Order change management

Hi all,
We have already implemented ECC 6.0 in a manufacturing project based industry. Now customer wants to track production order related changes. So we want to implement OCM.
Can anyboby please tell the detaild steps for implementing the OCM.
As per my knowledge i have already done necessary configurations. But when creating change master through CC01, in theentry screen, Function tab is not appearing. Can anybody tell the reason behind this.
Srijit.

Dear Srijit
Order Change Management is applicable for MTO/MTS Scenario,
First:-
In WorkScheduling View of Material Master (FERT/HALB or Any Defined for Production) you need to maintain "Overall Profile"
This Overall profile should be configured in SPRO > PRoduction>Shop Floor Control > Operations>Change Management for Production Orders-->Define Overall Change Profile.
Process of OCM follows this way:
Create a Change Number CC01 with Release Key
In Object Types select/tick "Actv", "object", "MgtRec",
You get the Change Number by Saving .
Use this Change Number to Change BOM or Routings
Then Release the Change Number useing Release Key till then you don't find the Change of BOM in Production Order.
Then go to Oder Change Process T Code :- COCM
Tick Change Number and Select the Change Number & Execute
Select the Production Order, click on “Procurement element” icon you get another screen select and execute again.
You get an Pop-Up screen. "Determine changes”, “Check changes”, “Change Original Order”.
you see the changes in BOM for Production Order i.e. after COCM.
Then Confirm the Changes in Production Order then New changes will be Active in production Order.
Refer : http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PPSFC/PPSFC.pdf
Look at  SAP note 436928, which descriped the restrictions from OCM if you are in ECC 6.0
Regards
JH

Similar Messages

  • Help required in OCM-Order change management

    Hi All,
    I have to implement the Order change managment. I did few setting which are required and than i created ECR using release key. but using OCM it tells me to first make the changes in MATERIAL BOM than using transaction COCM i can make the changes in required production order.
    But my requirement is i want to change the Production BOM or Production routing directly without touching Material BOM .
    As sometime it happens only 1 or 2 Order BOM s are need to be changed only not the Material bom. So i want to track the Changes made in Order using OCM.
    What is the solution that i can change the Production Bom OR Production Routing directly using OCM and also how can i make the changes in Sales Order.
    Pls do the needful.
    Thanks
    Ravi Khurana

    Using Order Change Management (change management for production orders), it is possible to include existing procurement elements (production orders, planned orders, purchase orders) that are also affected by a change, in the change process.
    The change process in OCM is based on Initiating Objects. These initiating object records refer to changes in sales orders or in master data, which, in turn, necessitate changes to production orders.
    Thus, it is not possible to change the order directly using OCM.

  • Production Order Change Management

    Hi ALL,
    Dealy need of following.
    How the changes to the production order can be viewed?
    Is there any tcode to check this ?
    Regards,
    MHP

    Dear Manish,
    In a standard system it is not possible to track the changes made to a production order.
    However, this can acheived in following ways.
    1.We can develop a custom made report to track changes made to an order.Please check this with your ABAPer.
    The overview of a report will be such that one can analyse the items added,deleted,new items inserted etc.
    2.We will be able to achieve this by order change management.Refer the following link.
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/41/3699761bc211d2b62b0000e8359890/frameset.htm
    Regards,
    Joseph Charles Vaikathussery

  • Order Change Management and direct manufacturing technique (SOBSL 52)

    Dear all,
    there is a statement in our SAP development team, that I can hardly believe:
    Order Change Management and direct manufacturing technique are not  fully supported in SAP standard (ECC6.0).
    Can any body help me with this issue?
    Kind Regards
    Bernd

    Dear Bernd,
    please see SAP note 436928, which descriped the restrictions from OCM.
    Regards,
    Sabine

  • Order Change Management(OCM) in SAP

    Dear All,
    OCM is applicable in MTO Scenario.
    Kindly let me know the steps involved to activate OCM n how to proceed
    further.

    Hi Bagchi,
    Order Change Management is applicable for MTO/MTS Scenario,
    <u>First:-</u>
    In WorkScheduling View of Material Master (FERT/HALB or Any Defined for Production) you need to maintain "<b>Overall Profile"</b>
    <i>This Overall profile should be configured in SPRO > PRoduction>Shop Floor Control > Operations>Change Management for Production Orders--><b>Define Overall Change Profile</b>.</i>
    <u>Process of OCM follows this way:</u>
    Create a Change Number <b>CC01 with Release</b> Key
    In Object Types select/tick "Actv", "object", "MgtRec",
    You get the Change Number by Saving .
    Use this Change Number to Change BOM or Routings
    <i><b>Then Release the Change Number useing Release Key till then you don't find the Change of BOM in Production Order.</b></i>
    Then go to Oder Change Process<u><b> T Code :- COCM</b></u>
    Tick Change Number and Select the Change Number & Execute
    Select the Production Order, click on “Procurement element” icon you get another screen select and execute again.
    You get an Pop-Up screen. "Determine changes”, “Check changes”, “Change Original Order”.
    you see the changes in BOM for Production Order i.e. after COCM.
    Then Confirm the Changes in Production Order then New changes will be Active in production Order.
    Regards
    Rehman
    <b>Reward Your Points If Useful</b>

  • WHAT IS ORDER CHANGE MANAGEMENT(OCM)

    HI GURUS,
    CAN ANYBODY EXPLAIN ME WHAT IS OCM , HOW TO USE IT.
    I UNDERSTAND THAT WITH OCM ANY CHANGES IN PROD ORDER GETS AUTOMATICALLY UPDATED IN MASTER BOM.
    IF ANY SCREEN SHOTS ARE THERE IT WILL BE MORE EASY TO UNDERSTAND
    HELPFUL ANSWER WILL BE GIVEN FULL MARKS.
    THANKS AND REGARDS,

    Hi,
    Order Change Management ( OCM) is used for tracking changes made to the Production / Process Orders.You can see the Change Management records after activating OCM in Order Header Screen--->
    Go to (Menu)--->Change Management.
    For detailed procedure for OCM pls go through the following link :
    [Order Change Management (OCM)|http://help.sap.com/saphelp_erp60_sp/helpdata/EN/41/3699761bc211d2b62b0000e8359890/content.htm]
    Hope this helps.
    Regards,
    Tejas

  • Order Change Managment

    I have a peculiar type of issue. The production order has the status CGFB- Confirm./goods mvmnt forbidden Which has been activated for the production order through <b>Order change Management</b>. But once this is being activated i am not able to do the delivery and order is blocked. So how should i deactivate this status in the production order. I have checked for the Material in the Work Scheduling view but no Overall profile is being usef for the Material. So i can i deactivate the Status CGFB in the production order set by the Order Change Managment.

    REPORT ZPPSFC179  has been runned  for the production order and the problem is not being solved
    Message was edited by:
            kumar jagadish
    Message was edited by:
            kumar jagadish

  • Difference  Between Order Change Management & Engineering change Management

    Dear,
    What is the Difference  Between Order Change Management & Engineering change Management ?

    Hi,
    ECM will help for Master data changes management.
    OCM will help to manage changes in Transaction Data like Production Orders.
    In brief,you have to first Create Change Number(part of ECM activity).then using that Change number, Master data(like BOM, Routing etc) has to be modified.
    Then through OCM affected Transaction Data(like Production Orders) for each change number to be Processed.
    Regards
    R.Brahmankar

  • Order change management in Sales order(MTO Scenario)

    Dear All,
    Iam trying to map OCm functionality.How is 'Initial object' created based on changes to the direct assignment of change numbers by using direct assignment.What exactly is this?I have a sales order of 10 pc. against which a prod. order is also created for 10 pc. If there is a change in qty. of sales order from 10 pc. to 15 pc.Is it possible to refelect the same in existing Prod.Order using OCM or any other functionality.

    Hi
    order cahage management is tio track the changes made in production order .
    It is no way to update the production order with changes made in sales order.
    Regards
    YMREDDY

  • Order Change Management activation

    Hi Experts,
    I want to activate the OCM (not in production server) to do some research. Can we deactivate it after making research.
    Requirement is "to trace the list of production orders that have undergone quantity or dates change".
    I would like to know whether it is difficult to deactivate like batch management.
    Regards,
    Jejesh

    Dear,
    It is not difficult to deactivate .
    Steps,
    In WorkScheduling View of Material Master (FERT/HALB or Any Defined for Production) you need to maintain "Overall Profile"
    This Overall profile should be configured in SPRO > PRoduction>Shop Floor Control > Operations>Change Management for Production Orders-->Define Overall Change Profile.
    Process of OCM follows this way:
    Create a Change Number CC01 with Release Key
    In Object Types select/tick "Actv", "object", "MgtRec",
    You get the Change Number by Saving .
    Use this Change Number to Change BOM or Routings
    Then Release the Change Number useing Release Key till then you don't find the Change of BOM in Production Order.
    Then go to Oder Change Process T Code :- COCM
    Tick Change Number and Select the Change Number & Execute
    Select the Production Order, click on Procurement element icon you get another screen select and execute again.
    You get an Pop-Up screen. "Determine changes, Check changes, Change Original Order.
    you see the changes in BOM for Production Order i.e. after COCM.
    Then Confirm the Changes in Production Order then New changes will be Active in production Order.
    Use COCM1 to find out the details or CO03--Extra --change
    Please check link from page 399.
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PPSFC/PPSFC.pdf
    Hope it will help you.
    Regards,
    R.Brahmankar
    Edited by: R Brahmankar on Nov 25, 2008 6:30 PM

  • ,COCM error - Order change management

    Hi,
    We changed the Bill of material, with change number. For that I have 7 production orders
    But in COCM transaction I am able to see only 6 orders. Why I am not able to see one production order.
    Thanks.
    Suresh.

    Hi Experts,
    Any updates on this?
    Thanks.
    Suresh.

  • Production Order Changes...

    I need the ability to identify changes made to a production order and the user that made the change.  There are instances of incorrect changes being made to production orders with no way to identify the user that made the change.  As examples, components are being 'final issued' but no one knows who set the 'final issue' indicator.  Labor hours are changed with no traceability to the user who made the change.
    SAP contains the capability to track changes to material master data, BOM data, and routing data.  Is there the same capability for production order data?

    Dear ,
    You need to activate Order Change Managment-SPRO-Shop Floor Control -System Modification  in case to trak production order change :
    A.Enhancements for Order Maintenance
            1.Enhancement for the Display/Change of Order Header Data
            2.Check Changes to the Production Order Header
            3.Checks Changes to Order Operations
    B.Enhancements for Order Change Management (OCM)
             1.Check Conflict for Change Step
             2.Definition of Comparison Fields for Order Comparison
    C.Enhancements for Order Confirmation
    Otherwise , from Basis side you can trak by
    1.ST03
    2.STAD-Provide  SAP T-code , user id , Client .Here you can find out what are the changes user did for any production order based on SAP Trxn .
    Regards
    JH

  • Production Orders Changes Log

    Hello,
    I would like to know if there is any Standard way in SAP to be able to see the modifications for a production order. I would like to see modifications in quantities or components.
    Does anybody knows if it is possible to retrieve that information in a standard way?
    Thanks

    Dear
    Changes in Production Order can be  traced through following ways :
    1.Order Change Management :
    Frist a Overall profile should be configured in SPRO > PRoduction>Shop Floor Control > Operations>Change Management for Production Orders-->Define Overall Change Profile.
    Create a Change Number CC01 with Release Key
    In Object Types select/tick "Actv", "object", "MgtRec",
    You get the Change Number by Saving .
    Use this Change Number to Change BOM or Routings
    Then Release the Change Number useing Release Key till then you don't find the Change of BOM in Production Order.
    Then go to Oder Change Process T Code :- COCM
    Tick Change Number and Select the Change Number & Execute
    Select the Production Order, click on Procurement element icon you get another screen select and execute again.
    You get an Pop-Up screen. "Determine changes, Check changes, Change Original Order.
    you see the changes in BOM for Production Order i.e. after COCM.
    Then Confirm the Changes in Production Order then New changes will be Active in production Order.
    Use COCM1 to find out the details or CO03--Extra --change
    Please check link  : http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PPSFC/PPSFC.pdf
    2.To  get the changes in Production Order apply SAP Note 390635.
    3 .You can use T.code AUT10 to check the changes made to production orders in specified period.
    Regards
    JH
    Edited by: Jiaul Haque on Nov 28, 2010 2:11 PM

  • Production order change document

    Hi experts,
    Can anybody please tell me where I can get change document for production order.
    I have first created order & then saved it. Later on I changed BOM component quantity.I didn't get any change document in GOTO--Change document. Where I faced message - No change process found for order 1000470.
    Please help.

    Hi,
    You will be able to get change documents, if you're working with Order Change Management. If not, then you will not be able to get the same.
    For OCM, you would need to configure the profile in OPL7 & OPL9, assign the same in material master. Then you will be able to manage changes via COCM.
    To understand better, refer to the link
    http://help.sap.com/saphelp_erp60_sp/helpdata/EN/41/3699761bc211d2b62b0000e8359890/content.htm
    Hope the above helps.
    Regards,
    Vivek

  • Production order changes overview

    Hello,
    I would like to know if, in the new SAP version (6.0), is there any way to display the changes done for a production order. The same functionality as in the material master chnage documents.
    Regards
    Laura

    I am afraid, it is a No without OCM(Order change Management)
    We could only see the Order status changes provided relevant Stauts change settings are active in OPL8 implementation tab.
    However I guess,we can get the changes in a prodcution order with the implementation of OCM.
    Regards
    Ratan

Maybe you are looking for

  • Color looks different within a document in different page

    Hi, I created a square with a green stroke (RGB-0.255.0) that I had placed on different pages within a document. On some pages, the green looks perfect and some other pages it looks like it is converted in CMYK, The green doesn't look the same. Does

  • CiscoSecure Services Client and Domain Logon

    I'm attempting to get CSSC to perform an authentication against our ACS database using Single Sign On. However, I need the username to be passed to ACS as DOMAIN\USERNAME whereas CSSC appears to pass just the USERNAME portion. ACU/ADU have the abilit

  • F110 - no valid oayment method found

    can somebody kildly let me know why am i getting this error in f110. response will be awarded . thanks.

  • Stop-Motion Filming

    Hello, I am trying to make a stop-motion film and the photo duration settings aren't working properly. I am using iMovie 6.0.2. I am not using Ken Burns. The default photo duration seems to be 9:29. To change this default, I have found the answer in

  • Compiler won't run application

    I downloaded Java 1.3.1_04 and I believed i installed it correctly when I compile a class the message is cannot run application. I set all paths correctly My dos prompt says the the Jre is installed. Why won't it run