During the MIRO process xxxx  has selected receipt lines that have already been vouched and processed another invoice against them.  We now have negative IR''s which the system booked against our GR account twice. This is creating an incorrect balance in the account.  We need to know the SAP process to correct these. 
Regards,
APT

Normally you can do this directly in the G/L line item display FBL3N for the GR/IR account and sort the items on assignment (ZUORN) which you can set in the G/L account master data (sort key) to the purchase order or purchase order+line item.
To make things easier you can plan in a daily job which clears all items on the GR/IR account for which ZUORN and amount are equal. The report you want is then the same as all open items on the GR/IR account.
Regards,
Johan

Similar Messages

  • Total hours booked against a maintenance plan

    Hi,
    How can I check how many hours have been booked against each maintenance plan.
    Many thanks.

    Hi
    Many thanks for the answer it was very useful.
    I went into IW38 and entered the maintenance plan no. and found all the maintenance orders against it.
    Then i went into IW49 and put all the maintenance orders in it and it gave out the actual work booked against each order.

  • I submit a negative number and it subracts twice the value

    I submit a negative number and it subracts twice the value on Numbers 08 running Lion

    "But as soon as I paste the two columns(column of names), (column of information) from the original bad sheet into it seems these pastings corrupt my numeric column in some way.  So it seems anything pasted from the original working sheet onto a good new sheet causes the new sheet to have the same problem."
    You might be able to strip that corruption with one of these techniques:
    Export the original document as a CSV file. Open this in Numbers, then transfer the names and information columns (individuallly) using Copy/Paste
    Export the original document as an MS Excel file, Open that file in Numbers.
    Copy the names column from the original document to the Clipboard.
    Select the first cell in the Names column of the new table.
    Use an Applescript to convert the contents of the clipboard to Text and paste it into the new document.*
       repeat with Information column
    Regards,
    Barry
    * I've contacted Yvan regarding a minor edit to a script he wrote some time ago to do this in Pages.

  • Time entries booked against network & activity are not transferring to PS

    Hi every one,
    We have scheduled a job to transfer time entries which were booked against network & activity on daily basis,  but for some reason the time entries are not getting posted against the network (Only for certain network, see attachment), though it is not showing any error message when i saw the spool log for the job in SM37. When i ran CAT5 in test mode it is showing time entries which needs to be booked against the network and activity.
    Can some one help me out to transfer the time entries via the job??
    I have attached the screenshot from CAT5 transaction.

    Hi Ram,
    Variant will determine the selection of personnel numbers and other parameter defined on CAT5 selection screen. If manually posting is happening on network then it means network are fine.
    What I can suggest is, you can create a new variant and then run it thought SM36 and check in SM37.
    Go in CAT5 transaction, and untick test run, log and dates transfer can be ticked. Then save. Then variant attributes screen will open save the variant with a name and description .lets assume you saved the variant with name TEST. If you wish you can on save the variant on certain number of network or personnel number, it depends on you to keep it blank or run variant for limited number of records.
    Now go in SM36 and click on STEP, in the ABAP program TAB enter "RCATSTPS", then select the variant using search help and you will find the variant defined above i.e. TEST.Check and save from bottom of the window. Come back once. Then click on START CONDITION, Date/Time - define a date and time for the variant "TEST" to run as a JOB.
    Check in SM37 you will find the schedule JOB run time and date. After the JOB is finished you check report CJI3 for actual posting of network.
    This will work fine, if in case you need few more fields to be defined in variant then I will suggest to create a variant via CATA instead of CAT5, their you will get more options to post time.
    Regards,
    Sandeep

  • Report to show hours booked against a project

    Hi all,
    Does anyone know if there is there a report that will show the number of hours booked for labour against a project and that also shows a breakdown of the labour costs?
    Many thanks.

    CJI3 - Line Item report can show you those values provided you include the fields Quantity, Personnel Number etc., in the layout.
    Regards
    Sreenivas

  • No cost booking against sales order+line item once accontng release is done

    Dear all,
    I want to stop all cost bookings against a sales order + line item once the accounting release for that item has been done.
    By cost booking i mean, all such transactions that are done for a sales order + line item that involve cost booking. Like, MB1A should not allow any goods issue against that sales order + item once accounting release is done.
    Is it possible to that in sales order? Like by using any status at item level.
    Please guide.
    regards
    SAPshed

    Hi Ajay,
    We have not kept automatic cost estimate marking during saving of sales order as costing dept wants  to confirm whether costing for the SO is correct or not.
    Hence we have to use CK51N.
    Now the problem is for any change in any line item of a sales order is changing the costing status from "VO" to "KA" for all line items of the given sales order in table KEKO.
    This is causing measure problem as production people are facing problem while making any change in production order as already there is a check put in CO02 that if cost estimate does not exist for underlying sales order, then change in production order should not be allowed.
    Similarly production order creation (converting planned order to production order) is getting held up.
    Costing user has to repeated run CK51N for all line items of a single sales order if there is any change in any single line item of the sales order.
    Hence pl. help and suggest as to what is to be done now.
    Regards
    Ratna

  • Double Booking against same freight condition In import PO.

    Dear All,
    I have a issue for import PO.Two freight forwarder have wrongly raised bills against the same consignment and the FI user book the both bill in MIRO.System allows the same and didn't give any error or warning message.My question is how i control the double booking of same amount ?
      In SPRO-MM-LIV - Incoming  InvoiceSet check for Duplicate invoice Indicator is set only for "Check Reference" and not for check company code and Invoice date. And our client user didn't maintain vendor in PO condition.But in MIRO they selects the condition and in Details tab>Invoicing .Party-- maintains the vendor and posts the MIRO.
    Please Guide me ...
    Regards
    Sachin

    Hello Jeyakanthan,
    I have set company code and invoice date.It helps a lot. Now system gives me message "Check if invoice already entered under accounting doc. no. 5100000069 2011 and  Message no. M8108".But when i open this 510000069 2011 in MIR5 i didn't find any similarity in this and the one which i am posting.Is there any other way out? But i notice if i m posting the duplicate entry (i.e. 2nd MIRO) against the same qty,in MIRO under "Settled qty" i can see the qty which was posted earlier MIRO.Can we use this for reference and can arranged the settled qty column near qty column in MIRO. In PO/MIGO there is facility to set the sequence of column but not in MIRO..
    Thanking you in advance.as usual your reply always helps a lot.
    Regards
    Sachin Thakur

  • Time booking against Sales Order

    Dear All
    I would like to know whether can i book time against sales order in CAT2 transaction. That is Rec. Sales Order or Rec. Sales order item.
    I need to transfer the price into controlling
    I have tried with the above but system throws an error of cost element
    Please advise
    Regards
    Deepu Pillai

    Hi Deepu,
    I have also same requirement. Can you share solution if you resolved above issue on CAT2 booking on SalesOrder.
    Hi All - If anyone worked on such scenario please guide me.

  • Synchronizing Address Book against a home server

    I have a Bubba Two home server setup with Debian Etch, and a Mac Mini.
    I want to synchronize Address Book’s contacts against this home server. What is the protocol or method of doing this? I want to synchronize the Address Book on two Macs through this server (and thus have three copies/backups too).
    PS: Don’t mention MobileMe. I know what the service does, but I want to use my own hardware.

    I have no idea what a Bubba Two or a Debian Etch are, but I created a unix bash script that uses the rsync -vvSauWEe ssh --delete --progress --stats command, and also made a launchd plist file to control when the script fires (you could use cron to automate the launch time, too -- it's deprecated but it still works).
    I am running this across the internet at large to sync Address Book and iCal between distant machines. If you plan to operate similarly, then note the -e ssh switch. You will need to set up ssh on all affected machines to use passwordless public/private key authentication. If you search the Unix forum here using the search term ssh-keygen I suspect you will find plenty of info on how to do that, if you don't know about that already. And, of course, if you are running across the internet at large, don't forget about port forwarding in your router.
    man launchd.plist and man rsync are some of the better man pages that I have seen. The rsync man page gives pretty good down-to-earth examples of how to use it, in my opinion.

  • My Address Book contacts disappeared twice. Where do they go?

    My Address Book contacts have disappeared twice; moreover, I can't seem to find them on Time Machine so that I can restore them. Is anyone else having this problem, and 1. how do I get my contacts back, and 2. how do I prevent this happening again?

    Hi, open these Folders...
    /Users/YourUserName/Library/Application Support/AddressBook/
    /Users/YourUserName/Library/Caches/com.apple.AddressBook/
    List what all is in them please & sizes.
    Could be many things, we should start with this...
    "Try Disk Utility
    1. Insert the Mac OS X Install disc, then restart the computer while holding the C key.
    2. When your computer finishes starting up from the disc, choose Disk Utility from the Installer menu at top of the screen. (In Mac OS X 10.4 or later, you must select your language first.)
    *Important: Do not click Continue in the first screen of the Installer. If you do, you must restart from the disc again to access Disk Utility.*
    3. Click the First Aid tab.
    4. Select your Mac OS X volume.
    5. Click Repair Disk, (not Repair Permissions). Disk Utility checks and repairs the disk."
    http://docs.info.apple.com/article.html?artnum=106214
    Then try a Safe Boot, (holding Shift key down at bootup), run Disk Utility in Applications>Utilities, then highlight your drive, click on Repair Permissions, reboot when it completes.
    (Safe boot may stay on the gray radian for a long time, let it go, it's trying to repair the Hard Drive.)
    If perchance you can't find your install Disc, at least try it from the Safe Boot part onward.

  • Can Credit Memo be booked against an Invoice?

    While raising a Credit Memo is it possible to refer or link the Credit memo being raised to the Invoice?

    >
    Mehul Ghanshyam Shah wrote:
    > Thanks for your reply Indranil...! Even my understanding is that CM cannot be linked to Invoice. But I wanted to be ensure the same.
    > Yes I am aware of MR8M.
    > But I need to know if there is any way an CM being raised (Using MIRO or any other available transaction), is it possible to link it to the Invoice already entered.
    I think you can check the same through table BSEG where against the credit memo (BELNR) you can find the invoice number (REBZG)
    Thanks & Regards,
    Indranil

  • I purchased and downloaded an ebook successfully but several months later can not open as book is corrupt. How do i redownload this book without paying twice?

    i have an ebook that has become corrupt, how do I get to access it without buying it again? Sourlime

    I would suggest contacting the company that you purchased the book from. If you have proof of purchase they should be able to help you get a new copy of the book.

  • Negative net book value of asset

    Hi Colleague,
    I have following situation on two my assets, but the reason is the same.
    In previous closed fiscal year 2013 in depreciation area 30 there has been posted depreciation in value of 353,17.
    Due to the wrong transaction type by creating of asset there has been performed correction.
    Is it possible to correct that this this value of depreciation from previous fiscal year will be reversed ?
    I attach screens who can allow to imagine this issue.
    Thanks a lot for any art of suggestions of correction !

    hi,
    if I need to use transaction abaa, which transaction type i need to use.
    When I performed this transaction i can see following information, that unplanned depreciation is negative in depreciation area.
    Please see attached screen
    Thanks

  • Time booking against prod order

    How can I book the operator time in a prod order.
    Is it needed that I should manitain the operator ID i

    Hi,
    You will have to configure the resource such that you have the standard value key to capture the operator hours. So when you do the confirmation of the operation, you can maintain the operation or labor time. You can define custom fields for operation where-in you can have provision to mention the operator ID if required during confirmation.
    You can then run various SAP standard reports (COOIS) to fetch this information. Try it and revert back.
    Regards,
    Swapnil

  • I just accidentally made a double purchase on an audiobook. I downloaded the first one and have the second repeat download on hold. How do I keep from being charged for this extra book I don't need?

    I accidentally made a double purchase on an audiobook. I am not sure what I did wrong but now I have one of the books downloaded and an identical purchase on hold to download...I don't want to pay for this book twice! How do I stop the download or how do I get this adjusted? When I looked in my purchases the book is there twice.

    Please pardon the intrusion…
    Hi,  Diavonex!
    Congratulations on advancing to Level 6!
    At the Water Cooler in the Level 6+ Lounge, we are throwing virtual confetti in celebration of your attainment of Level 6-dom. Would you care to join us at the Water Cooler?
    Towards the bottom of the index on the Apple Support Communities Home Page you soon will find the Lounge link available to you. It should work for you within the next 24 hours if all goes as it should.
    Hope to see you there soon!

Maybe you are looking for