Hi all,
           here in my scenarion, i got prodcution plant and R&D. in R&D production is going depends on sales indent.its prodcut is Bio fertilizer.one resource :fermenter.
           Machinary is fermenter.and one packing machine
           others are manual work.
           How can i define in sap .whether as seperate plant ..or one resource.
thanks
s.suresh kanna

Definition regarding the plants are not only based on resources but also in many logistic aspect, as inventories, transfer and deliveries.
If fermenter and packing machine are in the R&D section , and this is only related to prioduction,
I would create them in the same Plant but under a diferent Resposible or Planning Group. So you can follow the performance of this area separately.
Let us know if this can be helpful.
regards

Similar Messages

  • CTM planning for process industry

    Hi,
    We are taking CTM planning run in a process industry scenario where we are having continuous processing. But when we do CTM planning CTM creates PP/DS planned order to meet the delivery date of orders and for some orders their are unscheduled gaps between operation due to non availability of next resource.
    Is it possible to create orders in CTM without any unscheduled gaps between the operations as is the case in case of orders created using PP/DS?
    Regards,
    Sanjog Mishrikotkar

    Hi kiran Ghule,
    With the functions of the Quality Management (QM) module, you can implement it.
    The QM application component supports tasks associated with quality planning, quality inspection and quality control. In addition, it controls the creation of quality certificates you can do this
    Explore your self in this module if any problem then come back.
    Regards
    R.Brahmankar

  • Scenario about process industry

    1) please tell me steps or scenario for process industry?
    2) what is the difference between descrete manufacturing & process industry?

    Hi,
    Process industry where the production process is set and its continuous or batch production
    e.g.consumer goods
    discrete is like industry having production as per order only  
    e.g.machine manufacturer
    You have certain industry specific scenarios in SAP to map these
    Hope its clear to you
    BR
    Diwkar

  • Process Industry- How to map the Scenario?

    Dear Gurus,
    The is a Process Industry, Chemical Manufacturing Unit, which does the following sequence of Operation to get the Semi finished material.
    1) Acid, TC, and Catalyst are 3 Raw materials
    2) Acid, TC and catalyst after being put into reactors, they Undergo 2 Phases. Crude and Distillation
    At crude phase, Crude is Produced. But they dont want to do confirmation of crude.
    At Distillation stage, Main Fraction(MF), a semi-finsihed material is Produced
    But at the distillation Phase, 2 more, Products are produced in conjugation to MF.
    These 2 Products are Lower Fraction(LF) and Residue.
    When these LF and Residue are produced, they again put into reactor and some qty of TC is added to achieve MF which again produces some portion of LF and Residue. And these cycle goes on.
    They keep these process continuing. 
    In short: MF is derived in 2 ways
    Acid+TC+ Catalyst=MF
    LF+Residue+TC=MF
    Please help me in mapping below Points comprehensively.( They want one Order Type for 2 phases.)
    1) How BOM will be made of LF and residue if I treat them as Co-Product??? Or some other technique in SAP can map it?
    2) What is the Step by step Costing configuration of Co-Products. I searched lot but unable to find the proper settlement rule of Co-Products.
    Thanks
    Shailesh Mishra

    Dear Rahul,
    As I understand that Co-Products cannot be subjected to movt type 261 and same i have tested in system. So, concept of Co-Product is not applicable here either with Recursive BOM application.
    The solution which we have found here is that Client will make one of BOM of Acid+TC+ Catalyst
    which will give MF. The concept of Reverse Calculation will be applied. Daily product of LF and Residue will be extrapolated at the Month end. And the LF and residue Quantity will be tracked not from system. Only during month end, LF and Residue Physical Inventory will be taken and it will be treated as Raw materials So, in the Running Process Order 262 will be done of So-called LF and residue. Stock Up(+)
    And same Qty of LF and residue will be subjected to 261(Stock Down-) in the next month New Order in form of Raw material.
    So cycle of 261 and 262 of LF and residue in form of Raw materials will be Perpetual and settlement of orders will also be sacrosanct.
    Best regards
    Shailesh

  • Use of QM in Process Industry

    Hi,
    QM Expert ,I am from automobile sector, I want to know the detail requrement of SAP QM  in process industry,as per my knowedge only shelf life scenario is different other than all processes of QM ,please give the detail Scenario of relating QM in process industry in detail
    Regards
    Aditya

    hi
    QM in process industry can have a significant difference from Normal Automobile or Production system.
    It can be
    1.Batch manegment can  form significant part of Process Industry.
    2.Recurring inspection is also  huge part of Process Industry
    3.Inspection points along with sample drawing procedure in Inspection planning can be used in process industry.
    4.Shelf life material as you mensioned is significant.-->stability study
    5.Instead of Production orders Process order are used in Process industry.
    These are more or less can be observed in any process industry.
    Also Refer link
    www.sdm-c.com/files/Barcelona_Mazliach_SAP_QM.ppt
    Regards
    Sujit S Gujar

  • Production of mango in processing industry

    Hi,
    We have one scenario ,company is in process industry,they are manufacturing MANGO pulp,babana powder.
    The problem is that company itself having mango trees and banana trees and they are using these mangos and bananas for their finish product  means mango and  banana used as a  raw material.
    So,client producing raw material as wll as finish product,
    I want to know how production of mango and banana will be mapped in SAP right from planning to production .
    Note that these are seasonal fruits,so how they will plan beacuse water and fertilisers will consume through out period and production will happen in season only.
    Regards,
    vidyasagar

    Dear,
    How about maintain seperate plant for manufacture part. And Process as separate plant.
    By this you can capture manufacturing expenses like all maintenance, cropping, fertilization expenses at PLANT 1.
    And rest at PLANT 2.
    By this PLANT1 end can get a final price for the mangoes and can supply to PLANT2 as raw material. The rest processing can capture in PLANT2.
    The source for the answer from my side is WATER TREATMENT PLANT.
    The client process the miniral water and he owns the source of water supply like wells. Client supply through pipeline the raw material water (a distance of 60-70 kilometers range) to the processing plant. At source point client have maintenance for motors, maintenance of wells and lots of engineering and HR expenses. At final in plant he process, purification and some other process to make final product. Suggested with 2 plants and client agreed for this.
    What about this same process with your client??
    Regards,
    Syed Hussain.

  • Production of mango in process industry

    Hi,
    We have one scenario ,company is in process industry,they are manufacturing MANGO pulp,babana powder.
    The problem is that company itself having mango trees and banana trees and they are using these mangos and bananas for their finish product means mango and banana used as a raw material.
    So,client producing raw material as wll as finish product,
    I want to know how production of mango and banana will be mapped in SAP right from planning to production .
    Note that these are seasonal fruits,so how they will plan beacuse water and fertilisers will consume through out period and production will happen in season only.
    Regards,
    vidyasagar

    Hi
    See in your case, the mango fruit become mango pulb after some operations and the addition of some thing correct.
    so it have the bom and the routing obviously.
    in your bom  MANGO PULP - the components will be MANGO + WATER+FERTILISER
    you can add the water and fertiliser in planning or you can maintained as the comsumable materials.
    so as for you plan. the MANGO is the only material you need to plan to procure.since this is the season one. i think they will preserve it for the full year porduction.
    so you need to two planning for MANGO and the final product MANGO PULP.
    for MANGO , you need to plan such  a way that how much you need to preserve to produce the final mangao pulp.
    for MANGO PULP, you need to do the forecst as per the previous year sale. you can use the SEASION forecasrt menthod.
    revert back if any clearfication recuired.
    Thanks & Regards
    RAJ

  • Rework process for Customer returns in process Industry.

    Hi Gurus,
    We are working in a process Industry. The process is here we do
    Sales order
    MRP run
    Process order
    Process order confirmation
    delivery
    billing.
    Now the scenario is, once delivery done, customer returns the goods for rework.
    To complete this process, how can i go ahead and whether this will reflect in the PP module or not & how can we interrelate the SD with PP in this regard.
         Note: we dont have the CS module now
    Thanks.
    Thyagarajan.
    Message was edited by:
            thyagarajan krishnamurthy

    Hi amith,
    for return process you have to follow RE document type and LR for pgr
    while coming to excise you should have to do J1IEX without purchase order the the values of excise will be reversed .
    it should resolve your issue
    bvdv

  • Service Industry scenario

    Hello Friends,
    I am going to implement SD first time in airline industry, I think it is going to be like service industry scenario,
    Will you please let me know how the service order is created, How the process flow goes on?
    Which are the transactions involved in it?
    Thank you
    Sadanand.

    Hi,
    Process Flow
    This scenario includes the following process steps:
    Creating a service notification
    Changing the service notification (optional step)
    Check the task list
    Creating a sales order
    Change the sales order
    Changing the service order
    Time recording
    Confirming time to the service order (optional step)
    Confirming the materials used
    Creating resource-related billing request
    Creating the invoice for the billing memo request
    Closing the service order u2013 technical complete
    Key Points
    Service Order
    Definition
    Short-term agreement between service provider and service recipient, in which one-time services are ordered by the service recipient and resource-related billing performed upon completion.
    A service order contains the following data groups:
    Header data
    Location and account assignment data
    Object data
    Settlement data
    Operation data
    Component data
    Use
    The service order is used to document service and customer service work. In particular, you can use the service order to:
    Plan services specifically with regard to usage of material, utilities and personnel
    Monitor the execution of services
    Enter and settle the costs which arise from the services
    The data for the service order is entered in the history and is important for evaluations and future planning.
    You can also create a one-time customer in the order and transfer the data, for example, to the sales order. For more information, see Transfer of One-Time Customer Data and One-Time Customers and Vendors.
    Structure
    A service order contains operations that describe the individual work steps. An operation can be divided into sub-operations for greater detail.
    Spare materials and utilities, which are required for service work, can be planned in the operation.
    Integration
    Using the "worklist for notifications" for a maintenance or service order, you can group together similar notifications for processing. For more information, see Completion Confirmation.
    Services at several similar objects installed at the customer can also be processed using a service order.
    Regards,
    Murthy

  • I want to  prepare FONDRY INDUSTRY scenario for MM ponit of view.

    Dear Saper,
    i want to  prepare FONDRY INDUSTRY scenario for MM ponit of view.
    kindly help me .
    thanks.
    saran.

    hi saaavanakumar
    regarding foundry industry here process is different from other
    here there my might be scenario where a company sends the material and pattern to sub contractor , for pattern notional cost comes in to picture,this is info i had
    if my reply had helped u assign some points

  • Pricing in Process industry

    Dear All,
    In our scenario for Job work in textile processing industry we need to maintain the price (PR00). This price normally maintained is Rs.7.25/mtr and Rs.60/kg, therefore conversion relation is (1mtr = 120 g), hence the average weight required is 120g.
    There are two scenarios for example:-
    Normally if the average weight is 120 g then the customer is charged by 7.25 / mtr. If the average weight changes then,
    1.     Now if the dispatch material is 1mtr =140 g the billing will be on Kg basis which is approx   
                    Rs.8.40 / Mtr.
    2.     Now if the dispatch material is 1mtr = 110 g the billing will be 7.25 /mtr.
    How to MAP this in SAP pricing.
    RamananPV

    Dear PV,
             Create Master dta for the three materials like this.
    1.Material 1Average weight 120g
    2.Material 2 1mtr=140g
    3.Material 3 1mtr=110g
    Take sales unit as mtr (M)
    Maitain the price for the above materials based on the Unit meter (M) inthe transaction VK11 with the key combination Materail.
    According to that if you enter Material 1 in the sales order as 100 mtrs it will pick up the price relating to that from the condition record which is belongs to the Material 1
    I hope it will help you
    Regards,
    Murali.

  • Process flow in Process industry

    Hi PP Gurus,
    I want to have an idea about flow of process order in process industry with the details how the cost are captured per day if the process order continues for many days.
    Pl guide me in the process
    Thanks in advance
    Shanmugam Balamurugan

    Important Things Involved:
    O10C --- Control Recepie Destination (Clubbing of recurring PICs)
    O12C --- Process Instruction Category (PICs) -- Clubbing of Process Instruction Chars to be displayed
                                                                          as per requirement on PI Sheet.
    O13C --- Process Message Category --- After we have recorded the Enteries in PI sheet, If we need to update some ABAP/ Z table or We need to Trigger some program with those values then mapping for that is done here.
    BOM:CS01
    Resource:CRC1
    Master Receipe:C201
    Production Version:C223
    PI Characteristics:Ct04/O25C
    PP Process Flow:Cr01>Co53>co60/co55/co64/co67-->CO57
    SOP:MC84>MC81>mc76>mc75>md63
    Demand Management: MD61>MD02>MD04-->Cor1
    MRP Run: MD02,MD04

  • Synchronous process integration scenario with PI 7.1

    Hi all,
    Iu2019m trying to create a process integration scenario which contains two actions. Both actions use the same synchronous interface to a web service which takes some parameters and returns a value. When I check the configurability it displays the errors:
    Connection from Action1 to Action2 has no outbound interface
    Connection from Action1 to Action2 has no inbound interface
    and the warning:
    Connection from Action1 to Action2 has no mapping
    I first assigned the service interface as outbound interface to Action1 and inbound to Action2. Next I tried to assign the interface in- and outbound to both actions, but this didnu2019t change anything on the message. The same scenario with the interface set to asynchronous seems to be valid (but looses the return value of course).
    Can anyone give me a hint what Iu2019m doing wrong? Is there any special consideration for synchronous communication which doesn't apply for asynchronous services?
    Regards,
    Tarik

    Deleting and recreating the actions and service interfaces exactly the same as they were before solved the problem. Seems as if changes in the interface objects sometimes are not activated correctlyu2026

  • Configuring Process Integration Scenarios for Advanced Adapter Engine

    Hello @all,
    i've an asynchronous SOAP scenario and would like to configure an integrated configuration for Advanced Adapter Engine using a process integration scenario. In the documentation (Link below) it is described, that you can select local communication using AAE in the model configurator, but I couldn't find any hint. Any idea?
    Documentation:
    http://help.sap.com/saphelp_nw73/helpdata/en/48/ce987b18d3424be10000000a421937/content.htm
    Thanks and kind regards
    Andreas

    Hi,
    Use thse links:
    Advanced Adapter Engine Configuration in PI 7.1
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/700058f0-b1a1-2a10-39a8-ab2627b87cfa?QuickLink=index&overridelayout=true&47047071760975
    Sreeni.

  • Process extension scenario patch problem

    Hi,
    in my solution I had extension fields and one extension scenario. After I successfully deployed solution new requirement came - this extension field should also be available via "this" web service. So I created a patch and when I wanted to thick checkbox before that web service in process extension scenario and try to save it, it gave me following error.
    I tried to create another process extension scenario that includes just missing web service, but looks like extension field can have only one process extension scenario.
    Help, advice?

    Hi, Horst.
         We can directly create a new down payment from an existing Sales Order.
         So, it means there must be some way they are connecting.
         And I still think that "SalesOrder -General Information to Invoice Request-General Information" scenario is the one to use. (fully pregnant )
    I think Down Payment is just an invoice because it doesn't have its own BO and the down payment screen can be enhanced through CustomerInvoiceRequest BO.
    Regards,
    Fred.