregorianCalendar();
        return cal.getTime();
    }Hopefully this is useful for someone. I had been parsing the date strings with a Pattern before, which was not ideal.

  • Using partition variable in task sequence

    I need to configure a piece of software as part of a task sequence to direct some of its files to a specific partition.  I have the ts creating 3 partitions and I'm specifying variables for each: DataDisk = 10GB, UsersDisk = 100GB, OSDisk = 100% remaining
    free space.
    The 100GB partition is the one I need the software to use. In the "Custom Tasks" section of the ts "Dump MDT Variables" step dumps all MDT variables to a text file on the local machine so I can see at that time UsersDisk = D:\, DataDisk
    = C:\ and OSDisk = V:\, but after the deployment finishes UsersDisk = E:\.  Also in the "Custom Tasks" section I'm running the "Configure Data Igloo" to configure the program.  Is there a way to set UsersDisk = E:\ before I run
    the "Configure Data Igloo" step when there's also an internal DVD drive likely using E:\?
    Edit: I should add that it's all working properly at the moment but the "Configure Data Igloo" step is referencing E:\, not %UsersDisk% and I see this causing problems latter.  Does anyone know how the drive letters are assigned?  That is,
    why does %DataDisk% = D:\ and %UsersDisk%= E:\ after deployment, why not the reverse?

    Thanks for the reply Keith.  I'm not thrilled about having to customize the partition structure either but because we use Deep Freeze we need use Data Igloo to cache user profiles on a partition other than C:\.
    What I've ended up doing is using the 'Set Task Sequence Variable' tasks to set DataDisk = D:\ and UsersDisk = E:\ and then I can reference these variables for the task that configures Data Igloo.  To be clear for anyone trying to follow this, I'm not
    actually changing the letter assigned to the partitions, I'm just assigning a value to a variable which is then referenced in later task sequence steps.
    The thing that I'm not sure about is how the partition letters are assigned.  In my case the DataDisk partition is always assigned D:\ and UsersDisk is always assigned E:\.  I thought it might be alphabetical but I changed the 'Format and Partition
    Disk' step to rename UsersDisk to ADisk and it still gets letter E:\. 
    This isn't a big deal but if anyone knows how the letters are assigned please let me know.

  • Strategy escalation not appearing in the escalation node of UWQ.

    Hi,
    Module: Advanced Collections
    Customer has done the following test case:
    There are three work items in the collection strategy. First two work items are automatic and completed successfully. Third work item is manual and need to be escalated to manager, if it is not closed within time limit.
    Escalation for third Work Item has been setup. On the expiry of the time limit, system sends a email notification to the manager of the collector but this escalation is not appearing in the escalation node of the collectors work queue.
    Checked the collections implementation guide and found the following:
    "In the Escalation section, enter Yes and a closure time if you want an "automatic"
    notification sent to the collector’s manager if the work item is not completed in the
    specified time period"
    It has not specified whether the escalation appears in the workqueue node of the manager.
    I would like to know whether the escalations should appear in the escalation work queue node or is this an intended functionality.
    Thanks and regards,
    Hareesh

    Hareesh,
    As I see the work items a resource after esclation will only in the escalated node but not in the queue of the manager.
    My requirement was to show the UQW items of the subordinates of a manager in the UWQ apart from his own. I am not sure the R11.10 and above with some patch levels has that functionality out of the box, but I had to change the metadata view defnition to show that info in the UWQ.
    Going back to your question, escalations use task architecture. As the task owner is still the resource who holds the task of completing it, the task is not "assigned" to the manager but just a mail is sent keeping in the different bucket.
    Hence that **May** not show in the manager queue. But if you change the metadata views, you can show all of my subordinates tasks to the manager as well which includes the escalations.
    You can try using the task escalations screen to reassign the owner to be manager thus taking the task out my list and showing it up in my manager's list.
    I have not tested this but you can try this option and use as a process step.
    Thanks
    Nagamohan

  • How to register Custom Escalation class or project as a part of soa installer?

    Hi,
    I have written a custom class for human task escalation which is part of project i created which contains all libraries and other files related to escalation.
    To test it i manually put in oracle.soa.ext jar inside soa module in weblogic server.
    However i want to register it using java class using some API.
    Please help.

    Take a look at the following blog article:
    http://jamesmacesp.wordpress.com/2009/12/14/provisioning-sharepoint-sites-with-feature-receivers-part-1/
    Add your custom page normally using a module entry in the feature.  But apply it as the default welcome page using the event receiver.
    Paul Stork SharePoint Server MVP
    Principal Architect: Blue Chip Consulting Group
    Blog: http://dontpapanic.com/blog
    Twitter: Follow @pstork
    Please remember to mark your question as "answered" if this solves your problem.

  • Task Assignment to Ggroup - Group Members Not Getting Email

    I have a process with an approval activity with initial user selection set to a group rather than a specific user. I want all selected users to receive an email notification that a new task awaits them. When I assign to a specific user, the custom email template is sent to the user. When I assign to a group, the group members don't get the task assignment email.
    How do I change that so that group members will receive email notification of task assignment?
    Thanks in advance!
    Eric

    One possible solution:
    You can use our Group Lookup component to get a comma-separated list of the emails of the members of the group. Then, in the step before the User>assignTask step, send the group an email. The only problem is that you won't be able to embed a link directly to the task, because the task doesn't exist yet.
    Doc: http://avoka.dnsalias.com/confluence/display/Public/Lookup+DSC
    Download: http://www.avoka.com/avoka/escomponents.shtml
    To work around this problem, you can use the technique outlined here:
    http://blogs.avoka.com/2008/10/20/customize-user-task-escalation-after-assignment/
    http://avoka.dnsalias.com/confluence/display/Public/Customize+User+Task+Escalation+After+A ssignment
    If you need more assistance, contact info-at-avoka.com
    Howard

  • SLA/TAT calculation of a task.

    Hi all,
    We can include Human interaction in a BPEL process by adding a "Human Task" activity. In "Task Escalation and Expiration" policy of the task, we can define the expiration time and to whom we want to escalate this task once the task is expired. But all time calculation is done internally based on the date/time of the machine the server is running. These calculations deos not exclude weekends and public holidays. For example - If task is created on 19th Mar and expiration period is 2 days then task will be expired on 21th Mar.
    Is there any way/feature comes out the box to define a customized calendar to exclude weekends, public holidays in these calculations?
    Thanks
    Alankar Gupta

    Hello
    Did this in my current project the answer is
    1. Define a custom xpath function -> Oracle doco http://download.oracle.com/docs/cd/E15523_01/integration.1111/e10224/bp_appx_functs.htm#BEIIAHJH
    2. Call it from the human task on the deadlines tab.
    Regards Tristan
    Edited by: user10879274 on 27-Jun-2010 22:35
    Edited by: user10879274 on 27-Jun-2010 22:36

  • Transfer Gantt Chart View color's automatically to Team Planner View

    Hi there.  My project has 7 different resources with various Resource Names ending characters.  I've automatically color coded the bars on my Gantt Chart based on resource allocation by using Flags 1-7, Custom Fields, and the formula IIf(Left([Resource
    Names],3)="xxx",Yes,No).  I then change the format of each bar style to the color I desire.  
    I am looking for a way to automatically transfer the colors I have assigned the tasks in my Gantt Chart to the Team Planner view.  I don't believe there is a simple way to do this but would appreciate any help aside from manually formatting each of
    the tasks in Team Planner view.
    Thanks for the help!
    -Joe

    jbarrazotto --
    Alas, there is no way to do what you want with the Team Planner view.  This is because there is no dialog similar to the Bar Styles dialog where you can control the formatting.  Basically, the Team Planner view has definitions for Manually Scheduled
    tasks, Auto Scheduled tasks, Actual Work on tasks, External Tasks, and Late Tasks.  Using the corresponding buttons in the Styles section of the Format ribbon with the Team Planner Tools applied, you can control the fill color and the border color for
    every bar of one of those types.  But there is no way to add other buttons to the ribbon to control the Gantt-like bars that are shown in the Team Planner view.  So, what you want to do with the Team Planner view is not possible.  Sorry. 
    Hope this helps.
    Dale A. Howard [MVP]