MRP Logic -Negative Available quantity in MD04

Hi Experts,
We have negative available quantity in MD04. There are no receipts generated particularly for some period even after MRP Run.
MRP Type is maintained as P1- MRP Fixing type.
Safety time is maintained as 3 days.
Planning strategy is 40.
Please suggest, what would be the reason, why i am not getting schedule lines between 09-Aug and 27-Aug which makes available quantity minus, after that there are generation of schedule lines.
Please help with inputs..

Hi,
MRP type P1 is used with planning time fence(mandatory).
Have you used pl time fence. How many days? For those period system will not generate any more planned order.
Regards,
Dharma

Similar Messages

  • Negative Available quantity in MD04

    Hi Experts,
    We have negative available quantity in MD04. There are no receipts generated particularly for some period even after MRP Run.
    Please suggest.

    Hi,
    Check the MRP type in material master. If this is ND, then system will not make any procurement proposal. Also check the strategies such Make to stock / make to order. If the requirement strategy & the strategy in the material master differs, then also there will not be any procurement proposal.
    Regards,
    Prashant

  • Available quantity in MD04 not cumulating

    Can somebody tell me where is available quantity cumulated in MD04 for each new item controlled?
    for my client- few materials available quantity is gettig cumulated, but for others it si not getting
    so user is fed up as he has to manually add the available qty after each item
    Pls help

    Hi,
    The the quantity can be cumulated daywise, monthwise, like this u can control this setting in setting -->  Perios total tab. if u are used two diffrebt strategy while putting plan then the quantity can not cummulated.
    Regards,
    Shekhar Damle

  • MD04 - Available quantity

    Hi....
       I m creating a Report to display the available quantity for a
    particular material on a particular date....same way it is displayed
    in the standard tcode MD04.
    Also I need to display the projected usage quantity for next three
    months where user will input the date. I need to find this projected
    usage quantity again like MD04 transaction code. This tcode uses
    structures MDEZ and MDSU to display the available quantity and other
    data.
    Are there any function modules availble to get it or are there any
    tables from where i can get this required data?
    Thanks in advance,
    Prasad

    Maybe you could use the function module MD_STOCK_REQUIREMENTS_LIST_API?

  • How to get available quantity in Inventory levels  for all materials

    Hi..All
    I am Abap Developer and i have a Requirement that to Print a report that Displays " Inventory levels (available quantity) for all materials"
    1) What tables can i use to retrive the data to get the Inventory levels (available quantity) for all materials.
    2).What are the fields can used in that tables that use ful for end user.
    Thank you,
    Madhu .
    Edited by: madhubabu rao on Oct 15, 2008 9:10 AM

    Hi,
    I'm not sure what you mean when you are speaking about inventory levels and available quantity.
    I mean that you may have stock of 100 pcs of a certain material but from an open PrdOrd can come a reservation for this component (e.g. 20 pcs) that reduces this the available quantity (to 80 pcs).
    If you want only the stock levels, you don't have to write any ABAP code, since MB52 report is designed for this purpose.
    If you want to know the available stock (considering requirements (PIR, DepReq, SO), and stock-like MRP elements (PldOrd, PurReq, PrdOrd, PO, etc)) you should check report MD04 and examine how it works, which tables it uses (ST01).
    http://iorboaz.blogspot.com/2005/04/get-md04-data.html
    Regards,
    Csaba
    Edited by: Csaba Szommer on Oct 15, 2008 9:34 AM
    Edited by: Csaba Szommer on Oct 15, 2008 9:34 AM

  • MRP Net Required/Available  Qty

    Hello Gurus ,
    I am carrying out MRP at plant level .After that MD04 We are analysing the result .We are developing Z report where we need to show Net Required Quanity(-) or Avaialable Quanity .We are using MDKP/MDTB table .
    1.Material Requirement Planning No xxxxxxx is not getting updated in MDTB table .I am getting MRP Table no from MDKP using Plant /Material Combination .
    2.What is the SAP Table -Filed name   to retrive Net Required/Available Quatity  (Planned quantity on the time axis that results from comparing receipts, issues, and current warehouse stock)
    Thanks and regards
    JH

    Hi,
    You can try with below function module, goto SE37 and test it
    MD_STOCK_REQUIREMENTS_LIST_API
    Regards,
    Sankaran

  • Is there a possibility should not consider available quantity at time of MR

    Sir,
    Is there a possibility should not consider available quantity at time of MRP planning?
    Example:
    Available stock: 100
    Planning stock: 100 (MD61)
    Schedule line to be generate: 100 Qty (Exclude the available quantity at time of MRP planning)
    regards,
    sampath

    Dear Sampath/Raj,
    1) Move the stock to particular storage location for which you don't want to be consider by MRP
    2) Now go to OMIR t-code, input value as 1 for that particular storage location
    3) Go to MMSC, input value as 1 for that particular storage location
    4) Go to MRP - 4 view Down you can find field Storage location input value as 1
    5) Now run MRP, system will not consider stock of that particular storage location
    Regards
    Madhu

  • Available quantity

    Hi,
    The calculation for Available Quantity is sometimes confusing for certain companies. In SAP, Available=InStock-Committed+Ordered. Several companies consider Available as InStock-Committed.
    It would be great if this calculation could be user-definable (per company). For example, you could have this under Document Settings, with the options:
    Available=InStock-Committed+Ordered
    Or
    Available=InStock-Committed
    Thanks,
    Jose

    Hi Jose......
    I think you are not aware about MRP Functionality not only in SAP but in Basics also....
    Please go through these links......
    http://it.toolbox.com/blogs/sap-library/mrp-in-sap-business-one-a-business-scenario-10625
    http://wiki.sdn.sap.com/wiki/display/B1/SAPBusinessOne...ToGo-7.TheABCsof+MRP
    http://en.wikipedia.org/wiki/Material_requirements_planning
    Hope this will clear your doubt why this relation is important from planning point of view........
    Regards,
    Rahul

  • Change available quantity for Sales Order line during ATP control

    Hello,
    When sales order is created and item line is entered I need change available quantity for material. I mean not ATP quantity but available quantity (MCHB-CLABS for material/plant - I need remove some batches from logic)
    Could you tell me when I could add my enhancement for above purpose?
    Thanks in advance,
    E

    Did you try the assignment (Enhancement) ATP00001?

  • MB1A Problem - Available Quantity show 9,999,999,999

    Hello, Guru
    My company work on SAP ECC6.0, I'm about to do good issue but I struck on some problem.
    I have one material which is control in batch management and now I want to issue this material thru T-code MB1A, Mvt = 261, but while I trying to choose batch to issue, the system is giving the available quantity 9,999,999,999.
    Is it possible to get the actual batch quantity in storage Location, How can I config to fix this problem ?
    Thnx
    Karn
    Edited by: rravikran on Aug 20, 2009 5:19 PM
    Edited by: rravikran on Aug 20, 2009 5:50 PM

    I have already config batch detemination. This material don't have MRP View 1-4 but I choose availibility check 01 in sales/plant view.
    I check config at t-code OMCP and click transaction button to view good withdrawal (MB1A). The checking rules is 03 and  I click define checking rule button to view availibility check control overview, double click availibility 01 and checking rule 03.
    It sets as follows;
    Incl Purchase Order
    Include Reservation
    Include Sales Requirement
    Include Delivery
    Edited by: rravikran on Aug 21, 2009 6:51 AM

  • PS Budget Report S_ALR_87013558 shows negative available amount

    Hi ,
    We activated Availability control in our Project System. We created a project, WBS elements, network activities. Then setup the budget (WBS level) then release the budget. Purchase requisitions were made to PO items, some were receipted and some are still in Commitment. We also added the cost for Travel and Accomodation but haven't posted any actual cost for these network activities. Then when I generated S_ALR_87013558 the budget available amount shows a negative balance.
    I already run CJEN to reconstruct the table, CJBN to recontruct the availability control balance but it still generating the same negative available balance.
    We setup our tolerance limit to raise an error once the budget reached 100% but in this case it should already been triggered before reaching zero but it didn't happen.
    Any solution for the problem is greatly appreciated.
    From this going forward any cost that need to be added to the project triggers the error message BUDGET EXCEEDED! it supposed to been triggered before the negative available amount on the report was reached.
    The report show that I have an amount presented on the following columns:
    ACTUAL
    COMMITMENT
    REMORDPLAN
    ASSIGNED
    I already checked the individual network activities to checked if the balance showed in the RemOrdPlan is correct using the formula REMORDPLN = MAX(0, PLAN - (Actual+Commitment)) and it is consistent with the amount presented in the report.
    thanks
    sunil

    Hi,
    Some ideas :
    1st. Try to check the history when the AVAC activated. It could be AVAC activated after PR/PO created.
    2nd. Try run cj31. Compare the value there with the report S_alr_**** . If the value is not match , you should apply some notes. It could be your AVAC not working properly.
    3rd. In order to prevent any futher issue for another project. Try to CJBW, CJEN and CJBN, for all projects (one time only). Put some budget on it. Next step do background schedule (CJEN after that CJBN) let say for weekly for all projects.
    Hope can give you some ideas.
    Cheers,
    Nies

  • Inventory Error :Transaction quantity must be =  available quantity.

    An error occurred while relieving reservations.|Transaction quantity must be less than or equal to available quantity.
    while doing material transactions in transaction open interface iam getting above error......Kindly help me as i am struck here and it is high priority issue and need to be resolved as soon as possible..

    refer -
    Pending Move Transactions FAQ [ID 1141334.1]
    WIP_MOVE_TXN_INTERFACE Common Errors In Pending Move Transactions With Possible Causes And Action Plan To Process Them [ID 457066.1]
    Outside Processing Wip Move Transaction Fails With Overcompletion Quantity [ID 427558.1]
    Pending Move Transaction Error - Allow Moves Not Enabled [ID 780732.1]
    R12 OSP Job (Also Repetitive Schedule) Do Not Support Overcompletion: Error 'Transaction quantity must be less than or equal...' [ID 563011.1]
    cheers,
    VB

  • WM create TO: Available quantity in bin is zero

    Dear Gurus,
    I've got this error "Available quantity in bin is zero". Below is the step that I've done:
    1. MIGO to issue 5PC in batch 1 to cost center.
    2. In WM, stock now is in interim stype 911, qty -5 PC.
    3. Then I created TO to transfer from the real bin (BIN1) to interim area 911 --> System has error "Available quantity in bin is zero".
    4. I have double checked stock in WM (LX02, LS26,...), there is enough available stock in the BIN1, batch 1. Also there is no pending TR, TO.
    Please help to find the reason of this error and how I can clear this interim area.
    Thanks,
    Trang

    Hi Nick,
    After I did step 1, material document created and also TR created. I see this TR works normal like other TRs.
    But when I did step 3, create TO from material doc (LT06) or from the TR (LT04) with source bin is the real bin (such as Bin1) and destination bin is the auto interim bin named cost center (such as stype 911, Bin ADMIN), the system says that Bin1 has Available zero stock.
    What I've checked is:
    - I checked stock in IM (MB5B), stock is there. Stock in WM (LX02) also there in bin1.
    - I tried to do transfer order for other batches of the same material in the same bin1, everything goes ok. The error only happens with this specific batch 1! When I check batch master for batch1, I couldn't find any thing strange there.
    I still stuck with this error up to now. Please help!
    Trang

  • Negative ordered quantity

    I don't know why I got negative ordered quantity and negative committed quantity in my Item Master
    Could anyone know how to fix the problem ? Is it affect the operation and may I know any other cause will be affected?
    Regards,
    Alex

    Dear Alex,
    For this kind of issue please send a customer message to the Support Center, the consultant will help you out.
    Usually this kind of issue will need DB fixing to correct the data.
    For more information you could also refer to note:999124
    Incorrect committed\On order quantity when changing orders
    note:1137673  Incorrect ordered quantity after receipt from production
    Best Regards
    Helen Sun
    SAP Business One Forums Team

  • Internal Orders (Negative Available )

    Hello,
    Anybody knows how is posible that the available of an internal order is negative? What´s more we have activate Availability Control.
    Is it a system error?
    Thank you very much in advance.
    Patricia Guevara.

    Hello,
    Thank you very much ibn advance. I do´not require anything. We are in PSA and because of the year change we have observed that in 2008 my client has negative available in the internal orders (because of the goods receipts in 2008) and we do not know how because the budget is zero.
    Because of that it´s available is negative, and we do not know how this have ocurred if the Availability Control is activate.
    The normal situation is that when my client wants to receipt a purchase order the system issues an error because there is not budget in 2008 (It is yet zero).
    Do you understand me?
    Is it a system error? I think so.
    Thank you very much in advance.

Maybe you are looking for

  • Submit report in background

    Hai friends, Requirement is " I need to submit the report in background and program should execute only on every monday of the week. Pl do the needful and clarify with hard coding. Good answers expect good points. Regards, Vamsykrishna.

  • How to have two times the same iTunes library ?

    My parents are separated, so I have two computers (one with my father and the other one with my mother) and all my music is in the computer with my mother, I want to have the same iTunes library to my father how I should do?

  • Can't find license number on product?

    I can't find my license number on my boxed elements 13 product I purchased on Amazon.  There's numbers but none that fit in the license number boxes....I've checked the box, the sleeve, and there was no insert.

  • Multiple AM in CPX file - anyone got this to work ?

    Hi, It seems impossible to use multiple application modules from the same CPX file. For convenience reasons, I have many AM definitions in my CPX - (which the CPX wizard allows perfectly). I can create a first app module and it works perfectly. But w

  • PLEASE HELP syncing iphone...

    Hi so my problem here is really difficult to resolve. I got a brand new iPhone 5, and my computers usb ports are BOTH broken so i was hoping to sync my music within wifi sync, cuz i heard that works really well, but then i heard i need to plug it in