Planned cost in the project

Hi,
I have created a project using Assembly processing with strategy 85. The planned cost of the project per month is say Rs 50,000/- The duration of the project/ internal activity is for 6 Months. The scenario is the planned cost is fixed for each month.i.e Rs 50,000/-. I have maintained 'Plan Price for the period' in the costing variant to get planned cost equally distributed over 6 months. But the report shows (S_ALR_87013532) the planned cost is divided over 6 months (Rs 8,333/- for each month)
Could any one help me in resolving the issue.
Rgds,
Prasad

Hai Shrikrishna
Kindly check in the Costing Tab of the Workcenter which u are referring in the Network Activity.
In the Costing u need to maintain the valid Controlling area , Cost center , Act.type.Int.Processing (Key identifying the activity type used in other types of internal processing in costing like networks) and Formula key for costing (Key which refers to the formula used to determine costs per activity type).
Unless these are not maintained cannot get the Actual costs(not planned).
Based on the hours (planned) mentioned in the workcenter , work to be confirmed(CJ20N/CN25/Cn27) to convert the planned hours into costs.
ENJOY SAP PS.
Regards
PP

Similar Messages

  • Plan cost  in the costing variant

    Hello,Experts,
    I have one problem in controlling .I have Finish product which is produced through subcontracting.
    i have maintained Special procurement key 30(subcontracting) in the material master.
    I have produced material through subcontracting only (first P.O & then by MIGO).
    No  Production Order is there.
    Now the question is how plan cost of the subcontracting material has to be fetch?.
    Please help me out
    regards,
    mys

    Dear,
    While doing subcontracting process the following accounting docs will come
    suppose "X" is the finished component
    "A" & "B" are the child components
    the following documents will come
    X - stock BSX( debit)
    off set account X - ( credit)
    service cost FRL (debit)
    while doing with m.type 101
    NEXT
    stock account of chaild component A - BSX
    off set acount of stock - GBB - VBO(+)
    stock account of chaild component B - BSX(-)
    off set account of stock - GBB - VBO(-)
    while receiving the finished component i.e 543 m.type(raw material consumption account)
    Subcontracting handled through external operation in routing i.e Prod.Order>PR>PO>GR>Confirmation of Prod.Order is planned subcontracting which provide the subcontracting cost on order.That cost is loaded on the as actual cost on the order.Which in turn settle on the cost object.
    I don't think without production order you will get plann cost.
    Regards,
    R.Brahmankar

  • Inclusion of planned cost to the material while Invoicing

    Hi Everyone,
    We are facing a problem, kindly guide me to solve it:
    We are purchasing 'X' Material (split valuated) through a Purchase Order in which we did not provide any planned cost.
    But after GR we came to know that planned cost should also have been entered in the PO. But in the PO, while creation we did not select any planned cost line for the item. So after approval of PO and GR, we were not able to enter any planned cost.
    Now while adding up planned cost during Invoicing through MIRO, we are facing an error message:
    Error saving valuation data for material P1S002 0002
    Message no. M8829
    Diagnosis
    Error occurred when the system tried to save the valuation data.
    Please guide me how to do invoicing by including the planned cost and booking the planned cost in the material.
    Thanks and Regards
    Edited by: MP Vashishth on Jan 10, 2011 2:21 PM

    Hi,
    Thanks for your reply please.
    When i am trying to enter this freight value in the Material Tab, i am facing an error message :
    Error saving valuation data for material P1S002 0002
    Message no. M8829
    Diagnosis
    Error occurred when the system tried to save the valuation data.
    Procedure
    Contact your system administrator.
    Please guide.
    Thanks and Regards

  • Can't get the plan cost in the service order!

    Dear experts,
    I create a service order from a service Notification,in the service order , I assign a work center, activity type and work to Operations,however I can't get the plan cost in the Costs tab, when I use the T-code:IW42 confirm the service order, It can get this actual cost! I have maintain the activity type,I don't know why can't get the plan cost?
    thanks
    Lance

    Hello,
    Have you maintianed the activity pricing? I think the transaction is KP26.
    Prase

  • How to post costs to the project?

    Hello
    I need to post costs to the project for testing purposes. Please tell me how as I am not PS consultant
    Any costs to any period
    Thanks

    Hi Comandante,
    Release Project first, then Execute MIGO transaction.
    Selection Goods Issue, against Others.
    select movement type 221 Q.
    Check the availability of stock for any material in MMBE for same plant which is assigned in the WBSE/Project.
    Enter material, qty, WBSE, Plant and storage location and then Issue material. Check the actual cost against WBSE in CJI3.
    As suggested by robert, you can post actuals in the project but you have to run more transactions.
    Hope this helps you !!
    Br
    Hari.

  • Difference between the planned cost and the target cost

    Hello guys,
      I am really confused between the planned cost and the target cost.As Per the sap help target cost is cost required to produce certain quantity of material.And planned cost even carry the same definition.
        So is there any difference between these two cost.Are they same?

    Jitendra,
    Genarally in CO we will define Target cost is getting calculated in the Production order based on the "Standard Cost Estimate" after GR. Planned costs are calculated based on the current costs.
    Example:
    Assumption: Assembly Material A with Standard Price, Component B and Component C is maintained with Moving average
    Material A Cost 1EA = (component B = $10 + Component cost C = $20+ Activity Price $1) = $31, this is the standard cost estimate for the material.
    Now I create a production order on 15th of the month, and the Moving average price for component is now $20 due to subsequent GR with higher price. Now the planned cost for the order would be (20201)=$41, whereas the Target cost would be still $31.
    Hope I was able to clarify,
    Regards,
    Prasobh

  • PS - Report on Planned v/s actual cost of the project

    Hi,
    I have a client requirement on the above subject. In Report S_ALR_87013542, Under actual cost the system is taking both the Revenue and Actual cost booked on the project. Is there any other report wherein the system shows only the actual cost booked on the project so that planned V/s Actual can be compared.
    Rgds,
    Prasad

    Hi,
    You can also refer the report S_ALR_87013543 - Actual/Plan/Variance Absolute/Variance %. This will give the reports based on cost elements. Morever plan cost Vs actual cost can be obtained from Project Infosystem report (CN41/ CNS41).
    In fact the report S_ALR_87013533 is a hiecherachical report for plan & actual cost of project.
    If the system is calculating wrongly both revenue & actual cost under actual then you need to check Cost elements asignments & value category details.
    Hope this will help you.
    Regards,
    Rakesh Pradhan

  • Document number of Planned cost booked on Project system

    Hi All,
    I have a requirement wherein i need to find out the document number of the cost booked in Project and WBSE. Like for eg in Report S_ALR_87013532, there is planned cost.
    also in the same report S_ALR_87013532, we have OVERALL VALUES and TOTAL OF YEARS. What is the difference between the two ?
    Thanks in Advance
    Regards,
    Ajay

    Overall is derived from the Overall values planned for the project (at the overall level) - look at config of your planning profile - transaction OPSB.
    Total of Annual is the sum of the all annual values planned for the project.
    To get the document number, you will need to go to the line items. To go there, select the WBS element or whichever level you want to drill down to and then goto menu Goto -> Line items. You will be given a list of line items available (actual, plan, etc...). Once you get in there, you should be able to select the "Document number" field from the available fields or click on the "Document" item to view the posting document.

  • Cost of the project

    Hi,
    My client has delivered 100 bags of material to the customer and Client receive some (for e.g 70 bags)against delivery of material to a particular clientu2019s site as payment against deliver of goods to that project. In this case when Client calculate their Inventory at any particular date  the stock should be 100 bags but the value should be of 30 bags only(Because bill has been received for 70 bags).If client uses this stock for the project,how this value will be taken for cost of project.
    Thanks & Regards,

    HI,
    Pls. check it's thru' T-code CJI3.
    Change layout add material coloum.
    Regards,
    Vishal Kr. Sharma

  • Extraction of actual cost in the project

    hello all,
    Kindly suggest if any function module is available to extract actual cost incurred in the project? The actual cost includes the cost of material consumption, activity confirmation, Fi posting. The intention is to get the total actual cost on the WBS at one place.
    Regards,
    Sudhir

    RESOLVED

  • Reverse Planned Costs by the transaction CJ46

    I need to reverse planned costs. This process must be carried by transaction CJ46, but don´t works. Just reverse half of the value rather than reverse the total. There is any transaction where i can launch a negative value to pay the charges of structure that are not reversed?
    Thanks.
    António Pinho
    Edited by: FPinho on Feb 18, 2010 5:30 PM

    Not work
    But thanks
    Edited by: FPinho on Feb 8, 2010 5:25 PM

  • CIP Cost for the Project

    I want to write a query so that i can identify the CIP Cost related to the Projects.
    Can any one help me in this ?

    There is an already existing view PA_CAPITAL_PROJECTS_V , which provides summary information for a project. You can use that as a starting point.
    Thanks,
    Ram

  • Project plan cost

    Hi
    We are working with Project system and we trigger project from Sales order.
    We are using Assembly order for this purpose.
    When we are looking at plan cost of the project, cost is directly picked up from the material instead of referring to WBS BOM and production lot cost estimate.
    When we are creating project manually cost is picked up correctly from the WBS BOM.
    Do we need to do any special setting for cost when we are triggering project from the sales order??

    I think you might be using the Sales document as cost object in your configuration. For your requirement, you should use the Project as the cost object. Please check the account assignment category in the requirements class. It should be D (projects).
    Hope this helps.
    Regards,
    Ajinkya

  • Exclude Planned Costs - Define Tolerance Limit - Budget Control

    Hi,
    We are trying to customize our system in order to exclude the planned costs of the project of the budget availability control.
    Example: If once I have budgeted and released the project I add a component to the project I do not want to any error message to appear. Error should only appear once I generated the Purchase Requisition for an amount superior to the WBSE budget.
    We have been trying with the customizing point "Define Tolerance Limit", trying with different combination of the Activities Groups but we haven't succeed.
    Has anybody tried this before? Could anybody give me a hint?
    Thanks a lot

    Hi,
    The moment you save the project (after making changes to your project, say, adding new component), system will check against the budget (since AVAC is already active).
    We are trying to customize our system in order to exclude the planned costs of the project of the budget availability control.
    We have been trying with the customizing point "Define Tolerance Limit", trying with different combination of the Activities Groups but we haven't succeed.
    This is not possible.
    As an alternative, what you can do it, before adding the new component to the project activity, you need to update your budget (suppliment) with the expected cost of the componet you are adding. This way, you can avoid this error.

  • Project Plan cost report - not showing any output.

    Dear Experts,
    I have created several projects and done the planning.  I have used work centers and activity types for manpower cost planning. Also created some PRs against the project.
    When I goto the network activities and select the line item in the menu path Edit - costs - Planned/Actual - cost planned /actual
    It shows me the planned cost of the activity correctly.
    But when I am running the report CJI4, it shows nothing. The report is not at all executing.
    I dont understand why it's \not showing.
    I have checked the control key PS01 for the cost field is enabled (tick available on the cost friled)
    Can any one please help me??
    Thanks and Regards,
    Praveen

    1) Please check that the WBS element is integrated in plan, and the plan integration is fully activated in the project.
    2) Plan line items are only written in certain cases.
    The following rules are valid:
    1. Plan line items can be written in
    a) structure-oriented cost planning CJ40 (total values, annual values),
    b) cost planning on orders KO12,
    c) unit costing independent of cost elements,
    d) structure-oriented revenue planning CJ42 (total values, annual values)
    e) structure-oriented financial budgeting CJ48 (total values, annual values, period values)
    f) primary cost planning,
    g) activity planning,
    h) revenue element planning.
    2. Plan line items are never written in
    a) Unit costing on cost element level
    b) Network costing
    3. Line items are only written if a user status permits the business transaction 'Write plan line items' explicitly.
    Exception:
    For plan-integrated WBS elements and orders, line items are written in cost-element oriented planning if integrated corporate planning is activated in the fiscal-year parameters of the respective plan version, regardless of the user status.
    4. Plan line items for structure-oriented planning can only be displayed in the respective planning transaction under menu option "Extras-->Line items".
    Let me know if this was useful
    Ritesh