Organization Structure for multiple countries

Hi,
We are setting up GLOBAL support organization. Our support organization includes following countries:
1. China
2. Japan
3. Korea
I am reading the SAP blog from forum. It says that,
"Enter the necessary data in the address tab (City and Country). In the Function Tab, Select Service and Service Organization. In the Attributes Tabs, check for the attribute maintenance Scenario: Service that you have a value in the attribute Country. Be aware that the basic organizational determination process is based on the Country value. This means that all of your business partners should have the same value in this attribute. If you have more than one country then you should create several organizations".
My query is:
In my organization structure, it involves three countries (China, Japan & Korea). I have included all the three countries in a single organization structure. But as per the above statement, should i need to create three organization structure for three countries?
Regards
Kumar

Hi Kumar,
Sorry for late response: but the answer is no, only one structure for each country.
Dr. Berg

Similar Messages

  • HCM Processes and Forms : Using single Form Scenario for Multiple Countries

    Hi ,
    I have a requirement to design a HCM P&F form ( Single Process, Single Form Scenario ) to support multiple countries.  Form fields should be visible/invisible based on the country ( derived from the login Manager).  please help me with the following questions.
    1. Is it right way to enable/disable the fields in the same form scenario for multiple countries ( Approx. 20-25 countries)
    2. Is there any limitation to no. of fields on the form? does the form performs well with multiple dynamic conditions?
    3. If yes, what is the best way to do this? through Java Script / Back end Generic Service?
    Thanks in Advance,
    VR.

    Hi VR,
    1. Is it right way to enable/disable the fields in the same form scenario for multiple countries ( Approx. 20-25 countries)
    -You can use same form scenario or process for multiple countries if you are using fields based on international structure HCMT_BSP_PA_XX_R*. If you intend to use country specific fields then you may like to use different form scenario for different countries.
    2. Is there any limitation to no. of fields on the form? does the form performs well with multiple dynamic conditions?
    - As such there is no limiation for the fields.Yes, form performs well with multiple rule configurations.
    3. If yes, what is the best way to do this? through Java Script / Back end Generic Service?
    I interpret you would like to derive & show fields based on same backend logic, in that case you should generic service.
    If you want to show fields based on manager's logon then you should also use authorization BAdi.
    Regards
    Pooja

  • One TPV for multiple Countries

    Hi Experts,
    Could you pls share experirnce/knowledge around having one TPV for multiple countries together. The scenario is like below:
    1. There are mutiple Countries in Central America which are small islands for whom we need to roll out the Travel and Expense Solution.
    2. The Company code is only one which contains employees from all these Countries.
    Could you tell us how can we do the setup. Should we create one TPV at the company code level. OR should we rather use some other criteria for selecting the TPV maybe at the Personnel area or Personnel Sub Area level.
    Your help is much appreciated.
    Regards,
    Vijay

    Hi Kiron,
    These things I am aware about too. My real question is if I create only one TPV for the company code and assign the Country of the Company code then what issues would this cause. To name a few pls see below.
    1) The domestic Country would always be the Company code Country so would be treated as Domestic Country and show on the Form also as domestic Country even for the employees who are from other Countries.
    2) There are setting which SAP allows differently for Domestic and International like per diem, miles cumulations. So these necessarily have to be kept as same even though local laws are different in all these countries as Domestic is only the Company code Country.
    So I need detailed analysis of what impact I will have by having only one TPV as against making many TPV like one for each Country by using some other parameter like Personnel area/Personnel sub area etc.
    Appreciate your help!
    Regards,
    Vijay

  • Set up the Organizational structure for MSS scenario

    Hi!
    I would like to set up the Organizational structure for MSS scenario within SAP Portal.
    Question:
    1) How to set up/map real user from SU01 to Manager? (tcode, report)
    2) How to mark them as 'Chief' (tcode, report)
    3) How to be sure that PA & OM are configured correctly and the integration switch is on?
    Which SAP course or SDN blog describes this?
    Thank you very much!
    regards
    Jürgen

    How to be sure that PA & OM are configured correctly and the integration switch is on?
    Check It000 and IT0001 here u will get objects from OM and PA  (position ID , Job Key, organisational Key)
    and integration switch
    check plogi orga , plogi plogi , plogi perli  in V_T77s0
    Edited by: Sikindar on Feb 10, 2009 6:53 PM

  • How to modify organizational structure for workflow?

    Hi,
    What is the best practice for modifying the organizational structure for workflow? I know I can do all the changes in development and move it to production via transport system but is that always required.
    It seems tedious to transport the org plan from dev to prod every time there is a position change etc.
    And it does not allow you to change it in production since the client is locked.
    I don't even have all the users I have in production in my dev box so I can't assign the correct ones to positions. Would it mean I have to have the users in the dev box mirror the ones in production?
    Thank you,
    Sergiy

    This answer depends on the HR managment that you have there, if the HR area is a good coordinated area the best answer is to configure the system for automatic transports and pass the HR structures in this way, you can lock some dangerous infotypes in the T77TR tables and be sure that you will not have any trouble with that data. the best thing using this option is to have a specific DEV client to transport the HR structures.
    If you will not have any control between the Dev Environment changes and some people will modify in Prod and other people will make transports in a Dev environment, the best option is to open the client and modify the Org structures every time you need it.
    Refers to the SAP Press book Practical Workflow, section 5.4.2.
    Regards.

  • Organizational structure for MSS scenario

    Hi!
    I would like to set up the Organizational structure for MSS scenario within SAP Portal.
    Question:
    1) How to set up/map real user from SU01 to Manager? (tcode, report)
    2) How to mark them as 'Chief' (tcode, report)
    3) How to be sure that PA & OM are configured correctly and the integration switch is on?
    Which SAP course or SDN blog describes this?
    Thank you very much!
    regards
    Jürgen

    Hi,
    For MSS,
    Perner have the chief position in organization structure   that you can create in transaction PP01 and for relation ship infotype you have tio create 012 relationship.
    Infotype 0105 with subtype System User Name must exist
    PLOGI ORGA Switch MUSt BE Activated
    Regards,
    Kapil

  • Can we Exceucte campaign for multiple countries and Regions?

    Hi Experts,
    can we execute the campaign for multiple countries and Regiong at time? or
    Aany standard functinality for this type of requirement?
    thanks in advance,
    Regards,
    Prameela

    We don't support merging of multiple responses at this time. You could export your data and use an application like Excel to do this type of merging for you.

  • What are the central organizational structures for the following SAP applic

    What are the central organizational structures for the following SAP applications ?                                   
    a)     FI                              
    b)     SD                              
    c)     MM                              
    d)     CO                              
    thanks
    manoj

    hi,
    Inventry and Finance
    regards,
    varma

  • Organization structure for Case study .... need yr advice

    Hi …I am in process of preparing an org structure for one of the company.
    The company operations is like ….
    The company has four factories in different locations and have 3 Regional distribution centers (RDC) across india. Each distribution center has 5 branches (Sales Offices), in this way they 15 Sales offices across India.
    Most of the materials are procured by factories independently while some materials are centrally procured. Factories produce Finish goods and they are either sale to customer directly ( big regular customers) , or transferred to RDC to cater the requirements of other MID size customers and the other possibility to transfer it to Branches for Retail customers. RDCs also transfer FG to Branches.
    All factories , RDC and branches have warehouse facility , however branches have limited warehouse facility as the customers supported by them are very few and generally deliveries are made directly from RDC / Factory.
    They also have one R&D department in another location to develop new products and material is generally transferred from factories to R&D department.They also have one project division at the same (R&D) location which handles commissioning of new plants and procurement of capital goods.
    Raw Material , Semi finish and FG are transferred between factories and FG material is also transferred between RDCs.
    The group also has another Company which produces another line of products. RDCs and Branches of first company also work for second company (which means same RDC can store FG produced by both companies) and also Branches can also have FG material of both companies. Second company doesn’t have any specific R&D or capital division and R&D and capital of first company also work for second company.
    Inter company transfer between both companies is a regular practice.
    > Proposed Org structure
    Company – Group Company
    Company Code – First company and Second company
    Factory Configurations
    For first company
    4 Factories will be 4 plants
    Factories Structure (Storage locations / warehouses and storage type)
    Since factories have different type of material ( like FG , Raw material , WIP ) therefore I am confused what option I should select 
    1) 3 storage location ( for each plant) and one warehouse, 1 storage type
    2) 1 storage  location and three warehouses (I think this is not possible in SAP , not sure ?? )
    3) 1 storage location , 1 warehouse and 3 storage types
    RDC structure
    RDCs have full fledged warehouse facility and therefore thinking of making them also as Plant. Every RDC will have 6 Storage locations , 1 for First company RDC itself, 5 for associated branches and I feel each “RDC storage locations” should be a associated to a separate warehouse also.
    ( Since both companies produce different set of products therefore they will have different material and hence thinking of handling products of both companies in same plant and same storage location and warehouse , may be two storage type/area can be defined to differentiate material of both companies.)
    Branches: Will be storage locations under RDC …..
    While making branches as Storage location …. I have another question about valuation , since material from Plant and RDC is being transferred to Branches and  from there it is distributed to customers therefore the valuation of FG at BRANCH and RDC should be different as transportation cost , packing , unpacking etc cost should get added at Branch level.
    Therefore in case I make branch as Storage location , I will miss the valuation part while if I make them as Plant then there will be lot of documents get generated for each movement. Hence not sure for what option I should go.
    R&D:
    Since R& D department is involved in testing in New Product development and generally material is required to be scrapped after testing therefore thinking of making it as Plant with one storage location and may be here I don’t need any warehouse (WM) here.
    Project Division
    Project division may also be a separate plant with one storage location and NO WAREHOUSE is required to linked with it.
    Purchase Organizations
    4 purchase organizations for each plant respectively and 1 centralized purchase Org for central procurement.
    Your all valuable inputs are welcome .... looking foward to have a best possible configuration for above mentioned case study.
    Regards

    Phew... long long question
    The rule I generally follow is that the org structure should map reality.
    Company code - where Balance Sheet and Profit and Loss are prepared at the end of the year. If an entity does not do this, it is not a company code.
    Plant
    1) Each manufacturing facility is a plant (could be in 1 location or separate).
    2) Each separate location is a plant (even if it only stores goods). May be an overkill, but helps when legal requirements change or the location is upgraded.
    So in your case, RDC will be a plant (may be more than 1 if necessary). R&D should be a separate plant without warehouse management
    Storage location
    The only rule I follow is that there should not be any overlap of storage locations. So physically, any area of say 1 square foot should belong to one and only one storage location. Otherwise there is a lot of confusion during physical inventory. So logical locations are a no-no.
    I usually use a lot of storage locations.
    Don't have a warehouse spanning multiple plants (even though it is allowed).
    Purchasing organizations
    Have one for each location of purchase. If there is a team sitting in each plant procuring for only that plant, have it as a separate purchasing org (not strictly necessary, but makes authorization simple). For central purchasing, a central purchasing org should do nicely...
    Hope this helps,
    Lakshman

  • Organization structure for Inventory management

    Hi All,
    I am looking for organization structure specific to inventory management and also data flow architecture.
    If there is any standard org structure is available please share with me.
    Regards
    Vijay

    I am looking for organization structure specific to inventory management and also data flow architecture.
    > If there is any standard org structure is available please share with me.
    Hi Vijay,
    Standard Org Structure for IM starts with Plants and ends with Storage Locations. You can create required no of storage locations under your plants, where plants are assigned to company codes. Its always better to copy from master plant 1000/0001 while creating the plants where you can make changes during creation where required (factory calendar etc).
    All the material movements within the plant happen between storage locations, material-material, special stocks-unrestricted stocks with no accounting effect.
    Movements between the plants can be planned wrt your needs such as STO with no financial postings unless you have plant wise PCA
    You can follow the standard avaiable structure for your IM org structure.
    Regards
    Shiva

  • Organization Structure for Petro-oil business

    Hi experts,
    I'm a new consultant, and I'm implementing for a Oil & Gas Project. I want to ask you a recommendation about the solution for Organization structure.
    This business sell some kind of good:
    1) Hydro: mogas, diezel, mazut, kerosense...
    2) Non-Hydro: cement, Iron, gas, lubricant...
    I should use two org. structure for each kind, or just unique structure. Because each kind is controlled a different method, so I suggest use two org. structure, but its difficult for reporting.
    Plz help me.

    Hi Kumar,
    Sorry for late response: but the answer is no, only one structure for each country.
    Dr. Berg

  • Organization structure for real-estate project

    Hi
    I am required to work in a real-estate company project. 
    I am confused about the organization structure which should be created for the company.
    The company undertakes various projects like housing, shopping complexes, malls, wind-mills, etc.  and want to know the profitability reports of each individual project.  Every time  company will be starting new new construction activities.
    Please suggest an organization element how I can represent these in the Controlling Area and avoid number of GL accounts growing out of numbers.
    Points for helpful answers,
    Regards

    1. For Activating or Bring IS Retail Real Estate Module is there any additional user cost or license is required ?
    Hi  Jai
    Real estate module is not IS solution, licensing is normal for RE
    2. Is it possible to activate two industry solution in the same box ?
    yes you can with some small precations
    3. If yes, Will Retail and Real Estate or any existing Functional modules affect?
    No, there is no impact.
    4. Normally what is the time frame for implementing the Real Estate Module for GCC country zone.
    That based on project, max is 4 to 6 monts
    5. Real Estate is a new installation or Add-on ?
    No.
    Thanks
    Jilani

  • Sales Organization Structure for Distribution Industry

    Hi Experts,
    Need some inputs wrt Distribution Industry
    1. In Distributor set up. how should we set up the different manufactures which supply the products for distribution.
    2. How should we link the manufactures to Products they supply.
    3. How should we link the sales representatives to specific manufactures.
    4. Would it be a wise decision to incorporate manufactures as a division in the organization structure. Or should we map the manufactures as vendors and maintain the Vendor Info records.
    It would be really great if any one can share their experiences wrt to sales organization structure in the Distribution industry especially Pharma Distribution.
    Regards,
    KK

    hi
    this is to inform you that:
    first of all  i have a question to you.  you are manufacturer of products that means are you paying excise duty for manufacturing products or only distributor of products.
    1. In Distributor set up. how should we set up the different manufactures which supply the products for distribution.
    1.a. You can consider if you are manufacturing and distrubuting products
    If you are a manufacturer - tae material FERT if you are a distributor - tae HAWA asa material type.
    2. How should we link the manufactures to Products they supply.
    2.a. the organisation struccture lins each other & MMR also helps to lin 
    3. How should we link the sales representatives to specific manufactures.
    3.a. it may be specific to divisions tae one sales group for each specific divisions.
    4. Would it be a wise decision to incorporate manufactures as a division in the organization structure. Or should we map the manufactures as vendors and maintain the Vendor Info records.
    4.a. manufacturer as a vendor and different products a divisions.
    It would be really great if any one can share their experiences wrt to sales organization structure in the Distribution industry especially Pharma Distribution.
    sales organizations : 2 - domestic & exports
    distribution channels : 3 - retail - super stocists - C & F agents.
    retail/wholesales/distributors/superdistributors/super distributors - all you can consider all into one distribution channel or tae as different distribution channels you have to analyse from reports perspective to have all these.
    divisions - products = divisions lie cardiac - orthopedic to name a few.
    sales office : you can have many as per your requriment.
    sales group : basing on divisions = sales groups
    company code = how many balance sheets you are submitting now to AAI that many company codes you have to have.
    batch management with FIFO or LIFO strategy has to be mandatory in implementation.
    balajia

  • SAP MM Organization structure for the Utilities Industry

    Hi,
    Please let me know how does the typlical org structutre should look like for the Utilities company.
    Thanks in advance

    Hi,
    Material management organizational structure includes
    1. Purchasing Organization,
    2. Plant,
    3. Storage Location &
    4. Purchasing Group.
    Note:
    It depends how you project or design the purchasing group in the organization & purchase group can be created and represent as department .In general, company have many more departments & need to control & approval of all purchasing documents at department level & at the end to know cost incurred in each department with various activities( more then one& each GL represent one activity) .So in turn Purchasing group(department) is linked  to cost center and then different G/L accounts which represent various activities linked with the cost center.
    Regards,
    Biju K

  • Track Master Data Changes for Multiple countries

    Hi experts,
    I am in a Global HR Implementation & Rollout Project. We are creating Outbound Interfaces for 3 countries to export pay, time and general data to the 3rd party systems in those local countries. (Payroll is outsourced there).
    As well as sending New Joiners data every month, we need to send Changers data also to all those 3rd partys every month before the Payroll runs.
    I know 2 solution for this :
    a). Using Change Documents - Tcode : SCDO ..etc
    b). Using the report RPUAUD00.
    c). Using RBDMIDOC.
    Query :
    1). Are these the only solutions ?
    2). Whats the best solution for doing this for a Global Rollout project ? I need to track master data change for different countries for different set of Infotypes and fields. I need to send those Changers data as well as the New Joiners data through the Outbound Interface to all the local countries.
    This year we are doing for 3 countires, next year for 9 more countries, etc. Whats the best solution keeping this in mind ?
    Restrictions :
    1). Our Client HRs dont want us to disturb the report RPUAUD00 as they use that regularlly and want the flexibility to configure the configs themselves.
    2). If I must need to create and activate Change Documents for ALL individual fields, is there an easy way of doing this ?
    3). I need to send this Changers data from SAP to Legacy system, so dont know if RBDMIDOC will be a good solution for this. Any comments ?
    Just want the best possible and feasible solution for this issue.
    I will be please to allot point to anyone who gives a good solution.
    Moreover will be Thankfull also !!
    Cheers.

    Please try with transaction code "PC00_M02_LINF0"
    Cheers
    Suresh.KK