Purchase Order Cancellation/Deletion

Dear SAP Gurus,
I would appreciate if any of you could advise me the best way to handle the below specific scenario.
A PO is created based on a PR. It has been released an approved. No GR/IR has been created.
How do I cancel this PO (regardless whether there is only one item or more? I suppose it cannot be deleted at all from the system.
I would do the following.
1. Cancel the release
2. Update the line item(s) price to 0.01
3. Delete the line item(s) (Trash bin). Save PO
4. Go to PR. Block the PR and close it.
Detailed steps would be very much appreciated.
Also, what would the process be when there is already GR/IR posted against the PO?
Regards,
Jonathan

Hi,
I m losing hope now.
Can u plz tell me about that cancellation date option why it is not working and how that guy said that this is working on his system.?
I cannot undersand why?
And also i checked the second way as you suggested to select open Purchase Order in Open Item List. But you can close one P.O. at one time not multiple by selection.
Regards,
Ravi

Similar Messages

  • Send SRM Purchase order Cancellation request to Vendor using SAP PI

    Hi gurus,
    We have to build an interface to send Purchase order cancellation request to vendor once the PO is deleted in SRM using PI.
    Could some one please send me out a document to set up this interface.
    Thanks in advance for your help.
    Regards,
    Catherine

    Hi Catherine,
    did you get any chance to go through the below links.
    Purchase Order from SRM to SUS ( Supplier Self Service )
    PO from SRM to supplier via PI 7.1 | SCN
    Thanks,
    Naveen

  • I created a purchase order and deleted it.

    I created a purchase order and deleted it.
    when i query the purchase order even in history table the PO is not avaialble. why?
    The table i queried
    In release r12
    SELECT *
    FROM apps.po_history_all

    Your po archive is probably be set to Archive on "approval" or "communicate".
    Since you deleted the po before approving, it never got archived.
    Check your document types in PO Setup menu.
    Hope this helps
    Sandeep Gandhi
    Omkar Technologies Inc.
    Independent Techno-functional Consultant
    513-325-9026

  • Auto Purchase Order Cancellation

    Dear Experts,
    If it is possible of Auto Purchase Order Cancellation after a decided date?
    I tried it with  Purcahse Order> Accounting Tab > Cancellation Date.
    My posting date of P.O. was 13-01-2012 and Cancellation Date was 14-01-2012.
    But P.O. has not been cancel yet.
    if there is any other workaround then plz suggest or I am missing something in procedure.
    Thanks in Advance.
    Regards,
    Ravi

    Hi,
    I m losing hope now.
    Can u plz tell me about that cancellation date option why it is not working and how that guy said that this is working on his system.?
    I cannot undersand why?
    And also i checked the second way as you suggested to select open Purchase Order in Open Item List. But you can close one P.O. at one time not multiple by selection.
    Regards,
    Ravi

  • Tcode for Purchase Order Cancellation?

    Tell me the tcode for purchase order cancellation and in which tcode to view the cancelled POs.?

    hi vinaya,
    Use T-Code Me 22N for Cancellation of PO
    =>  Select the document to be cancelled by clicking the icon ‘other PO’.
    =>  Select the item to be cancelled in the item overview.
    =>  Click the cancel icon on the screen(dustbin icon) .
    =>  Save the PO again. The item will continue to appear in the screen but with a    dustbin icon attached. No document can be posted referring this PO / line item.
    Regards,
    Naveen

  • Purchase Order cancel

    Dear All Experts,
    My problem  is to cancel Purchase Order and Payment document. Details are as below.
    Prepared Purchase Order using Capital Order ( i.e used Capital Budget in this PO)
    Prepared Down Payemt Request and payment made to the vendor.
    Bank Reconciliation has been done.
    Now somehow , we want to cancell Purchase Order. So Vendor has given Payment back in next month which we have paid to him.
    Payment received entry made.
    Now i want to cancel Payemnt voucher and also cancel Purchase Order to make my capital budget free. i want to make budget amount free which is used in Purchase Order .
    What is a way out for this problem. How to received budgeted amount back which i have used in Purchase Order.
    Regards
    Swati Shah

    Dear,
    If you go to the payment document and double click on the bank line item you can see the clearing document number, this document number is from BRS. So first, you have to delink this document number with the payment document number. Go to FBRA and put the payment document and choose reset option which will delink the clearing document number, if error pop up then give the clearing document number and try.
    But try a work around for BRS, because as this entry will effect the statement in GL balances. If you want to do BRS again then you need to reverse all those documents so that this entry will not be recorded again for clearing.

  • Purchase Order (PO) delete

    sir,
    how Purchase order (PO) can be deleted.
    Regards,
    Praveen

    Hi,
    You can select purchase order line items in change mode ME22N of PO & delete.
    Rgd,
    Chetan

  • How to do form personalization on purchase order cancell functionality

    Hi,
    how to make form personalization on purchase order form so that user should not cancell the PO.
    Please suggest.
    Thanks

    This is already available in the additional line information..though..
    If you still want that at line level to be displayed..maybe you need to customize the form...not sure how u can handle that logic
    Mahendra

  • Purchase Order Item deleted; purchase requsition quantity not update

    Hello,
    We have PR-20025224 item 130 the quantity ordered is 200 on 2 PO 4200039509 and 4200083799 (100 each)
    One of the PO (4200083799) is deleted (No GR)so the quantity ordered should be 100 only in the purchase requisition u201CStatusu201D tab.
    Normally the program RM06HL04 should correct the quantity ordered but it does not.
    In the status tab in purchase requistion details are as below
    Proc Status:- B PO Created
    Block ID - Not Blocked
    Ord Qty - 200
                 - 05 Relese Completed
    Thanks to help me in this issue.

    Hello Jurgen,
    Thanks a lot for the reply.
    I checked the deleted PO, in "Delivery Schedule" tab at right end the last column is "PReq Closed" and it is blanked.
    Actually the client need is, once the PO deleted, in the purchase requistion "Status" tab "Ord Qty" gets changed (In this case it should reduce by 100 no from 200 nos, because other PO is for 100 nos)
    But PR Ord Qty does not changed.
    Is it possible that, the PR quantity gets changed once PO deleted?
    Thanks for the reply and hep.
    Hemant

  • Regarding purchase order header deletion flag indicator

    hi all,
    Right now in SAP PO header deletion flag has been set to X.
    so what i need is the PO should be flagged only at item level .
    how can i proceed?where can i find the deletion flag in the transaction screen?

    You can find in item overview (RM06E-LOEKZ)

  • Reg:purchase order header deletion flag

    hi all,
    right now in SAP PO header deletion flag has been set to X.
    so what i need is the PO should be flagged only at item level .
    how can i proceed?where can i find the deletion flag in the transaction screen?

    Hi,
    To set deletion flag at PO item, select the item and click on delete icon (a garbage bin).
    Cheers.
    ...Reward if useful.

  • Cancellation of purchase order

    Hi all
    how can i cancel purchase order & how can i check document flow of purchase order.how can i checked for particular PO good receipt happend or not if its happen how can we cancell whole document.
    regards
    ajit

    how can i cancel purchase order
    Cancellation means you do not want to receive the material from that Vendor, that means no GR & No IR should happen.
    for that You need to Select the Line Item & put Block / deletion indicator.
    & how can i check document flow of purchase order.how can i checked for particular PO good receipt happend or not if its happen how can we cancell whole document.
    If you do any GR/IR then there will be Purchase order History tab at PO Line Item level, you can find the Mat Doc number & Invoice Number .and if you want to cancel the Material Document , you can do it through MIGO or MBST.

  • Purchase Order deleted by mistake

    Hi all,
    We have a purchase order that was deleted by accident.  We we wanted to remove one of the line items and it set the whole purchse order for deletion.  Is there a way to undelete a purchase order?  Thanks all for your help and let me know if I need to clarify anything.
    Regards,
    Victor Lam

    I am not sure how it initially happened.  I was able to recreate it in our test client.  I created a purchase order and deleted the line item.  I then ran program RM06EV47 to set the deletion flag for the PO.  We are trying to reverse it.  SAP Support recommended writing a program to reverse this, but we were looking for way to do it with out making a new program.

  • Deleted Purchase Orders

    Deleted Purchase Orders
    Posted: Dec 30, 2009 1:34 AM Edit Reply
    Hi,
    We are working in Oracle Applications 11i. A user has complained that 4 purchase orders do not exist in the reports. I have checked the database table po_headers_all and there are no records with the desired segment1 numbers. My guess that these purchase orders were deleted from the application interface. Any other suggestions?
    So, I have two inquiries:
    1. is there any table that contains archived purhase orders or historical information where i can find the missing information?
    2. how can i disable the DELETE priviledge from the Purchasing users or responsibility and from the Purchase Orders form POXPOEPO ?
    Any help in this matter will be appreciated..

    Hi AHS;
    Please check [this link|http://www.oracleappshub.com/posts/23/blog/understand-8220drop-shipment8221-in-order-management-part-ii-oracleapps-epicenter/] and also check [this thread|http://forums.oracle.com/forums/thread.jspa?messageID=2507389&#2507389] for priviliege and see its helpful
    Also check:
    http://download.oracle.com/docs/cd/B11454_01/11.5.9/acrobat/po115ug.pdf
    http://download.oracle.com/docs/cd/A60725_05/pdf/poug.pdf
    Regard
    Helios

  • Purchase Order Allowed to Modify After Material Posting and Invoice

    Hi Experts,
    Why do SAP allows the scenario to change the Purchase Order once Material Document is posted and Invoice is Created unlik Sales Order? Do we have any business scenarios reagarding allowing the PO change?
    Thanks for the Clarification. Hopefully I will be enlightened by SAP's behavior in the Purchasing Process.

    Hi Cecilio,
    PO is changable even after GR and IR has been completed. If the invoice has been received or the goods have been paid for, and your intended change affects the price, the change will be ineffective.
    Please refer to the Online documentation, MM Purchasing -> Purchase Orders -> Changing, Cancelling, and Blocking Purchase Orders.
    Also if you want to delete the PO, when all the procurement process is finished, it must be possible to delete the PO item for archiving purpose for example.
    You can see the on-line help on that matter:
    "You cancel items in a purchase order by deleting them. Please note that an item may only be deleted if it is closed (that is
    to say , there is no outstanding quantity to be delivered or invoiced). Items are regarded as closed if, for example:
    · the ordered quantity (or more) has already been delivered
    · the ordered quantity has been invoiced in full
    · no related follow-on processes (such as reservations) are active
      in the stystem."
    Hope this can help